Report for March 2021

Report Date
March 2021

Report by Muriel Mewissen for Gavin McLachlan (Programme Owner) and Stephen Roy (DTI Portfolio Manager).

 

Section One: Programme Commentary, RAG and Resources Update

During March, one project was successfully completed:

The follow on project started on 26 March:

Therefore, the status of the programme is set to GREEN.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Programme RAG Overview & Forward Look - March 2021

 

Programme Resource to end of March 2021

NB: The programme budget increases by 61 days, up from 191 days following start of new project DTI057, see PRICCL 6.

 

Section Two: Projects Not Started

No further project due to start in 2020/21.

 

Section Three: Projects in Progress

Project Info Project Managers Commentary
DTI054 Large Events Platform

 

Milestones
Target Date Title
05-Mar-2021 Project Closure

 

RAG Status

Closed

Report by Muriel Mewissen for March 2021

Achievements in Last Period

  • Project was formally closed on 5 March.
  •  The Closure Report is available

Top Issues

  • None

Key Next Steps

  • None

DTI057 EventsAir - Embed and Optimise

 

Milestones

Target Date Title
03-May-2021 End of Planning

 

RAG Status

GREEN

Report by Andy Stewart for March 2021

Achievements in Last Period

  • Project formally approved to start 
  • Project planning phase commenced 
  • Meeting scheduled with governance group on 12th April to review project scope
  • Initial investigation has commenced regarding the feasibility of integrating with the SRS CRM system 

Top Issues

  • A number of accessibility related concerns have been raised by the Accessibility Officer 

Key Next Steps

  • Complete planning phase 
  • Commence project activity 
  • Follow up on reported accessibility concerns 

 

Section Four: Closed Projects

Project Programme Manager's Commentary
DTI054 Large Events Platform This project was started in June 2020 and was closed on 5 March 2021. The Closure Report is available to view.
DT055 Unibuddy Procurement This project was started in June 2020 and was closed on 17 December 2020. The closure report is available to view.
DTI056 Virtual Visits This project was started in July 2020 and was closed on the 4 December 2020. The closure report is available to view.
DTI053 Online and Digital Events Service This project was started in May 2020 and was closed on the 18 September 2020. The closure report is available to view.
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No