- Report Date
- May 2017
Report compiled by Doug Laurence, IS Apps Programme Manager for Martin Morrey (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
Overall Programme RAG:
Forward Look and RAG
Resource Position
Section Two: Projects Not Started
Project Info |
Project Manager's Commentary |
DTI012
User Centred Portal Proof of Concept
|
Scheduled to commence after completion of DTI011. Expected to be 1st August 2018 |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
WEB009
Responsive MyEd and EdWeb Integration
Discretionary
Milestones
RAG Status
AMBER
|
Report by Karen Stirling for May 2017
Achievements this period
- UAT in progress with channel owners
- IDM Connector testing still to be completed
- On-going resolution of JIRAs
- Meta Tags development completed and being tested
- Pre Live activity under way
Issues
- The project UAT has still to be completed and signed off - this has been due to delays in meta tags development work being completed by LTW resource ready for testing, availability of business resource to complete IDM connector testing
- There are a number of Channel owners who have not completed testing - this is with Service Owner and Project Sponsor to progress sign off
- There is the potential risk of testing not being completed and readiness for deployment to live due to key LTW resource not available due to attendance at overseas conference
- Should there be any development work required the key project developer is on leave for 2 weeks and only returns on week the project is due to deploy to live
- Project has also been impacted by availability of key IS Apps and LTW resource who are also aligned to DTI project activities this has been raised with Project Sponsor and Programme Owner
- Project budget has been further impacted by delays, Project Sponsor has confirmed funding available from DTI re-estimation in progress
Next Steps
- Resolution of outstanding JIRAs
- UAT completed and Acceptance Sign off
- Pre Live deployment activity completed
- Deployment to Live
The project status is currently AMBER due to User Acceptance testing not completed and signed off , key project resource not available and project budget requires to be revised
|
DTI011
User Centred Portal Pilot
Discretionary
Milestones
RAG Status
Amber
|
Report by Doug Laurence for May 2017
Achievements in Last Period
- Project Brief approved by WIS.
- Team Day held.
- Technical Lead (Mairi)'s time confirmed.
Issues
- Technical Lead (Mairi Fraser) allocation is not confirmed
- Co-Location Space is not being fully utilised
- Change in Planning Milestone
- Change to UX Resourcing
- Senior Supplier Meetings are not being held
Next Steps
- Ensure feedback from Martin and Marissa's visits to University of Wisconsin and Open Apereo Conference are fed into project
- Progress with Research deliverables for next milestone
- Interns deliver first presentation
- Confirm new UX Resource
The project status is amber due to issue regarding impact of UX Resourcing which is being recruited.
|
DTI020
Notifications Service - Rollout, Integrations and Subscribers
Discretionary
Milestones
RAG Status :
GREEN
|
Report by Karen Stirling for May 2017
Achievements in last period
- Project Manager Assigned
- Project website and ASTA TR code created
- Initial kick off meeting with Project Sponsor, new Service Manager, Service Owner and Programme Manager to start mapping out project brief
- Initial engagement with L&UC and USD
- Initial kick off meeting with IS Apps to understand previous projects WEB007 and WEB010
- Request issued to Apps Resource manager for development resource to review outstanding JIRAs from previous projects
- Draft project brief in progress
- Meeting held with MVM to understand their requirements for Learn Announcements
- Initial engagement with Procurement for New SMS Subscribers work package
Issues
- Project dependencies need to be understood - diagram produced to aid discussions
- Risk around Development team resource as key developer is aligned to DTI Enterprise APIs project
- Potential for resource days allocated in 16/17 not to be spent
Next steps
- Engagement with Corporate and Timetabling colleagues
- Planning work packages, estimation and resource allocations
- Complete project brief and sign off
- Commence work package 1 to rollout service
The project status is currently GREEN
|
Section Four: Closed or Withdrawn Projects
Project Info |
Project Managers Commentary |
WEB010 |
Project Closed 10-Mar-2017 |
Notes from Programme Meeting