Report for September 2017
- Report Date
- September 2017
Report compiled by Chris Lawford (Programme Manager) for Alex carter (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Key Achievements in Last Period
- EDW Security Policy complete
- Technical Architecture Design complete
- ETL Tool procurement strategy decided (Open mini-tender)
Top 3 issues
- 17/18 Programme budget not approved. ETL ITT cannot be issued.
- Approval of governance for budget changes for ETL tool procurement.
- Re-plan of EDW build, following agreement on technical architecture.
Key Next Steps
- Return of AMBER projects to GREEN, via governance approvals.
- EDW DEV build.
- Issue of ETL ITT
- End of planning stage for EDW Business engagement, beginning of execution phase.
- Delivery of BI/MI Analysis Toolkit.
Status and Forward Look
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary | |
---|---|---|
DTI005 ETL Tool Implementation |
Planned to start Dec-17 | |
DTI021 EDW Embed & Optimise |
Planned to start Jan-18 |
|
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||
DTI004 - ETL Tool Procurement Discretionary Milestones 11-Aug-2017 ITT Issued 08-Nov-2017 Project Delivery 23-Nov-2017 Project Close RAG AMBER |
Report by Nick Graham for September 2017 Achievements in Last Period
Issues
Next Steps
The project is reporting AMBER. Issues - Market engagement, procurement strategy & ITT production have over-run, leading to overspend. Re-costed and re-scheduled plan for completion approved by stakeholders was submitted to WIS for authorisation 29th Sept and then overwritten. Re-submitted to WIS for 6th Oct. Approval will return project to GREEN. No further SMT action required.
|
||||||||
DTI006 - EDW Implementation Discretionary Milestones 21-JUL-17 Planning Complete 29-SEP-17 Design Phase Complete 24-NOV-17 Org Hierarchy ASOR 06-DEC-17 Infrastructure Build Complete 08-DEC-17 Deployment 12-JAN-18 Project Close RAG AMBER |
Report by Chris Lawford for September 2017 Achievements in Last Period
Issues
Next Steps
The project is currently reporting AMBER, until such time as the project has been re-planned and approved.
|
||||||||
DTI019 - BI/MI Analysis Toolkit Discretionary Milestones
RAG GREEN |
Report by Sue Woodger for September 2017 Achievements in Last Period
Issues
Next Steps
RAG Commentary: n/a |
||||||||
DTI022 - EDW Business Engagement Discretionary Milestones 15-SEP-17 Planning Complete 22-DEC-17 Project Delivery 14-JAN-17 Project Close RAG AMBER |
Report by Geoff Cropley for September 2017
Achievements in Last Period Initial kick-off session held confirming approach objectives and deliverables. Further refinement of activities is continuing will be agreed at the next workshop to be held on 3rd October. Project planning is expected to complete with Asta and project brief submitted by 13th October 2017. Issues
Next Steps
The project is reporting AMBER, until planning is complete. |
Section Four: Closed or Withdrawn Projects
DTI003 Withdrawn
COM029 Proof of concept project has now been closed.
Attachment | Size |
---|---|
capture1.png | 28.29 KB |
capture2.png | 35.85 KB |