Report for October 2017

Report Date
October 2017

ITI - Enterprise Services(ENT) Report

 

Programme Commentary, RAG and Resources Update

Overall Programme RAG: AMBER

The programme status is set as AMBER as we are still working around the 10Gbit network switch issues in order to continue working on the Openstack and VDI projects. The outstanding actions to be completed with that build will need to be done before we can go fully into service. A meeting with CIS has led to a workplan being produced to progress this before October. However, this workplan has not been followed and we are not very much further forward.  We worked to our  contingency plan of connecting in our new virtual hosting servers temporarily by 1Gb and we are able to meet the demand for virtual machines. Issue 1 in the Programme Issue Log. We also have PM Lea Anderson leaving on 17/10 who needs replaced on several ENT project.  Update to be provided in November report.

Programme Owner and Manager Overview

 

Codesort descending Programme Owner commentary, with Programme Manager updating as necessary RAG Manager Status Stage
ENT010

Private Cloud Provisioning

GREEN Graeme Wood In Progress Execute
ENT013 BCP for Enterprise Services BLUE David Watters Closed Close
ENT016 Automation of Infrastructure Deployments BLUE Lea Anderson Closed Close
ENT019 Authentication and Authorisation Review 2016-17

Next Steps​

  • Await comment from the sponsor
  • Close project
RED Lea Anderson In Progress Accept
ENT020 Centralised Logging

Next Steps

  • Load outstanding tasks onto Jira and manage deliveries. 
RED Lea Anderson In Progress Execute
ENT021 EASE Web Site Refactor BLUE Jon March Closed Close
ENT022 Data Centre Efficiency & Expansion

Next Steps

  • Identify all work instructions and maintenance contracts currently in place
  • Review existing generator controls against best practice
  • Plan to replace or improve the existing generator controls to improve performance, plant control and monitoring. 
  • Review building management reporting and systems
RED Lea Anderson In Progress Procure
ENT023 Windows Server 2016

Next steps

  • Build Local Profile Servers
  • Build Printer test servers
RED Lea Anderson In Progress Execute
ENT024 Email Directories Refactor

Next Steps

  • Technical design.
  • Planning and produce a project brief.
  • Coordinate with COM033.
GREEN Jon March In Progress Plan
ENT025

Automation of Infrastructure Deployments 17/18 Next Steps

  • HLD and sign off
  • Project Brief to V1.0
  • Basic Netscaler vService creation
RED Lea Anderson In Progress Execute
ENT026 VMware service improvement

Next Steps

  • Install Brocades into the core t locations
Migrate the VDI to mobile devices servers
RED Lea Anderson In Progress Plan
ENT027 Enterprise Monitoring   Maurice Franceschi Not Started Initiate
ENT028 Vmware Integrated Container Build   Maurice Franceschi Not Started Initiate
ENT029 Apps Account Management   Maurice Franceschi Not Started Initiate
ENT030 Implement Dell OME   Maurice Franceschi Not Started Initiate
ENT031 Authentication & Authorisation improvements 17/18   Maurice Franceschi Not Started Initiate
ENT032 Mailing Lists   Maurice Franceschi Not Started Initiate
ENT033 Mail Relays Data Management   Maurice Franceschi Not Started Initiate
ENT034 DR Testing for Enterprise Services   Maurice Franceschi Not Started Initiate
ENT035 Enterprise Services rolling decommission/upgrade project   Lea Anderson Not Started Initiate