Status report for January 2016

Report Date
January 2016

Report compiled by Dawn Holmes (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)

Section 1: Programme Commentary, RAG and Resources Update

Section 2: Projects Not Started

Section 3: Projects In Progress

Section 4: Closed or Withdrawn Projects

Section 1: Programme Commentary, RAG and Resources Update

 

  • FIN081 Document Management - this project is currently suspended and the programme has insufficient budget to re-open.  High-level scoping meeting suggests that the bulk of the remaining work could be undertaken by Finance staff.  It is recommeded that this project now be withdrawn.
  • FIN104 Scan & Destroy - Business Analyst assigned to undertake up to 5 days analysis as agreed with the FIN(FIS) Programme Owner
  • FIN111 eExpenses - eAuthorisations changes related to eExpenses were more extensive than anticipated, which will impact on our ability to deliver the 7th development iteration.
  • AP56-039 Version One - project was due to start this month but assigned Project Manager is on extended sick leave
  • FIN106 ALBACS Replacement - a live payment run still hasn't been undertaken which will soon start to impact on the project timeline & estimate.  This has been escalated to Programme level.
  • FIN113 Migrate eTime/JAMS - project started this month as planned
  • Strategic review - still no agreed funding or scope of work.  This has been escalated to Portfolio level.

 

 

 

Section 2: Projects Not Started

 

Project InfoProgramme Managers Commentary

AP45-020

Estates & Buildings - Finance interface requirements

Core funded

Planning - Aug 2016

Delivery - Jan 2017

 RAG Status : GREEN

Due to delays in the work being undertaken in Estates & Buildings, this project has been deferred to 16/17

AP56-016

eFinancials upgrade

Core funded

Planning - Jun/Jul 2016

Delivery - May 2017

 RAG Status : GREEN

ABS have informed us that v5 of eFInancials will be released in March.  As this will be the Beta version, it's unlikely that the full version will be released until around June.  The project has been delayed in the plan accordingly.

AP56-039

Financial documents revitalisation (Version One)

Core funded

Planning - Jan 2016

Delivery - May 2016

 RAG Status : GREEN

Assigned Project Manager is currently off sick.  Will start once they return in Feb.

AP56-054

Finance BI improvement

Core funded

Planning - May 2016

Delivery - Jan 2017

 RAG Status : GREEN

 

 

Section 3: Projects in Progress

 

Project InfoProject Managers Commentary

FIN081 (AP12-024)

Document Management for Finance Applications

Category: Discretionary

Milestones

(TBC)

RAG Status : BLUE (Suspended)

Project is currently suspended and the programme has insufficient budget to re-open.  High-level scoping meeting suggests that the bulk of the remaining work could be undertaken by Finance staff.  Decision needed on whether this project can be withdrawn.

FIN104 (AP45-018)

Supporting scan & destroy policy using Serengeti

Category: Compliance

Milestones

(TBC)

RAG Status : BLUE (Suspended)

Project is currently suspended and the programme has insufficient budget to re-open.
 
5 days have been allocated from the programme budget to undertake some analysis and a Business Analyst has been assigned.
 

FIN106 (In-year)

ALBACS Replacement

Category: Compliance

Milestones

DateMilestone
29-Jan-2016Deployment Sign Off Review (DSOR)
05-May-2016Closure
05-May-2016Decommission Albacs

RAG Status : GREEN

Report by Anne Mathison for January 2016

Achievements:

  • Further testing took place in January
  • Acceptance Testing signed off
  • Deployed successfully in December
  • Requested Bottomline support to set up HSM Users accounts
  • Agreed rollout will take place in February

Issues:

  • None

Next Steps:

  • Finance will actively use C-series in  Live with old password while waiting for HSM Bottomline work
  • Deployment sign off review (DSOR) will follow once Finance agreed Live is correct then all the runs will follow with C-series
  • Agreed Finance will actively use Live C-Series as soon as accounts set up by Bottomline
  • Live rollout out in February 16.
  • Agree when project will be suspended and for how long
 
 

FIN108 (AP56-042)

Essential Enhancements (FIS)

Category: Discretionary

Milestones

Target date

Title

01-Jul-2016

Delivery of final enhancements batch

15-Jul-2016

Deployment Sign-off Review of final enhancements batch

22-Jul-2016

Closure Sign-off Review

RAG Status : GREEN

Report by Jill Nicoll for January 2016

Achievements in last period

  • Finance provided requirements for Batch 2 Jira FIN108-13 (eTime)

Issues

  • January project meeting cancelled due to PM's illness

Next Steps

  • Finance to provide business requirements for remaining Batch 2 Jiras
  • ISA and Finance to progress with Batch 2 deliveries

FIN109 (AP56-042)

Essential Enhancements (SAS)

Category: Discretionary

Milestones

(TBC)

RAG Status : BLUE  (suspended)

Report by Jill Nicoll for January 2016

Project is currently suspended

FIN110 (AP56-015)

Coldfusion upgrade for finance applications

Category: Compliance

Milestones

Target dateTitle
31-Mar-2016Project Delivery
15-Apr-2016Project closure

 RAG Status : GREEN

Report by Ben Armstrong for January 2016

Achievements this period

  • Technical Architecture Documents (TADs) drafted for each of the 7 Finance applications in scope
  • Intitial feedback received from Tech Management and Apps Management on the draft TADs
  • Each of the applications have been entered into the Change Management Database as configuaration items

Issues

  • EIT has a dependency on the Printing Services Online (PSO) application which itself is being upgraded under a separate project; EIT has been scheduled as the last Finance application to be deployed to allow time for PSO to be upgraded and then tested in parallel.
  • The system developer originally booked to carry out the deployment of 2 of the applications has moved to the SSP development team; the team manager is to advise a replacement resource.
  • Some concurrent changes are being made to the Student Finance Channel application; as the changes are being made by the same system developer booked to carry out the upgrade we have reassurance that this will be managed and should not impact the upgrade

Next steps

  • Complete the updates to the TADs following feedback
  • 6 of the 7 applications (all except EIT) will be deployed to Dev and Test environments using Bamboo
  • User acceptance testing will be undertaken for 2 of the 7 applications (WebFirst and eStores); others to follow

FIN111 (AP56-036)

eExpenses enhancements

Category: Discretionary

Milestones

Target dateTitle
05-Feb-2016End of first 4 development iterations
08-Feb-2016Go-live
01-Apr-2016First phase of rollouts completed by Finance
13-May-2016End of additional development iterations
16-May-2016Go-live
27-May-2016End of maintenance iteration
03-Jun-2016Closure

 RAG Status : AMBER

Report by Dawn Holmes for January 2016

 Achivements this period

  • Completion of development iteration 3. Completed User Stories are documented on the iteration 3 page
  • Planning for development iteration 4.  Prioritised User Stories selected for development are documented on the iteration 4 page
  • Go-live of prioritised eAuthorisations changes to facilitate new eExpenses features such as approvers' financial limits

Issues

  • Authorisations changes took longer to complete than anticipated which may affect the project's ability to complete a 7th iteration later in the year. Therefore the project is being reported on AMBER.

Next steps

  • Complete development iteration 4
  • Go-live of latest eExpenses software
  • Finance to commence roll-out to Schools

FIN112

Strategic Review of Financial Review

Category: Funded

Milestones

tbc

 RAG Status : RED

Report by Dawn Holmes for January 2016

Achievements this period

  • Workshop held with VAT Team
  • Workshop outputs written up & distributed for futher input

Issues

  • This project work still has no formal definition or funding agreed

Next steps

  • Workshop with Financial Accounting

 

FIN113 (AP56-017)

Migrate JAMS & eTime applications

Category: Compliance

Milestones

tbc

 RAG Status : GREEN

Report by Anne Mathison for January 2016

Achievements in last period:

  • Initiation of project
  • Project manager assigned
  • Project website set up

Issues:

  • None

Next Steps:

  • Investigation in to JAMS and eTime migrations
  • Estimation of project agreed
  • Discussion with Senior User
  • Draft Brief completed
  • Agree JAMS milestones and budget
  • Agree eTime milestones and budget
  • Brief approved
  • Start JAMS Design

Section 4: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN105 (AP45-019)

Financial reporting changes for FRS102

David Watters

Category: Compliance

Project closed 07/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin105/completion_report

FIN102 (In-year)

eExpenses Phase 2

Dawn Holmes

Category: Discretionary (Sponsor Funded)

Project closed 11/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin102/completion_report

FIN101 (AP23-003)

SSO/Launchpad Phase 2

Morna Findlay

Category: Discretionary

Project closed 18/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin101/completion_report

FIN086 (AP23-004)

ePay Reconciliation

Category:  Compliance

Project closed 07/10/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin086/completion_report

 

Documentation

Not available.