Report for February 2018
- Report Date
- February 2018
Report Date
28th February 2018
Report compiled by Alison Armstrong (User Experience Programme Manager)
for Neil Allison, Stratos Filalithis, Lisa Dawson, Colan Mehaffey, and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
- DTI009 - Define User Experience Service project continuing as planned
- Recruitment of the new UX programme roles, i.e., UX Lead and UX Juniors is taking considerably longer than anticipated, despite chasing, completion of the initial job grading by HR has been pending since the Autumn. It now looks increasingly unlikely that the UX roles will be in place within the target timescale of the final quarter of FY 2017/18. Other interim options to cover the resourcing gap are being considered to maintain service continuity.
-
DTI009 - work is nearing completion on case studies based on work completed to-date for DT & SEP to prove the service model. This work included the production of UX insight support (primarily user research) for the BI Tools, UCP, and Enterprise APIs programmes. The case studies work and write-up is on schedule for completion by late March 2018. The case studies will be uploaded to a new User Experience Services website due for launch by early April. The site will feature information about the services available via the programme and the case studies, along with signposting for further information.
-
A User Experience Showcase event has been scheduled for 4th April to help raise awareness of the programme, what it has achieved to-date and the UX support available, and to promote engagement with key stakeholders. Joe West, the shared Communications Officer for DT has been briefed, and Neil and Joe have discussed the communications approach and support required for the event and the programme. An email with the event details was issued to IS Apps Project Services team on 26th February, an article on the event has also been published on the Digital Transformation Sharepoint area. The User Experience Services website will be launched to coincide with the showcase.
-
Agreed that DTI009 project would close on completion of case studies and the evaluation work on 9th April.
-
It has been agreed that a new "Embed and Optimise User Experience Services" project will be set up to focus on planning, i.e., for ongoing management and rollout of the service and longer-term sustainability. Initial groundwork on the plan will be progressed within DTI009 prior to closure.
-
The UX Steering Group meeting is on 4th April to align with the review and closure of the DTI009 project, and to agree next steps, objectives and scope for future projects including the proposed new Embed & Optimise the User Experience Services project.
- Overall the User Experience Programme is GREEN at this point in time.
DTI009 – GREEN
DTI010 – project completed and closed on 3rd November 2017.
RAG & Forward Look
Resources to end of February 2018
Section Two: Projects Not Started
N/A.
Section Three: Projects in Progress
Project Info |
Project Managers Commentary |
||||
DTI009
Category: Discretionary Milestones
RAG Status GREEN |
Report by Sue Woodger for February 2018 Achievements in last period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info |
Project Managers Commentary |
DTI007 EdGEL as a Service Category: Discretionary |
Project closed 28 July 17. Some items require follow up in 17/18 and these are detailed in DTI007 Deliverables tracker |
DTI008 EdGEL Technology Delivery and Transition to Business As Usual Category: Discretionary |
Project closed 28 July 17. Some items require follow up in 17/18 and these are detailed in DTI008 Deliverables tracker |
DTI010 Digital Experience Standards Category: Discretionary |
Project closed 3 November 17. |