- Report Date
- June 2017
Report Date
30th June 2017
Report compiled by Alison Armstrong (User Experience Programme Manager)
for Neil Allison, Stratos Filalithis, Lisa Dawson, and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
- DTI007 - Engagement strategy initiation deliverable completed 12 June
- DTI007 - Create a defined EdGEL process deliverable completed 13 June
- DTI008 - EdGEL Compliance Audit completed, and technical investigation to confirm project resource estimates completed
- DTI008 - Initial Design model created and checked
- DTI009 - Proposing a defined UX service deliverable completed and signed-off
- DTI009 - Establish cycle of User Experience training deliverable has been scheduled to start from 17th July
- IS App DT Lunchtime Seminar on User Experience held on 19th June
- User Experience programme showcase session held on 27 June - successful in gathering feedback to inform future planning, e.g., for 17/18
- EdGEL Steering Group held on 28th June - sign-off of two more UX deliverables completed to-date, and analysis of proposed new User Experience team composition and requirements
- User Experience Steering Group held on 30th June - reviewed programme progress
- Communications and engagement meeting for User Experience service scheduled for 5th July
- DTI010 Deliverable walk-through scheduled for 4th July
-
Overall the User Experience Programme is GREEN at this point in time, and on track.
DTI007 – GREEN
DTI008 – GREEN
DTI009 – GREEN
DTI010 – GREEN
RAG & Forward Look
Resources to end of June 2017
Section Two: Projects Not Started
N/A.
Section Three: Projects in Progress
Project Info
|
Project Managers Commentary
|
DTI007
EdGEL as a Service
Category: Discretionary
Milestones
RAG Status GREEN
|
Report by Sue Woodger for June 2017
Achievements
- The milestone ‘Engagement strategy initiation’ was due 7 July but completed early on 12 June. This has two deliverables:
- O2 D1 Engagement : Output DTI007 O2D1-GEL Engagement-2017-05-29.docx (includes summary of engagement and Insights)
- O2 D1 Engagement : Output DTI007 O2D1 GEL Hackathon Proposal-2017-04-21.docx
- It should also be noted that Engagement activity will be ongoing.
- The deliverable ‘A defined EdGEL process’ was completed on 13 June. The output was a document entitled DTI007 O1D1-GEL Processes-2017-06-07.docx which summarised proposals for the GEL platform, assessment, development process, triage, backlog and Standards
Issues
- The departure of the Digital Design Consultant on 2 June 2017 has impacted the deliverables across all projects and the project sponsors are feeling this impact and acknowledge that delays are happening, pushing many deliverables into July and they are reprioritising some deliverables to help with these delays.
Next Steps
- Continue progressing completion of remaining deliverables
- Complete review of design proposals for changes to the EdGEL website
- Complete review of the existing interaction style guide
- Review of requirements to facilitate 17/18 planning
RAG Commentary N/A
|
DTI008
EdGEL Technology Delivery and Transition to Business As Usual
Category: Discretionary
Milestones
RAG Status GREEN
|
Report by Sue Woodger for June 2017
Achievements
- Consultant was on site 27-28 June to input into O1 D4 Code store by way of a review and proposals
- The deliverable ‘O2D1 Key principles for using and contributing to EdGEL’ was approved by the project team and the EdGEL Steering group on 28 June. This has led to the completion of the milestone ‘Guidelines for contributing to and using EdGEL’
- The deliverable ‘O1D5 EdGEL Compliance dev work’ development work was completed at the beginning of June but there were some outstanding jiras. All jiras have now been closed so the deliverable is complete.
Issues
- The departure of the Digital Design Consultant on 2 June 2017 has impacted the deliverables across all projects and the project sponsors are feeling this impact and acknowledge that delays are happening, pushing many deliverables into July and they are reprioritising some deliverables to help with these delays.
- The Technical Lead was on leave and on return was diverted to live issues in WEB009. This means that the technical deliverables have been delayed until mid July
- O1 D1 Technical requirements gathered
- O1 D2 Evaluation of tools and frameworks to use
- O1 D4 Code store created encompassing code standards for using and contributing to EdGEL and version control
Next Steps
- Prepare recommendations for changes based on the Code Store review
- Review of service management and maintenance requirements for 17/18
- Continue progressing completion of remaining deliverables
- Define technical requirements, complete evaluation of tools and framework
- O3D4 Agreed Map future task meeting arranged for 17 July
RAG Commentary N/A
|
DTI009
Define UX Services
Category: Discretionary
Milestones
RAG Status GREEN
|
Report by Sue Woodger for June 2017
Achievements in Last Period
- An open session was held 27 June which consisted of lightning talks in order to showcase the work done so far and to gather feedback and evolve UX models. Project sponsors blogpost on the event can be found at http://website-programme-blog.is.ed.ac.uk/engaging-understanding-users-pilot-user-experience-service-showcase/
- The following deliverables were completed this month:
- O1D4 Establish a cycle of delivery to meet university demand
- O2D3 Provide a ‘sales pitch’ for the service – this has led to the completion of the milestone ‘Proposing a defined UX service’ on 12 June. The outputs from this milestone are:
- DTI009-02D3-UX EdGEL Standards services - long-v1.3-170531.pptx
- DTI009-02D2-Initial HCD process-170509.pptx
- O4D2 Stakeholders identified to validate the service (Will include consultation with Iain Fiddes, Mark Ritchie etc.)
Issues
- The departure of the Digital Design Consultant on 2 June 2017 has impacted the deliverables across all projects and the project sponsors are feeling this impact and acknowledge that delays are happening, pushing many deliverables into July and they are reprioritising some deliverables to help with these delays.
Next Steps
- Continue developing the initial design model into a practical service blueprint model
- Complete a walkthrough of the model on 4 July
- Proposed service model review (in alignment with DTI010 standards) – meeting scheduled for 6th July
RAG Commentary N/A
|
DTI010
Digital Experience Standards
Category: Discretionary
Milestones
RAG Status GREEN
|
Report by Sue Woodger for June 2017
Achievements
- UX Steering Group meeting held 30 June
Issues
- The departure of the Digital Design Consultant on 2 June 2017 has impacted the deliverables across all projects and the project sponsors are feeling this impact and acknowledge that delays are happening, pushing many deliverables into July and they are reprioritising some deliverables to help with these delays.
- Milestone ‘Report on findings, levels of standards compliance etc. and finalise what is an acceptable level’ was merged with ‘Evolve service outline based on experience and feedback’ as the work is being carried out as part of the service outline
Next Steps
- Continue with completion of project deliverables due in 16/17 and planning for 17/18
RAG Commentary N/A
|
|
|
Section Four: Closed or Withdrawn Projects