Project Info
|
Project Managers Commentary
|
FIN135
Printing Services System Procurement and Implementation
Sponsor Funded
Milestones :
RAG Status :
AMBER
|
Report by Ben Armstrong for October 2021
Achievements in Last Period
- Continued user acceptance testing and progress with setting up link to Worldpay
Issues
- User testing has revealed several issues which must be resolved before progressing to deployment; specifically an issue related to previewing products and attaching accurate prices to those products. As a result the Scope RAG has been shown as AMBER this month to reflect the unresolved issues. This has been reported to the supplier, Canon, who is working on fixes.
- The link to Worldpay (from WPM) has experienced delays in the set-up meaning the payment / credit card element has not yet been ready for testing; the team have experienced issues with making contact with Worldpay and this has been escalated internally within the Finance Department
- The P&M delivery timescale for Payroll is now set at February 2022 and this project's second phase delivery (punch-out integration with P&M) must align with that date
- The project timeline is behind schedule and project milestones need to be revised; revised delivery dates must be agreed with the sponsor and team for phase 1 delivery (students and external users) and phase 2 delivery (P&M users - internal). As a result, the Time RAG has been shown as AMBER this month
- There is no finalised support arrangement in place yet; discussions have been held with Production Management and within the project team and an OLA is now being drafted
Next Steps
- Agree revised project milestones
- Resolve user testing issues with supplier
- Complete Worldpay link and related payment testing
- Finalise support arrangements (and related documentation) for phase 1 delivery
|
FIN139
HR and Payroll Annual Maintenance 21/22
Core Funded
Milestones :
| Milestones |
Due Date |
| Phase 1 Security Updates |
TBC |
| Decision point for TYE |
TBC |
| DSOR |
TBC |
| Closure |
TBC |
RAG Status :
GREEN
|
Report by Ben Armstrong for October 2021
Achievements in Last Period
- Project initiation document completed and signed off
- Apps Review governance group gave approval for project to start
- Development Technology resources booked
Issues
-
Awaiting confirmation of resource booking request for Applications Management; request has been submitted and in dialogue with Anne Graham as resource manager
-
We have to start the project with assurances that P&M will pick up tax year end work; we are liaising with P&M and this has been agreed subject to noting a project risk
Next Steps
- Confirm milestones
- Appoint project team members
- Sign off project brief
- Install first set of security patches through DEV and TEST environments
|
FIN140
PCI DSS Compliance IT Work
Core Funded
Milestones :
RAG Status :
GREEN
|
Report by Susan Ridder-Patrick for October 2021
Achievements in Last Period
Issues
- Slight delay in collating list of areas in scope and development of the brief due to leave taken by the Business lead and Project Manager.
Next Steps
- Draft Brief and seek approval
|