Report for April

Report Date
April 2015

Report compiled by Dawn Nicholls (Programme Manager) for Liz Welch (Programme Owner)

Section 1: Programme Commentary, RAG and Resources Update

Section 2: Projects Not Started

Section 3: Projects In Progress

Section 4: Closed or Withdrawn Projects

Section 1: Programme Commentary, RAG and Resources Update   

Commentary

 

 

 

Section 2: Projects Not Started

 

Project InfoProgramme Managers Commentary

AP45-020

Estates & Buildings - Finance interface requirements

Core funded

Planning - August 2015

Delivery - January 2016

RAG Status : GREEN

Deferred to Aug 2015 to support funding shortfall for RMAS

Budget allocation reduced to 50 days as this work overlaps with the corresponding  E&B project

 

 

Section 3: Projects in Progress

 

Project InfoProject Managers Commentary

FIN081 (12-024)

Document Management for Finance Applications

Category: Discretionary

Milestones (TBC)

RAG Status : SUSPENDED

Project is currently suspended awaiting appropriate resource from both FInance and Project Services

FIN086 (AP23-004)

ePay Reconciliation

Category:  Compliance

 

Milestones

      (TBC)

 

 RAG Status: AMBER

Report by Jill Nicoll for April 2015

Achievements in last period

  • Project un-suspended
  • New project manager assigned
  • Project estimation spreadsheet updated to reflect actual effort spent to date, and to include a project management estimate to complete (the previous estimate for project management having already been exceeded)

Issues

  • WPM has provided a file, but not in the directory required by the JAMS transfer process, nor in the format required by JAMS.  The Project Sponsor has requested a revised file, but WPM has not yet responded to this request.

Next Steps

  • WPM to provide a valid file, in the correct format and location
  • Revised project estimate to be reviewed by Project Sponsor and Programme Manager

(Note:  Cost RAG status will remain Red until revised project estimate has been agreed)

  • Once the valid WPM file has been provided in the correct format and location, ISA to secure appropriate development specialists, and re-plan the remainder of the project 

(Note:  Time RAG status will remain Amber until project re-planning is completed)

FIN094

SAAS/SLC Reconciliation

Category: Compliance

Milestones

Target dateTitle
08-May-2015Integration/Acceptance sign-off
11-May-2015Go-live
25-May-2015Deployment sign-off
08-Jun-2015Closure

 RAG Status: GREEN

Report by Dawn Nicholls for April 2015 

Achievements this period

  • Meeting held with key stakeholders from FSS, Accounts Payable and Finance Accounts to agree the revised financial procedures.
  • Agreement reached on go-live for w/c 11th May
  • Project re-planned for new agreed dates & resources requested

Issues

  • Student IDs with leading zeros are failing the validation checks.  A small change has been made to the application to re-insert these zeros if they are missing from the file. 

Next steps

  • Final UAT for student IDs with leading zeros
  • Deployment to live

 

Full details on project activities can be seen in the Project Journal

FIN098

eExpenses Replacement

Category:  Discretionary

Milestones

Target dateTitle
06-Apr-2015Pilot launch
20-Apr-2015Closure

RAG Status: RED

Report by Dawn Nicholls for April 2015

Achievements this period

  • Applications Management have been working with FIS to try and resolve the issues with the eFinancials interface

Issues

  • The pilot was not launched as planned this month due to issues uncovered with the eFinancials upload routine.  These issues were not detected during UAT and are preventing any expense claims from being uploaded for payment.  The issues are being worked on by Appications Management and although some progress has been made, we stil have not been able to successfully load any expense claims.  This additional work is causing the budget to escalate and the pilot cannot launch until this is resolved, therefore the project has been placed on RED status as we are currently unable to deliver the project.  We may now need to involve ABS to try and find an acceptable resolution.

Next steps

  • Resolve issues with eFinancials upload routine
  • Close the project 

    

Further details on project activities can be seen in the Project Journal

FIN099

Essential Enhancements for Finance Applications 2014/15

Category: Disctretionary

Milestones

 

RAG StatusGREEN

Report by Stephanie Ruthven for April 2015

Achievements in Last Period

  • eStores changes deployed to Live and signed off (FIN099-06/07/14)
  • Webfirst fix deployed to Live, pending sign off (FIN099-15)
  • FPM and CP now going through Load Balancer on Test (FIN099-35)
  • ALBACS replacement passing over to new project FIN106 (was FIN099-42)
  • FPM upgraded to v2.2, pending sign off (FIN099-69)

Issues

  • Bank Wizard certificates are now out of date. Requested updated versions from Experian.
  • Issues encountered when installing the new version of FPM on Dev. This took longer than expected.

Next Steps

  • Continue to with FIN099-02 change of hosting Bank Wizard from internal to external.
  • Finance to sign off live deployment of Webfirst fixes (FIN099-15/56)
  • Finance testing DEV and TEST for eInvoicing (FIN099-24)
  • Arrange live deployment of FPM/CP through load balancer (FIN099-35)
  • Finance to supply feedback on eIT enhancement (FIN099-55)
  • Finance to sign off second Supplier Self Service patch on LIVE (FIN099-67)
  • Schedule time with ABS to reconfigure Paperclip (FIN099-68)
  • Finance to sign off FPM upgrade (FIN099-69)

FIN101

SSO/Launchpad Phase 2

Category: Discretionary

Milestones

  • To be agreed.
 RAG Status: RED
Report by Morna Findlay for April 2015
 

Achievements this period

  • Crisis telephone meeting arranged with ABS, FIS and project team after which a plan to progress issue will be developed

 

Issues

  • Efinancials issues (logout messages and java issues) remain unresolved  (reported to ABS)
  • Interrmittent issues with webcoa remain unresolved   (reported to ABS) 
  • Eprocurement issue in DEV deprioritised as agreed with business - not being worked on
  • CP issue in DEV deprioritised as agreed with business - not being worked on
  • Delivery milestone  to be proposed by business lead
  • Project likely to run over currently agreed budget due to effort required to resolve identified issues
  • regular updating of OpenAm delivered by FIN103 may not be sufficient for users of Launchpad only

 

Next Steps

  • Hold telephone conference with ABS to develop plan to resolve efinancials  and webcoa issues
  • Agree project budget, milestones and scope with project sponsor
  • Agree if regular upload of OpenAM in scope for this project or not
  • Sign off webcoa in TEST
  • Deploy webcoa, exceluploader and paperclip to LIVE.

 

The project RAG status is RED as the milestones have not been agreed or approved,  and the deliverables are at risk due to the risk to the remaining project budget being insufficient to deliver them. 

FIN102

eExpenses Phase 2

Category: Discretionary (Sponsor Funded)

Milestones

Target dateTitle
26-Jun-2015End of development iterations (final delivery)
10-Jul-2015End of maintenance iteration
24-Jul-2015Project closure

RAG Status : GREEN

 

 

Report by Dawn Nicholls for April 2015

Achievements this period

  • User Stories have been reviewed & an initial prioritisation has taken place
  • Technical set-up and familiarisation has been completed
  • High-level design has been completed for interfacing electronic receipts to Serengeti
  • Foundations stage has been completed.

Issues

  • Project Brief not yet formally signed off due to conflicts for the Project Managers time.  The draft has been produced & circulated and a kick-off meeting held with the Project Sponsor to clarify objectives, priorities and timescales so all that remains is the formal sign-off.

Next steps

  • Start development iterations

  

Further details on project activities can be seen in the Project Journal

 

FIN103

SSO/Launchpad Phase 3 (eAuthorisations)

Category: Discretionary

Milestones

Target dateTitle
01-May-2015Integration sign-off workpackage 1
15-May-2015UAT sign-off workpackage 1
19-May-2015Delivery of workpackage 1 (OpenAM integration)
02-Jun-2015Deployment sign-off workpackage 1
12-Jun-2015Closure
RAG Status : GREEN
Report by Dawn Nicholls for April 2015

 

Achievements this period

  •  Build sign-off for workpackage 1

Issues

  • Decision from Project Sponsor to de-scope remaining workpackages to fund resolution of technical issues with the phase 2 project (FIN101).  This will cause the project to temporarily to show as under-budget in Asta until the change in project budget can be formally approved

Next steps

  • Formalise de-scoping of remaining workpackages & return budget to Finance programme for phase 2 project (FIN101) 
  • Integration testing of workpackage 1
  • UAT of workpackage 1
  • Go-live of workpackage 1

 

 

 

 

Further details on project activities can be seen in the Project Journal

FIN104

Supporting scan & destroy policy using Serengeti

Category: Compliance

Milestones

tbc

RAG Status :

Report by Morna Findlay for April 2015
 
 

FIN105

Financial reporting changes for FRS102

Category: Compliance 

Milestones

 

08-May-2015Analysis & build sign-off
22-May-2015Acceptance sign-off
02-Jun-2015Delivery sign-off
12-Jun-2015Project closure

RAG StatusGREEN

Report by David Watters for April 2015
 

Achievements in Last Period

  • Project brief, estimate and plan completed and submitted to WIS
  • First sets of reports developed and deployed into TEST
  • Reports successfully tested by staff in Finance

Issues

  • None reported

Next Period

  • Next round of reports to be coded and tested
  • All updated reports to be deployed into LIVE

 

Section 4: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN097

Archiving for eFinancials

Category:  Funded

Project closed 27/11/14

Closure milestone

Completion report

 

FIN100

ABS Systems Patching for Java 7

Category:  Funded

Project closed 14/11/14

Closure Milestone

Completion Report

AP34-016

Student Fees - Interest charging on invoices

Category: Funded

Project withdrawn as part of mid-year review

 

Documentation

Not available.