Report for February 2019
- Report Date
- February 2019
Report compiled by Chris Lawford (Programme Manager) for Alex carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Key Achievements in Last Period
- EDW Embed & Optimise project in progress, handed over to replacement project manager.
- Talend Implementation project in progress, handed over to replacement project manager
- Talend environments built.
- Talend Training started.
Top Issues
- Some delays in Embed & Optimise project, re-planning exercise in progress.
- Additional budget required to complete Talend Implementation.
Key Next Steps
- Monitor progress on inflight projects, prepare for project closures and support project managers.
- Prepare for programme closure.
- Secure budget needed to complete the programme (this has now been done, hence the green RAG status).
Overall the programme is reporting GREEN.
Status and Forward Look
(see programme financials)
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||||||||||||||
DTI005 - ETL Tool Implementation Discretionary Milestones 01-Mar-2019 Acceptance Sign-off (ASOR) 08-Mar-2019 Project Delivery 22-Mar-2019 Project Closure RAG AMBER |
Report by Andy Stewart for Feb 2019 Achievements in Last Period
Top Issues
Key Next Steps
Overall, the project is reporting AMBER due to budget concerns.
|
||||||||||||||||||||
DTI021 - EDW Embed & Optimise
Discretionary Milestones:
RAG: AMBER |
Report by Anne Mathison for February 2019 Achievements
Issues
Next Steps
The project is reporting AMBER. Revised Budget and milestones have been revised; however, due to the lack of contingency - it will remain at amber |
Section Four: Closed or Withdrawn Projects
DTI003 Withdrawn
DTI004 ETL Procurement has now been closed.
DTI006 EDW Implementation has now been closed.
DTI019 BI/MI Analysis toolkit has now been closed.
COM029 Proof of concept project has now been closed.
DTI022 Business Engagement has now been closed.
Attachment | Size |
---|---|
![]() | 16.95 KB |