Report for January 2018
- Report Date
- January 2018
Report Date
31st January 2018
Report compiled by Alison Armstrong (User Experience Programme Manager)
for Neil Allison, Stratos Filalithis, Lisa Dawson, Colan Mehaffey, and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
- DTI009 - Define User Experience Service project continuing as planned
- DTI009 -The revised budget proposal has now been received and approved. Colan and Neil to work on the longer-term sustainability plan, e.g., via production of a proposal for ISG Planning Round funding (submitted through LTW) beyond the life of the User Experience programme to cover the period from 2019/20 onwards.
- It was agreed that UX programme recruitment activity (beyond initial job grading which is currently ongoing) could continue with a view to having the UX roles in place within the final quarter of FY 2017/18.
-
DTI009 - work is well underway on potential case study "pilots" to prove the service model, this includes the production of UX (primarily user research) insight support for the EDW, BI Tools, and Enterprise APIs programmes. The work is on schedule for completion by Mid-March 2018.
-
Existing contract UX resource (Magdalena Tsiobanelis) completed her contract on 31st January 2018 as planned.
-
DTI0010 - project now completed and closed.
-
Agreed that project would close on completion of case studies and the evaluation work with the latter due to complete in March.
- Overall the User Experience Programme is now GREEN at this point in time.
DTI009 – GREEN
DTI010 – project completed and closed on 3rd November 2017.
RAG & Forward Look
Resources to end of January 2018
Section Two: Projects Not Started
N/A.
Section Three: Projects in Progress
Project Info |
Project Managers Commentary |
||||
DTI009
Category: Discretionary Milestones
RAG Status GREEN |
Report by Sue Woodger for January 2018 Achievements in Last Period
Issues
Next Steps
Project is GREEN as revised dates have been approved by WIS |
Section Four: Closed or Withdrawn Projects
Project Info |
Project Managers Commentary |
DTI007 EdGEL as a Service Category: Discretionary |
Project closed 28 July 17. Some items require follow up in 17/18 and these are detailed in DTI007 Deliverables tracker |
DTI008 EdGEL Technology Delivery and Transition to Business As Usual Category: Discretionary |
Project closed 28 July 17. Some items require follow up in 17/18 and these are detailed in DTI008 Deliverables tracker |
DTI010 Digital Experience Standards Category: Discretionary |
Project closed 3 November 17. |