Report for August 2017
- Report Date
- August 2017
Report compiled by Chris Lawford (Programme Manager) for Alex carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
DTI004 - ETL Tool Procurement
- Market Research phase completed.
- We are in the process of agreeing the procurement strategy. This will shape the remainder of the project.
Once the strategy is decided the remainder of the project can be accurately assessed for scope and planning.
DTI006 - EDW Implementation.
- Security policy draft completed and under review.
- Technical architecture design in progress.
- Org/Hierarchy subject area design in progress.
DTI019 - MI/BI Analysis Toolkit
- Analysis work underway.
DTI022 - EDW Business Engagement
- PM assigned 30/08.
- Project planning underway.
Status and Forward Look
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
DTI005 ETL Tool Implementation |
Planned to start Dec-17 | |
DTI021 EDW Embed & Optimise |
Planned to start Jan-18 |
|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||
DTI004 - ETL Tool Procurement Discretionary Milestones 11-Aug-2017 ITT Issued 08-Nov-2017 Project Delivery 23-Nov-2017 Project Close RAG AMBER |
Report by Nick Graham for August 2017 Achievements in Last Period
Issues
Next Steps
The project is reporting AMBER. Issue - market evaluation has taken c 8 weeks longer than planned, and Procurement have advised an open ITT strategy should be followed. Subject to Programme Board confirming this strategy, the remaining project activities will then be replanned and scheduled in light of this. No SMT action required.
|
||||||||
DTI006 - EDW Implementation Discretionary Milestones 21-JUL-17 Planning Complete 29-SEP-17 Design Phase Complete 24-NOV-17 Org Hierarchy ASOR 06-DEC-17 Infrastructure Build Complete 08-DEC-17 Deployment 12-JAN-18 Project Close RAG GREEN |
Report by Chris Lawford for August 2017
Achievements in Last Period
Issues
Next Steps
The project is currently reporting GREEN.
|
||||||||
DTI019 - BI/MI Analysis Toolkit Discretionary Milestones
RAG GREEN |
Report by Sue Woodger for August 2017 Achievements in Last Period
Issues
Next Steps
RAG Commentary: n/a |
||||||||
DTI022 - EDW Business Engagement Discretionary Milestones 15-SEP-17 Planning Complete 22-DEC-17 Project Delivery 14-JAN-17 Project Close RAG AMBER |
Report by Chris Lawford for August 2017
Achievements in Last Period
Issues
Next Steps
The project is reporting AMBER, until planning review submitted. |
Section Four: Closed or Withdrawn Projects
DTI003 Withdrawn
COM029 Proof of concept project has now been closed.
Attachment | Size |
---|---|
![]() | 28.4 KB |
![]() | 36.02 KB |