Section 1: Programme Commentary, RAG and Resources Update
The programme budget is showing a large surplus this month as the remaining eExpenses work has been moved out to 16/17 but the related budget of 62 days is still to be released back to the CSG portfolio. The 22 days remaining on the core funded balance row are to be released to FIN108 Essential Enhancements (FIS) to cover some high priority research reporting requirements from eTime.
- FIN111 eExpenses is shown on RED this month as the timeline has moved out to 16/17. This change has been agreed with the Portfolio Manager and the days will be made available next year to cover this work by trading off effort for this year with Estates & Buildings.
- FIN110 Coldfusion Migrations is shown on AMBER this month as the timeline is moving out due to issues encountered in UAT which require further investigation
- FIN113 eTime & JAMS Migration is shown on AMBER this month due to issues encountered in the Dev environment and resource conflicts in the technical team to address these
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP45-020 Estates & Buildings - Finance interface requirements Core funded Planning - Aug 2016 Delivery - Jan 2017 RAG Status : GREEN | Due to delays in the work being undertaken in Estates & Buildings, this project has been deferred to 16/17 |
AP56-016 eFinancials upgrade Core funded Planning - Jun/Jul 2016 Delivery - May 2017 RAG Status : GREEN | ABS still have not confirmed the release date for v5 of eFInancials so the majority of this project has now been moved out to 16/17 with just a small number of days retained in 15/16 for project initiation. |
AP56-054 Finance BI improvement Core funded Planning - May 2016 Delivery - Jan 2017 RAG Status : GREEN | This project is planned to start at the end of May |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||
FIN104 (AP45-018) Supporting scan & destroy policy using Serengeti Category: Discretionary Milestones
RAG Status : GREEN | Report by Dawn Holmes for April 2016 Achievements this period
Issues
Next steps
| ||||||||||||||||||||||||||||||
FIN106 (In-year) ALBACS Replacement Category: Compliance Milestones
RAG Status : GREEN | Report by Anne Mathison for April 2016 Achievements:
Issues
Next Steps:
| ||||||||||||||||||||||||||||||
FIN108 (AP56-042) Essential Enhancements (FIS) Category: Discretionary Milestones
RAG Status : GREEN | Report by Jill Nicoll for April 2016 Achievements in last period
Issues
Next Steps
| ||||||||||||||||||||||||||||||
FIN109 (AP56-042) Essential Enhancements (SAS) Category: Discretionary Milestones
RAG Status : GREEN | Report by Jill Nicoll for April 2016 Achievements in last period
Issues
Next Steps
| ||||||||||||||||||||||||||||||
FIN110 (AP56-015) Coldfusion upgrade for finance applications Category: Compliance Milestones
RAG Status : AMBER | Report by Ben Armstrong for April 2016 Achievements this period
Issues
Next steps
| ||||||||||||||||||||||||||||||
FIN111 (AP56-036) eExpenses enhancements Category: Discretionary Milestones
RAG Status : RED/BLUE (suspended) | Report by Dawn Holmes for April 2016 This project was due to be un-suspended this month but following discussions with the Project Sponsor we have agreed to postpone the un-suspension until late September. This is due primarily to the pressure of other Finance projects taking place in 15/16 and the volume of effort required to complete the first phase of eExpenses rollout. Further details about the change can be seen in the Issue/Change Log. | ||||||||||||||||||||||||||||||
FIN112 Strategic Review of Financial Review Category: Funded Milestones
RAG Status : GREEN | Report by Dawn Holmes for April 2016 Achievement this period
Issues
Next steps
| ||||||||||||||||||||||||||||||
FIN113 (AP56-017) Migrate JAMS & eTime applications Category: Compliance Milestones
RAG Status : AMBER | Report by Anne Mathison for April 2016 Achievements: -
Issues:
Next Steps:
Project RAG status of AMBER due to resourcing issues | ||||||||||||||||||||||||||||||
FIN114 (AP56-039) Financial documents revitalisation (Version One) Category: Discretionary Milestones
RAG Status : GREEN | Report by Nikki Hacket-Reed for April 2016 Achievements this periodA meeting to introduction myself to the Finance Team and understand their concerns and challenges around the Financial Documentation Revitalisation Version 1 deliverable. Also to establish the scope of the deliverable. A meeting with Anne and Paul to introduce myself and discuss the deliverable requirements of the Finance Team. 'AS'IS' process mapped. 'AS IS' Sign off is no longer required due to the 'Access Rights' scope deliverable no longer being relevant as Corporate Policy and Audit dictate this is not allowed. Weekly team meeting organised and in diaries Draft plan/3point Estimate completed Asta tasks set up and initial timesheet assignments allocated as agreed with Anne and Paul. IssuesNONE Next StepsProject Brief signed off and presented to WIS for approval Business Requirements established and documented Technical Design Document Implementation plan and test scripts written
|
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN105 (AP45-019) Financial reporting changes for FRS102 David Watters Category: Compliance | Project closed 07/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin105/completion_report |
FIN102 (In-year)eExpenses Phase 2 Dawn Holmes Category: Discretionary (Sponsor Funded) | Project closed 11/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin102/completion_report |
FIN101 (AP23-003)SSO/Launchpad Phase 2 Morna Findlay Category: Discretionary | Project closed 18/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin101/completion_report |
FIN086 (AP23-004) ePay Reconciliation Category: Compliance | Project closed 07/10/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin086/completion_report |
FIN081 (AP12-024) Document Management for Finance Applications Category: Discretionary | Project withdrawn due to insufficient budget |