Report for May 2016
- Report Date
- May 2016
Report compiled by Dawn Holmes (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)
Section 1: Programme Commentary, RAG and Resources Update
Section 2: Projects Not Started
Section 3: Projects In Progress
Section 4: Closed or Withdrawn Projects
Section 1: Programme Commentary, RAG and Resources Update
FIN106 ALBACS Replacement successfully completed this month. Completion report linked in section 4.
FIN114 Financial Documents Revitalisation (Version One) and FIN112 Strategic Review of Financial Systems are both now expected to span into early 16/17. This will impact on the planned project work for 16/17 by approximately 20 days and funding options are still to be discussed with the relevant Project Sponsors.
Other project work is expected to complete in June/July as planned and the programme budget is in a healthy position with adequeate coverage for the remaining planned work.
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP45-020 Estates & Buildings - Finance interface requirements Core funded Planning - Aug 2016 Delivery - Jan 2017 RAG Status : GREEN | This is now planned for 16/17 |
AP56-016 eFinancials upgrade Core funded Planning - Aug 2016 Delivery - May 2017 RAG Status : AMBER | ABS still have not confirmed the release date for v5 of eFInancials so all of this project has now been moved out by a further month to start in 16/17 |
AP56-054 Finance BI improvement Core funded Planning - Aug 2016 Delivery - Apr 2017 RAG Status : RED | The project start date has been moved out to start in August at the request of the Project Sponsor so that it follows on from the FInancial Strategic Review |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||
FIN104 (AP45-018) Supporting scan & destroy policy using Serengeti Category: Discretionary Milestones
RAG Status : AMBER | Report by Dawn Holmes for May 2016 Achievement this period
Issues
Next steps
| ||||||||||||||||
FIN106 (AP45-925) ALBACS Replacement Category: Compliance Milestones N/A RAG Status : BLUE | Report by Anne Mathison for May 2016 Achievements:
Issues
Next Steps:
| ||||||||||||||||
FIN108 (AP56-042) Essential Enhancements (FIS) Category: Discretionary Milestones
RAG Status : RED
| Report by Jill Nicoll for May 2016 Achievements in last period
Issues
Next Steps
| ||||||||||||||||
FIN109 (AP56-042) Essential Enhancements (SAS) Category: Discretionary Milestones
RAG Status : GREEN | Report by Jill Nicoll for May 2016 Achievements in last period
Issues
Next Steps
| ||||||||||||||||
FIN110 (AP56-015) Coldfusion upgrade for finance applications Category: Compliance Milestones
RAG Status : AMBER | Report by Ben Armstrong for May 2016 Achievements this period
Issues
Next steps
| ||||||||||||||||
FIN111 (AP56-036) eExpenses enhancements Category: Discretionary Milestones RAG Status : BLUE (suspended) | Report by Dawn Holmes for May 2016 This project is now suspended until 16/17 | ||||||||||||||||
FIN112 Strategic Review of Financial Review Category: Funded Milestones
RAG Status : GREEN | Report by Dawn Holmes for May 2016 Achievements this period
Issues
Next steps
| ||||||||||||||||
FIN113 (AP56-017) Migrate JAMS & eTime applications Category: Compliance Milestones
RAG Status : RED | Report by Anne Mathison for May 2016 Achievements:
Issues:
Next Steps:
| ||||||||||||||||
FIN114 (AP56-039) Financial documents revitalisation (Version One) Category: Discretionary Milestones
RAG Status : AMBER | Report by Nikki Hackett-Reed for May 2016Achievements this periodProject Brief signed off and WIS approved Business Requirement Definition W/S/ TO BE review/ Documentation Look & Feel review/BRD Signed off Implementation plan and test scripts written John Milliken engaged to review documentation cleanse/amendments
ABS resource challenges (leavers), John Miliken Annual Leave (20/6-01/7) and Gordon Forbes Annual Leave (04/07-15/07) have all impacted on our proposed support requiremetns for delivery prior to 15/16 year end. UAT period, whilst still over a 2 week period has been reduced to 5 days instead of 10 days. Handover to production may be impacted GO LIVE still with in 15/16 (29/07) but Closure 16/17 (30/08 ) IssuesIssue 5 (Risk5) - 03/06/16 - Due to ABS resource challenges the period in which John Miliken from ABS can support us for concurrent Build/ Integration/ Acceptance / Delivery has been extended to 21/07 - 27/07 which means we will not close until 30/08 and enter 16/17. Next StepsNone in June |
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN105 (AP45-019) Financial reporting changes for FRS102 David Watters Category: Compliance | Project closed 07/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin105/completion_report |
FIN102 (In-year)eExpenses Phase 2 Dawn Holmes Category: Discretionary (Sponsor Funded) | Project closed 11/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin102/completion_report |
FIN101 (AP23-003)SSO/Launchpad Phase 2 Morna Findlay Category: Discretionary | Project closed 18/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin101/completion_report |
FIN086 (AP23-004) ePay Reconciliation Category: Compliance | Project closed 07/10/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin086/completion_report |
FIN081 (AP12-024) Document Management for Finance Applications Category: Discretionary | Project withdrawn due to insufficient budget |
FIN106 (AP45-925) Albacs Replacement Category: Compliance | Project Closed 31/05/2016 Link to completeion report https://www.projects.ed.ac.uk/project/fin106/completion_report |