Report for September 2015
- Report Date
- September 2015
Report compiled by Dawn Nicholls (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)
Section 1: Programme Commentary, RAG and Resources Update
Section 2: Projects Not Started
Section 3: Projects In Progress
Section 4: Closed or Withdrawn Projects
Section 1: Programme Commentary, RAG and Resources Update
N.B. There has been a change to the way that the project RAG status is determined for all IS Projects, with the changes applying from this month onwards. The main change is that the RAG will now also reflect the changes over the last month, whereas previously it was the current status at the time of writing the report. This means that if there has been a change to the time, cost and/or scope during the reporting period that would otherwise have made the project status RED or AMBER at that time, then the project will be reported as RED or AMBER. This means that we expect to see more RED or AMBER projects than previously. A one-page summary of the ISG RAG status indicators is available on this page.
3 projects closed this month: -
FIN105 (AP45-019) Financial reporting changes for FRS102
FIN102 (In-year) eExpenses Phase 2
FIN101 (AP23-003) SSO/Launchpad Phase 2
- FIN108 Financial Systems Essential Enhancements (FIS) is shown on RED status as there has been a significant change to the project budget during the reporting period due to the project bening split into two (50 days for FIS & 50 days for SAS under FIN109). No further action is required and the project has now returned to GREEN status.
- FIN106 ALBACS Replacement is shown on RED status as the project closure date has been extended by 3 months at the Sponsor's request to allow for 3 clear payroll runs before the project closes. No further action is required and the project has now returned to GREEN status.
- FIN110 Coldfusion upgrade for finance applications is shown on RED status as early estimates predict circa 200 days may be required to complete this work. This project was already 50 days in deficit for this year as the completion date had to be brought forward from next year in order to meet with the termination date of Coldfusion 9. The overall result is that this project is likly to need an additional 150 days this year. This project involves migrations for both FIS & SAS and so the overall Finance programme will need to be reviewed to accommodate these additional days.
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP45-020 Estates & Buildings - Finance interface requirements Core funded Planning - Feb 2016 Delivery - Jul 2016 RAG Status : GREEN |
|
AP56-016 eFinancials upgrade Core funded Planning - May 2016 Delivery - Mar 2017 RAG Status : GREEN | |
AP56-017 Migrate JAMS & eTime applications Core funded Planning - Jan 2016 Delivery - May 2016 RAG Status : GREEN | |
AP56-036 eExpenses enhancements Core funded Planning - Oct 2015 Delivery - Feb 2016 RAG Status : GREEN | |
AP56-039 Financial documents revitalisation (Version One) Core funded Planning - Nov 2015 Delivery - Mar 2016 RAG Status : GREEN | |
AP56-054 Finance BI improvement Core funded Planning - May 2016 Delivery - Jan 2017 RAG Status : GREEN | |
TBC Strategic review of financial systems Sponsor funded Planning - tbc Delivery - tbc RAG Status : GREEN |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||
FIN081 (AP12-024) Document Management for Finance Applications Category: Discretionary Milestones (TBC) RAG Status : SUSPENDED | Report by Dawn Nicholls for September 2015 Meeting held with key Finance & IS Apps Stakeholders to determine resources & effort to re-direct project scope to either Cash Office or Income Section documentation. Agreed that FIS could undertake a lot of the preparation work for these areas to determine the quantity & quality of the documents to be scanned. The project will seek to re-open once that work is complete. | ||||||||||
FIN086 (AP23-004) ePay Reconciliation Category: Compliance Milestones
RAG Status: GREEN | Report by Jill Nicoll for September 2015 Achievements in last period
Issues n/a Next Steps
| ||||||||||
FIN101 (AP23-003)SSO/Launchpad Phase 2 Category: Discretionary Milestones N/A RAG Status: BLUE | Report by Morna Findlay for September 2015 Achievements this period
IssuesNo outstanding issues | ||||||||||
FIN102 (In-year)eExpenses Phase 2 Category: Discretionary (Sponsor Funded) Milestones N/ARAG Status : BLUE (closed) | Report by Dawn Nicholls for September 2015 Achievements this period
Issues
Next steps
| ||||||||||
FIN104 (AP45-018) Supporting scan & destroy policy using Serengeti Category: Compliance Milestones (TBC) RAG Status : SUSPENDED | Project is currently suspended as insufficient budget to re-open | ||||||||||
FIN106 (In-year) Albacs Replacement Category: Compliance Milestones (to be agreed) RAG Status : RED | Report by Anne Mathison for September 2015 Achievements
Issues:
Next Steps:
| ||||||||||
FIN108 (AP56-042) Essential Enhancements (FIS) Category: Discretionary Milestones
RAG Status : RED (Note: RAG status is RED to indicate a change since last month's report. The project's current RAG status is GREEN.) | Report by Jill Nicoll for September 2015 Achievements in last period
Issues
Next Steps
| ||||||||||
FIN109 (AP56-042) Essential Enhancements (SAS) Category: Discretionary Milestones
RAG Status : BLUE (suspended) | Report by Jill Nicoll for September 2015 Achievements in last period
Issues
Next Steps
| ||||||||||
FIN110 (AP56-015) Coldfusion upgrade for finance applications Category: Compliance Milestones
RAG Status : RED | Report by Dawn Nicholls for September 2015 Achievements this period
Issues
Next steps
|
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN105 (AP45-019) Financial reporting changes for FRS102 David Watters Category: Compliance | Project closed 07/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin105/completion_report |
FIN102 (In-year)eExpenses Phase 2 Dawn Nicholls Category: Discretionary (Sponsor Funded) | Project closed 11/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin102/completion_report |
FIN101 (AP23-003)SSO/Launchpad Phase 2 Morna Findlay Category: Discretionary | Project closed 18/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin101/completion_report |