Report for November 2015

Report Date
November 2015

Report compiled by Dawn Nicholls (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)

Section 1: Programme Commentary, RAG and Resources Update

Section 2: Projects Not Started

Section 3: Projects In Progress

Section 4: Closed or Withdrawn Projects

Section 1: Programme Commentary, RAG and Resources Update

 The overall programme budget is in a balanced position with a small contingency being held to cover any technical issues with the ALBACS Replacement or Coldfusion Migrations.

  • FIN081 Document Management for Finance Systems - this project is currently suspended and the programme has insufficient budget to re-open.  High-level scoping meeting suggests that the bulk of the remaining work could be undertaken by Finance staff.  Decision needed on whether this project can now be withdrawn.
  • FIN104 Supporting Scan & Destroy Using Serengeti - this project has been suspended for some time due to the volume of higher priority work.  Agreement is needed on if/when to progress this project within 15/16.  A small number of days (5) are available to undertake some high level analysis to see what technical solutions might be available.  DIscussions would then need to take place on how to fund any further work.
  • FIN108 - Essential Enhancements (FIS) - this project has been flagged as RED due to the increase in budget during the reporting period. This increase has been approved by all relevant parties and the project is now on GREEN status.
  • FIN111 - eExpenses Enhancements - the timeline has been extended following agreement to introduce a 2 month gap mid-project to allow Finance to roll out the application across the University.  The final development iterations after the gap will then be utilised to look at priority feedback from the rollout.  The overall budget is not affected by this.
  • AP45-020 E&B FInance Interface Requirements - this project has been moved out to 16/17 but discussion is needed on whether the project is still required.
  • FIN106 ALBACS Replacement - the timeline has been extended slightly to ensure there is sufficient time for Finance to run several live payroll payment runs before the project closes. The budget and scope are not affected.
  • FIN109 - Essential Enhancements (SAS) - the project budget has been reduced by 10 days to help cover the deficit for the compliance Coldfusion migrations
  • AP56-016 - eFinancials upgrade - the beta release date of the new version of eFinancials has been delayed by ABS to Feb 2016 so the start date of this project has been moved out. The days that this has freed up have been used to offset the deficit for the compliance Coldfusion
  • The Strategic Review project is starting to undertake activities but no Project Brief has been agreed or funding secured so this has been flagged as RED and requires further discussion with the SAS Programme Owner.

Section 2: Projects Not Started

 

Project InfoProgramme Managers Commentary

AP45-020

Estates & Buildings - Finance interface requirements

Core funded

Planning - Aug 2016

Delivery - Jan 2017

 RAG Status : GREEN

Due to delays in thework being undertaken in Estates & Buildings, this project has been deferred to 16/17

AP56-016

eFinancials upgrade

Core funded

Planning - Jul 2016

Delivery - May 2017

 RAG Status : GREEN

ABS have yet to formally release v5 of eFInancials.  The current forecast is for the beta version in February 2016 which would result in the project not starting until Jul/Aug 2016

AP56-017

Migrate JAMS & eTime applications

Core funded

Planning - Jan 2016

Delivery - May 2016

 RAG Status : GREEN

 

AP56-039

Financial documents revitalisation (Version One)

Core funded

Planning - Jan 2016

Delivery - May 2016

 RAG Status : GREEN

 

AP56-054

Finance BI improvement

Core funded

Planning - May 2016

Delivery - Jan 2017

 RAG Status : GREEN

 

TBC

Strategic review of financial systems

Sponsor funded

Planning - tbc

Delivery - tbc

 RAG Status : RED

Work is already starting on this project but no Project Brief or budget has been agreed.  Effort is being temporarily coded to the programme level but this needs to be formally agreed.

 

Section 3: Projects in Progress

 

Project InfoProject Managers Commentary

FIN081 (AP12-024)

Document Management for Finance Applications

Category: Discretionary

Milestones

(TBC)

RAG Status : BLUE (Suspended)

Project is currently suspended and the programme has insufficient budget to re-open.  High-level scoping meeting suggests that the bulk of the remaining work could be undertaken by Finance staff.  Decision needed on whether this project can be withdrawn.

FIN104 (AP45-018)

Supporting scan & destroy policy using Serengeti

Category: Compliance

Milestones

(TBC)

RAG Status : BLUE (Suspended)

Project is currently suspended and the programme has insufficient budget to re-open.  Suggestion is to spend 5 days looking at high-level requirements to understand what might be possible.
 

FIN106 (In-year)

ALBACS Replacement

Category: Compliance

Milestones

DateMilestone
11-Dec-2015Acceptance
17-Dec-2015Deployment
29-Jan-2016Deployment Sign Off Review (DSOR)
05-May-2016Closure
05-May-2016Decommission Albacs

RAG Status : GREEN

Report by Anne Mathison for November 2015

Achievements:

  • Bottomline were on site 5 Nov to set up the Hardware Security Module's (HSM's) although they were not connected at that point
  • All ITI VM Servers were restarted on 24 -Nov to allow for the Hardware Security Module (HSM) to be connected in December
  • Following that the VM Servers were set up with HSM
  • Bottomline's 3 day visit  took place on 1-3 Dec to set up TEST.
  • Test was checked out and verified using C-series.
  • Finance successfully completed initial Testing and Training.
  • Agreed date with Bottomline regarding Live deployment set up
  • Agreed Finance will actively use Live C-Series in January

Issues:

  • None

Next Steps:

  • Complete Acceptance Testing
  • Agreed Live set up date as 21-Dec with Bottomline
  • System will not become actively Live until January
  • Live rollout out in January 16.

Test installation complete. Acceptance testing now underway.

FIN108 (AP56-042)

Essential Enhancements (FIS)

Category: Discretionary

Milestones

Target dateTitle
01-Jul-2016Delivery of final enhancements batch
15-Jul-2016Deployment Sign-off Review of final enhancements batch
22-Jul-2016Closure Sign-off Review

RAG Status : RED, to reflect that RAG has changed within the last month

(The current RAG status is GREEN.)

Report by Jill Nicoll for November 2015

Achievements in last period

  • Batch 1 work is progressing

Issues

  • Batch 1 progress has been slow, due to higher priority demands in both IS and Finance.
  • The Project Sponsor has increased the project's budget from 50 to 65 days.

Next Steps

  • Finance to provide business requirements for remaining Batch 1 Jiras
  • ISA and Finance to progress with remaining Batch 1 deliveries
  • Project team to agree content of second batch

FIN109 (AP56-042)

Essential Enhancements (SAS)

Category: Discretionary

Milestones

(TBC)

RAG Status : BLUE  (suspended)

Report by Jill Nicoll for November 2015

Project is currently suspended

FIN110 (AP56-015)

Coldfusion upgrade for finance applications

Category: Compliance

Milestones

Target datePrevious dateTitle
31-Mar-201631-Mar-2016Final delivery date
15-Apr-201615-Apr-2016Project closure

 RAG Status : GREEN

Report by Ben Armstrong for November 2015

Achievements this period

  • Met with core project team to discuss scheduling of resources and applications for upgrades
  • Secured Development Technology resources for the ColdFusion 11 (CF11) environment set-up tasks

Issues

  • None noted

Next steps

  • Prepare CF11 environments
  • Follow up with Software Development Team on resource requests for Bamboo tasks

 

FIN111 (AP56-036)

eExpenses enhancements

Category: Discretionary

Milestones

Target dateTitle
05-Feb-2016End of first 4 development iterations
08-Feb-2016Go-live
01-Apr-2016Rollout completed by Finance
29-Apr-2016End of additional development iterations
02-May-2016Go-live
13-May-2016End of maintenance iteration
20-May-2016Closure

 RAG Status : GREEN

Report by Dawn Nicholls for November 2015

 Achievements this period

  • The Project Brief and planning stage have been formallly signed-off
  • The foundations stage successfully completed
  • Development iteration 1 uccessfully completed.  User Stories prioritised for development are documented at https://www.projects.ed.ac.uk/project/fin111/page

Issues

  • Resource conflicts for the developers time has reduced progress
  • Technical issues with mass storage on Test for electronic receipts

Next steps

  • Development iteration 2

Section 4: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN105 (AP45-019)

Financial reporting changes for FRS102

David Watters

Category: Compliance

Project closed 07/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin105/completion_report

FIN102 (In-year)

eExpenses Phase 2

Dawn Nicholls

Category: Discretionary (Sponsor Funded)

Project closed 11/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin102/completion_report

FIN101 (AP23-003)

SSO/Launchpad Phase 2

Morna Findlay

Category: Discretionary

Project closed 18/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin101/completion_report

FIN086 (AP23-004)

ePay Reconciliation

Category:  Compliance

Project closed 07/10/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin086/completion_report

 

Documentation

Not available.