Report for August 2015
- Report Date
- August 2015
Report compiled by Dawn Nicholls (Programme Manager) for Liz Welch (Programme Owner)
Section 1: Programme Commentary, RAG and Resources Update
Section 2: Projects Not Started
Section 3: Projects In Progress
Section 4: Closed or Withdrawn Projects
Section 1: Programme Commentary, RAG and Resources Update
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP45-020 Estates & Buildings - Finance interface requirements Core funded Planning - Feb 2016 Delivery - Jul 2016 RAG Status : GREEN |
|
AP56-015 Coldfusion upgrade for finance applications Core funded Planning - Sep 2015 Delivery - Mar 2016 RAG Status : GREEN | |
AP56-016 eFinancials upgrade Core funded Planning - May 2016 Delivery - Mar 2017 RAG Status : GREEN | |
AP56-017 Migrate JAMS & eTime applications Core funded Planning - Jan 2016 Delivery - May 2016 RAG Status : GREEN | |
AP56-036 eExpenses enhancements Core funded Planning - Oct 2015 Delivery - Feb 2016 RAG Status : GREEN | |
AP56-039 Financial documents revitalisation (Version One) Core funded Planning - Nov 2015 Delivery - Mar 2016 RAG Status : GREEN | |
AP56-054 Finance BI improvement Core funded Planning - May 2016 Delivery - Jan 2017 RAG Status : GREEN | |
TBC Strategic review of financial systems Sponsor funded Planning - tbc Delivery - tbc RAG Status : GREEN |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||
FIN081 (AP12-024) Document Management for Finance Applications Category: Discretionary Milestones (TBC) RAG Status : SUSPENDED | Project is currently suspended as insufficient budget to re-open | ||||||||
FIN086 (AP23-004) ePay Reconciliation Category: Compliance Milestones
RAG Status: GREEN | Report by Jill Nicoll for August 2015 Achievements in last period
Issues
Next Steps
| ||||||||
FIN101 (AP23-003)SSO/Launchpad Phase 2 Category: Discretionary Milestones 14-09-15 Deployment Review 19-09-15 Close | Report by Morna Findlay for August 2015 Achievements this period
Issues
Next Steps
RAGThe project RAG status is RED as the efinancials deliverable has had to be descoped. | ||||||||
FIN102 (In-year)eExpenses Phase 2 Category: Discretionary (Sponsor Funded) Milestones
RAG Status : GREEN | Report by Dawn Nicholls for August 2015 Achievements this period
Issues
Next steps
Further details on project activities can be seen in the Project Journal | ||||||||
FIN104 (AP45-018) Supporting scan & destroy policy using Serengeti Category: Compliance Milestones (TBC) RAG Status : SUSPENDED | Project is currently suspended as insufficient budget to re-open | ||||||||
FIN106 (In-year) Albacs Replacement Category: Compliance Milestones (to be agreed) RAG Status : GREEN | Report by Anne Mathison for August 2015 Achievements
Issues:
Next Steps:
| ||||||||
FIN108 (AP56-042) Essential Enhancements Category: Discretionary Milestones Planning - Sep 2015 Delivery - Jun 2016 RAG Status : GREEN | Report by Jill Nicoll for August 2015 Achievements in last period
Issues
Next Steps
|
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN105 (AP45-019) Financial reporting changes for FRS102 David Watters Category: Compliance | Project closed 07/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin105/completion_report |