Report for March 2017

Report Date
March 2017

Report compiled by Doug Laurence, IS Apps Programme Manager for Martin Morrey  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

Commentary

Overall Programme RAG:

 

Forward Look and RAG

 

Resource Position

 

Section Two: Projects Not Started

Project Info Project Manager's Commentary

DTI012

User Centred Portal Proof of Concept

Scheduled to commence after completion of DTI011. Expected to be 1st August 2018

 

Section Three: Projects in Progress

Project Info Project Manager's Commentary

WEB009

Responsive MyEd and EdWeb Integration

Discretionary

Milestones

14-Apr-2017 Phase 2 Acceptance Review
25-Apr-2017 Phase 2 Deployment
09-May-2017 Phase 2 Deployment Review
De-scope Phase 3 Improved alignment between MyEd and EdWeb
23-May- 2017 Closure

RAG Status

AMBER

Report by Karen Stirling for March 2017

Achievements this period

  • Commencement of internal UAT and also UAT being completed by channel owners
  • Load testing completed
  • On-going resolution of  JIRAs

Issues

  • Project activity has been restricted over the past 2 weeks due to technical issues impacting Bamboo Service, key project resource has been allocated to this activity therefore no progress with resolving outstanding project JIRAs.
  • User Acceptance testing has been on-going however issue with functional accounts not resolved due to developer availability has limited the amount of UAT that can be undertaken.
  • Channel owners are being chased to completed remaining testing, where possible
  • Project has also been impacted by availability of key IS Apps and LTW resource who are also aligned to DTI project activities this has been raised with Project Sponsor and DTI Programme Owner
  • Due to the impact of delays the project will have to review and revise project milestones targeting the week commencing 24th April for deployment to live on proviso all key project resource (LTW and IS Apps) are available to cover deployment activities
  • Business team resource availability to complete meta tags development work
  • Request issued to Project Sponsor to agree to remove phase 3 improved alignment between MyEd and EdWeb from project - waiting for response for PICCL to be raised

Next Steps

  • IDM Connector activity
  • Resolution of outstanding JIRAs
  • Meta Tags development complete
  • UAT completed and Acceptance Sign off
  • Pre Live deployment activity
  • Deployment to Live

The project status is currently AMBER due to technical issues impacting deployment of code to test environment unable to progress JIRAs until resolved.

 

DTI011

User Centred Portal Pilot

Discretionary

Milestones

Target Datesort descending Title
18-Apr-2017 Planning
31-Jul-2017 Delivery 1
30-Nov-2017 Delivery 2
28-Feb-2018 Delivery 3
31-Jul-2018 Delivery 4
31-Aug-2018 Embedding
14-Sep-2018 Closure

RAG Status

Amber

Report by Doug Laurence for March 2017

 

Achievements in Last Period

  • Completion of Initiation Stage Tasks
  • Agreed Scope for Pilot with Service Excellence
  • Collaborative Space secured on Floor F, Argyle House
  • Successful completion of March 17 DTI Programme Board
  • Resources Secured for Planning Stage
  • Initial Product Backlog populated
  • Initiation of collaboration with UX Programme
  • Initiation of collaboration with APIs Programme

Issues

  • Resources assigned for Planning Phase have not been able to provide requested time. Progress is, however, continuing with no lasting affect expected.

Next Steps​

  • Planning Stage Tasks

The project status is currently Amber due to resourcing for both the planning phase and future delivery.

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
WEB010 Project Closed 10-Mar-2017

 

Notes from Programme Meeting

Note Action Status