Report for September 2017
- Report Date
- September 2017
Report Date
29th September 2017
Report compiled by Alison Armstrong (User Experience Programme Manager)
for Neil Allison, Stratos Filalithis, Lisa Dawson, and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
- DTI007 - Project completed and closed on 4th August
- DTI008 - Project completed and closed on 4th August
- DTI009 - All 16/17 project deliverables completed and signed-off
- DTI009 - refinement work ongoing on the "Define UX Service" document to improve the service model in line with wider business area feedback, and service sustainability concerns
-
DTI009 - Forward planning for 2017/18 - meeting held on 22nd August 2017, reviewed priorities, initial draft outline plan and costings prepared, further amendments agreed and ongoing. Budget challenges were highlighted and additional funding will be required to deliver against the current scope of services within the programme.
DTI0010 - Project deliverables now completed, closure report completed, further refinement of the "Define Digital Experience Standards Service" deliverable ongoing, project now due to complete 30th October. - UX Programme Review meeting held with Gavin on 27th July. Gavin confirmed that the UX Service, Digital Experience Standards and EdGEL services will all sit under the same UX Service umbrella (at least during the life of the User Experience programme)
- Steering Group meeting held on 28th August - agreed further engagement needed to encourage adoption, and reinforce the value/benefits. (Initial focus needs to be on the UX Service to Service Excellence, prior to communication and rollout to the wider University.) Key priority is for Programme Owner to complete the rollout planning before the 27th Sept DTI Governance Board meeting. An initial plan was prepared but further work is required to adjust the plan in line with the anticipated resource requirements.
- DTI010 Define Standards document - based on feedback from key stakeholders, further refinement of the document is needed and ongoing including movement to more of a self-service model.
- Overall the User Experience Programme is GREEN at this point in time, and on track to continue in 17/18 with completion of forward planning a key priority.
DTI007 – project completed and closed.
DTI008 – project completed and closed.
DTI009 – GREEN - project deliverables completed, project and programme will continue in 2017/18 as planned.
DTI010 – AMBER - project deliverables completed but further refinement of the "Define Digital Experience Standards" deliverable is required and currently in progress, project expected to complete late Oct.
RAG & Forward Look
For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.
Resources to end of September 2017
For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.
Section Two: Projects Not Started
N/A.
Section Three: Projects in Progress
Project Info |
Project Managers Commentary |
||||||||
DTI009
Category: Discretionary Milestones RAG Status GREEN |
Report by Sue Woodger for September 2017 Achievements in Last Period
Issues
Next Steps
RAG Commentary N/A
|
||||||||
DTI010 Digital Experience Standards Category: Discretionary Milestones Milestones
Revised milestone still to be approved by WIS RAG Status AMBER
|
Report by Sue Woodger for September 2017 Achievements
Issues
Next Steps
RAG Commentary: Project is Amber as new revised milestone for closure to be approved by WIS – will be submitted this week. |
Section Four: Closed or Withdrawn Projects
Project Info |
Project Managers Commentary |
DTI007 EdGEL as a Service Category: Discretionary |
Project closed 28 July 17. Some items require follow up in 17/18 and these are detailed in DTI007 Deliverables tracker |
DTI008 EdGEL Technology Delivery and Transition to Business As Usual Category: Discretionary |
Project closed 28 July 17. Some items require follow up in 17/18 and these are detailed in DTI008 Deliverables tracker |
|
|
Attachment | Size |
---|---|
![]() | 12.06 KB |