Report for October 2015

Report Date
October 2015

Report compiled by Dawn Nicholls (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)

Section 1: Programme Commentary, RAG and Resources Update

Section 2: Projects Not Started

Section 3: Projects In Progress

Section 4: Closed or Withdrawn Projects

Section 1: Programme Commentary, RAG and Resources Update

  • FIN086 ePay Reconciliation closed this month
  • FIN081 Document Management & FIN104 Scan & Destroy remain suspended due to insufficient budget to re-open. Discussion are taking place with the Project Sponsor to agree options.
  • FIN110 Coldfusion Migration is RED this month as the scope and budget have increased significantly within the reporting period.  The additional days have been secured by reducing & deferring other project in the programme and releasing days from the contingency balance.  The changes have now been agreed so the project will be returning to GREEN status
  • FIN111 eExpenses Enhancementment started this month
  • AP45-020 E&B Finance Interface Requirements may not be needed.  Once confirmed these days can be released to cover shortfalls for other priority work in the programme.
  • FIN109 Essential Enhancements (SAS) has sacrificed 10 days to help fund the shortfall for the priority compliance work for Coldfusion migrations
  • FIN106 ALBACS Replacement has been flagged as AMBER due to the extending timelines.  These delays are the result of a culmination of minor issues which are preventing finalisation of the on-site date for the supplier.
  • The Strategic Review project is starting to undertake activites but no Project Brief has been agreed or funding secured so this has been flagged as RED.

The overall FIN budget has been re-assessed and re-balanced in preparation for the mid-year review and is now in a balanced position

 

 

 

Section 2: Projects Not Started

 

Project InfoProgramme Managers Commentary

AP45-020

Estates & Buildings - Finance interface requirements

Core funded

Planning - Feb 2016

Delivery - Jul 2016

 RAG Status : GREEN

Due to delays in thework being undertaken in Estates & Buildings, this project may be deferred to 16/17 and the days used to fund other priority Finance work

AP56-016

eFinancials upgrade

Core funded

Planning - May 2016

Delivery - Mar 2017

 RAG Status : GREEN

ABS have yet to confirm the release date for the new version of eFin.  The current forecast is for the beta version in December 2015 which would result in the project not starting until Jun/Jul 2016

AP56-017

Migrate JAMS & eTime applications

Core funded

Planning - Jan 2016

Delivery - May 2016

 RAG Status : GREEN

 

AP56-039

Financial documents revitalisation (Version One)

Core funded

Planning - Nov 2015

Delivery - Mar 2016

 RAG Status : GREEN

 

AP56-054

Finance BI improvement

Core funded

Planning - May 2016

Delivery - Jan 2017

 RAG Status : GREEN

 

TBC

Strategic review of financial systems

Sponsor funded

Planning - tbc

Delivery - tbc

 RAG Status : RED

Work is already starting on this project but no Project Brief or budget has been agreed.  Effort is being temporarily coded to the programme level but this needs to be formally agreed.

 

Section 3: Projects in Progress

 

Project InfoProject Managers Commentary

FIN081 (AP12-024)

Document Management for Finance Applications

Category: Discretionary

Milestones

(TBC)

RAG Status : BLUE (Suspended)

Project is currently suspended and the programme has insufficient budget to re-open

FIN086 (AP23-004)

ePay Reconciliation

Category:  Compliance

Milestones

  N/A

 RAG Status: BLUE (Closed)

Report by Jill Nicoll for October 2015

Achievements in last period

  • Project closure confirmed

Issues

   n/a

Next Steps

   n/a

FIN104 (AP45-018)

Supporting scan & destroy policy using Serengeti

Category: Compliance

Milestones

(TBC)

RAG Status : BLUE (Suspended)

Project is currently suspended and the programme has insufficient budget to re-open
 

FIN106 (In-year)

ALBACS Replacement

Category: Compliance

Milestones

DateMilestone
04-Dec-2015Installation / Integration
08-Dec-2015Acceptance
10-Dec-2015Deployment
16-Dec-2015Deployment Sign Off Review (DSOR)
07-Apr-2016Closure
07-Apr-2016Decommission Albacs

RAG Status : AMBER

Report by Anne Mathison for October 2015

Achievements:

  • Finance have clarified the DNS information that Bottomline required
  • Discussed getting HSM set up to wait until Networks are ready before it will be connected
  • Planned Bottomline to be on site to set up HSM's - 5-Nov
  • Now making progress with Networks currently establishing the days when this can take place
  • Finance, Bottomline and IS Apps have provided the information that Bottomline require

Issues:

  • None

Next Steps:

  • Production, Finance and IS Apps agreed 24 Nov is when the ITI VM Servers can take place
  • Following this the VM Servers can be set up with HSM
  • Bottomline re HSM on site 5 Nov to set up HSM's although not connected at this stage
  • Agree plan for Bottomline 3 day visit - 1-3 Dec to set up TEST, where Test checked out for 2 days and Finance training takes place 3 Dec.
  • Agree plan for Bottomline to set up LIVE agree with Finance

Project has been updated for the April decommissioning.

FIN108 (AP56-042)

Essential Enhancements (FIS)

Category: Discretionary

Milestones

 

Target dateTitle
01-Jul-2016Delivery of final enhancements batch
15-Jul-2016Deployment Sign-off Review of final enhancements batch
22-Jul-2016Closure Sign-off Review

RAG Status : GREEN

Report by Jill Nicoll for October 2015

Achievements in last period

  • Batch 1 requirements selected and prioritised
  • Where business requirements have been specified, effort has been estimated and ISA resources secured

 

Issues

  • By the Business Lead's request, Jira FIN108-6 was added to Batch 1, inserted with Priority 3.  This increases the scope of Batch 1, but does not change the overall scope of the project.  Associated Risk 10 raised.

 

Next Steps

  • Finance to provide business requirements for remaining Batch 1 Jiras
  • ISA to progress with Batch 1 deliveries

FIN109 (AP56-042)

Essential Enhancements (SAS)

Category: Discretionary

Milestones

RAG Status : BLUE  (suspended)

Report by Jill Nicoll for October 2015

Project is currently suspended

FIN110 (AP56-015)

Coldfusion upgrade for finance applications

Category: Compliance

Milestones

 

Target dateTitle
06-Nov-2015End of planning
31-Mar-2016Final delivery date
15-Apr-2016Project closure

 RAG Status : RED

Report by Dawn Nicholls for October 2015

Achievements this period

  • Project Brief and related estimates, risks and stakeholders drawn up & distrubuted for review
  • Revised estimation produced to incorporate 2 additional applications

Issues

  • The scope of the project has been increased as two additional applications have been identified for migration (Time Allocation Survey & WPMserve)
  • The current estimate is 186 days against a proposal budget of 100 days.  This has been discussed with the Programme Owners in Finance and the additional days have been secured by reducing/deferring other projects in the programme.
  • Due to the increased scope and budget during the reporting period, the project is being reported as RED but the required changes are now agreed so the project will return to GREEN

Next steps

  • Sign-off planning stage
  • Agree sequence of migrations with business users
  • Secure resources for technical prep work

FIN111 (AP56-036)

eExpenses enhancements

Category: Discretionary

Milestones

 

Target dateTitle
06-Nov-2015End of planning
20-Nov-2015End of foundations
19-Feb-2016End of development iterations
04-Mar-2016End of maintenance iteration
11-Mar-2016Closure

 RAG Status : GREEN

Report by Dawn Nicholls for October 2015

Achievements this period

  • Project kick-off meeting held with Business Lead and key stakeholders
  • Work undertaken to review & prioritise Jiras from previous eExpenses project

Issues

  • None this month

Next steps

  • End of planning sign-off
  • Start foundations stage

Section 4: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN105 (AP45-019)

Financial reporting changes for FRS102

David Watters

Category: Compliance

Project closed 07/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin105/completion_report

FIN102 (In-year)

eExpenses Phase 2

Dawn Nicholls

Category: Discretionary (Sponsor Funded)

Project closed 11/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin102/completion_report

FIN101 (AP23-003)

SSO/Launchpad Phase 2

Morna Findlay

Category: Discretionary

Project closed 18/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin101/completion_report

FIN086 (AP23-004)

ePay Reconciliation

Category:  Compliance

Project closed 07/10/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin086/completion_report

 

Documentation

Not available.