Report for May 2016

Report Date
May 2016

Report compiled by Dawn Holmes (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)

Section 1: Programme Commentary, RAG and Resources Update

Section 2: Projects Not Started

Section 3: Projects In Progress

Section 4: Closed or Withdrawn Projects

Section 1: Programme Commentary, RAG and Resources Update

FIN106 ALBACS Replacement  successfully completed this month.  Completion report linked in section 4.

FIN114 Financial Documents Revitalisation (Version One) and FIN112 Strategic Review of Financial Systems are both now expected to span into early 16/17.  This will impact on the planned project work for 16/17 by approximately 20 days and funding options are still to be discussed with the relevant Project Sponsors.

Other project work is expected to complete in June/July as planned and the programme budget is in a healthy position with adequeate coverage for the remaining planned work.

 

 

 

Section 2: Projects Not Started

 

Project InfoProgramme Managers Commentary

AP45-020

Estates & Buildings - Finance interface requirements

Core funded

Planning - Aug 2016

Delivery - Jan 2017

 RAG Status : GREEN

This is now planned for 16/17

AP56-016

eFinancials upgrade

Core funded

Planning - Aug 2016

Delivery - May 2017

 RAG Status : AMBER

ABS still have not confirmed the release date for v5 of eFInancials so all of this project has now been moved out by a further month to start in 16/17

AP56-054

Finance BI improvement

Core funded

Planning - Aug 2016

Delivery - Apr 2017

 RAG Status : RED

The project start date has been moved out to start in August at the request of the Project Sponsor so that it follows on from the FInancial Strategic Review

 

Section 3: Projects in Progress

 

Project InfoProject Managers Commentary

FIN104 (AP45-018)

Supporting scan & destroy policy using Serengeti

Category: Discretionary

Milestones

Target dateTitle
01-Jul-2016End of analysis
15-Jul-2016Closure

RAG Status : AMBER

Report by Dawn Holmes for May 2016

Achievement this period

  • Analysis of 'as is' process is complete
  • Statistics compiled on Serengeti reliability

Issues

  • The analysis has been more complex than anticipated as the current processwas not well understood or documentated.  This has resulted in a need for an additional 4 days budget to complete the analysis summary.
  • Due to annual leave and resource conflicts from higher priority projects, the analysis sign-off and closure have been moved out by 2 weeks.
  • As a result of these two issues the project is being reported on AMBER

Next steps

  • Complete write-up of summary & recommendations document

FIN106 (AP45-925)

ALBACS Replacement

Category: Compliance

Milestones

N/A

RAG Status : BLUE

Report by Anne Mathison for May 2016

Achievements:

  • 3 months successfully running with C-Series
  • Decommissioned Albacs
  • Tidy up of Albacs completed and removal from servers
  • Completed Albcas Closure
  • Albacs Replacement Closure to WIS 3-Jun-16

Issues

  • None

Next Steps:

  • Project Closed

FIN108 (AP56-042)

Essential Enhancements (FIS)

Category: Discretionary

Milestones

15-Jul-2016

Deployment Sign-off Review of final enhancements batch

22-Jul-2016

Closure Sign-off Review

RAG Status : RED

  • The RAG status shows as RED, to reflect that the scope and budget have changed within the last month. 
  • The current status of all RAG measures is GREEN.

Report by Jill Nicoll for May 2016

Achievements in last period

  • Build completed for Batch 3 Jira FIN108-13 (eTime - H2020 Print Preview for new Category/Tasks Types)
  • eFin Dev and Test issues resolved for Batch 3 Jira FIN108-2 (International Bank Validation (Phase 1) - Change of Hosting from UOE to Experian)
  • Batch 3 budget and scope extended, for the development of an eTime reporting universe, and to address a prioritised list of eExpenses / eAuthorisations Jiras transferred from FIN111.
  • Acceptance testing sign-off achieved for Batch 3 Jira FIN108-32 (Build eTime universe and Research FP7 report)

Issues

  • Finance have identified a number of critical enhancements required to eTime and eExpenses.  The top priority items from this list have been added to the project's scope.
  • To meet the added scope, 32 ring-fenced days have been added to the project's budget, from the Finance Programme (22 days from Balance row; 10 days from Project Planning row).
  • FPM Dev issues for Batch 3 Jira FIN108-26 (FPM v2.3 Configuration on Dev Environment) are not yet resolved.

Next Steps

  • Finance to provide business requirements for remaining Batch 3 Jiras
  • ISA and Finance to progress with Batch 3 deliveries

FIN109 (AP56-042)

Essential Enhancements (SAS)

Category: Discretionary

Milestones

15-Jul-2016

Deployment Sign-off Review of final enhancements batch

22-Jul-2016

Closure Sign-off Review

RAG Status : GREEN

Report by Jill Nicoll for May 2016

Achievements in last period

  • eFin password change applied in Dev (FIN109-8)
  • Acceptance testing sign-off achieved for eAuthorisations universe and reports (FIN109-10)
  • eFin BI access changes signed off in Live (FIN109-19)

Issues

  • UAT Testing on the eAuthorisations BI universe and reports extended beyond the planned sign-off and deployment date, and beyond the planned budget.
    • With the agreement of the Business Lead and the Programme Manager, the IS effort for this extension was transferred to FIN112.

Next Steps

  • Deploy eAuthorisations BI universe and reports to Live (FIN109-10)
  • Apply eFin password changes to Test (FIN109-8)

FIN110 (AP56-015)

Coldfusion upgrade for finance applications

Category: Compliance

Milestones

Target dateTitle
10-Jun-2016Project Delivery
08-Jul-2016Project closure

RAG Status : AMBER

Report by Ben Armstrong for May 2016

Achievements this period

  • The upgrades to the Web First and eStores applications were successfully deployed in their Cold Fusion 11 (CF11) Live Environments on 11th May
  • The upgrades to the Student Finance Channel and WPM applications were successfully deployed in their Cold Fusion 11 (CF11) Live Environments on 24th May

Issues

  • Project delivery date moved out by 3 weeks due to issues encountered with testing the Online Print Credit application, which has a dependency on EIT.  The change to dates was approved by the Sponsor, Programme Manager and WIS.  The issue was resolved and the Time RAG is shown as AMBER this month to reflect the change in dates but will revert to GREEN next month.

Next steps

  • Fix the issues found in the Student Finance Channel's Live environment following the ColdFusion deployment
  • Fix the outstanding issues found with the Time Allocation Survey and EIT applications' Live environments following their ColdFusion deployments
  • Migrate the TAS and EIT applications to Live in CF11
  • Confirm deployment sign off for all applications migrated by the project; this is scheduled for 21st June

FIN111 (AP56-036)

eExpenses enhancements

Category: Discretionary

Milestones

 RAG Status : BLUE (suspended)

Report by Dawn Holmes for May 2016

This project is now suspended until 16/17

FIN112

Strategic Review of Financial Review

Category: Funded

Milestones

Target dateTitle
30-Jun-2016Workshops complete
15-Jul-2016Action plans complete
29-Jul-2016Closure

RAG Status : GREEN

Report by Dawn Holmes for May 2016

Achievements this period

  • 4 further workshops have taken place this month, ISG, SCE, MVM & Cash Office
  • Workshop outputs written up & distributed for review
  • First draft analysis of workshop outputs reviewed with Business Leads
  • 6 additional workshops have been requested by the Project Sponsor, which are being arranged for June/July

Issues

  • Discussion held with Finance Business Leads regarding potentially reducting the budget asthere was still a substantial amount remaining to be used in 15/16 but due to the additional workshops this reduction is now not required.
  • It is proving difficult to schedule the additional workshops before the end of June due to the holiday season and financial year end.  There is a chance that the project may have to extend into 16/17 in order to complete all of the requested workshops or that the number of workshops will have to be reduced. This is still to be discussed with the Project Sponsor.

Next steps

  • Confirm and conduct remaining workshops
  • Complete analysis on remaining workshop outputs
  • Consolidate common themes to create action plans & quick wins

FIN113 (AP56-017)

Migrate JAMS & eTime applications

Category: Compliance

 Milestones

DateMilestone
10-Jun-2016Acceptance for eTime
13-Jun-2016Acceptance for JAMS
15-Jun-2016Live for eTime
22-Jun-2016LIVE for JAMS
29-Jun-2016DSOR for eTime
6-Jul-2016DSOR for JAMS
6-Jul-2016Closure

 RAG Status : RED

Report by Anne Mathison for May 2016

Achievements:

  • eTime TAD completed
  • JAMS TAD completed and updated (3-Jun)
  • Migrated eTime environment in DEV
  • DEV Build for eTime completed
  • Dev Tech resourcing bookings resolved
  • Migrate JAMS environment in DEV
  • Build JAMS in DEV
  • Migrated eTime environment in TEST
  • Migrate JAMS environment in TEST
  • Load balancer updated (Unix) for Dev and Test for JAMS and eTime
  • Revised Milestones and Budget approved

Issues:

  • Additional 15 days budget required to cover technical issues encountered in Dev, plus further delayed delivery & closure milestones, therefore the project is reported on RED this month

Next Steps:

  • eTime TAD updated (6-Jun)
  • Acceptance Test eTime in TEST
  • Acceptance Test JAMS in TEST
  • Live prep for eTime
  • Live prep for JAMS
  • Load balancer updated (Unix) for Live for JAMS and eTime
  • eTime LIVE
  • JAMS LIVE
  • DSOR for eTime
  • DSOR for JAMS
 

FIN114 (AP56-039)

Financial documents revitalisation (Version One)

Category: Discretionary

Milestones

Target date

Title

Complete

06/05/16

Planning

YES

29/07/16

Delivery

NO

30/08/16

Closure

NO

 RAG Status : AMBER

Report by Nikki Hackett-Reed for May 2016

Achievements this period

Project Brief signed off and WIS approved

Business Requirement Definition W/S/ TO BE review/ Documentation Look & Feel review/BRD Signed off

Implementation plan and test scripts written

John Milliken engaged to review documentation cleanse/amendments

 

ABS resource challenges (leavers), John Miliken Annual Leave (20/6-01/7) and Gordon Forbes Annual Leave (04/07-15/07) have all impacted on our proposed support requiremetns for delivery prior to 15/16 year end.

UAT period, whilst still over a 2 week period has been reduced to 5 days instead of 10 days.

Handover to production may be impacted

GO LIVE still with in 15/16 (29/07) but Closure 16/17 (30/08 )

Issues

Issue 5 (Risk5) - 03/06/16 - Due to ABS resource challenges the period in which John Miliken from ABS can support us for concurrent Build/ Integration/ Acceptance / Delivery has been extended to 21/07 - 27/07 which means we will not close until 30/08 and enter 16/17.

Next Steps

None in June

Section 4: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN105 (AP45-019)

Financial reporting changes for FRS102

David Watters

Category: Compliance

Project closed 07/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin105/completion_report

FIN102 (In-year)

eExpenses Phase 2

Dawn Holmes

Category: Discretionary (Sponsor Funded)

Project closed 11/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin102/completion_report

FIN101 (AP23-003)

SSO/Launchpad Phase 2

Morna Findlay

Category: Discretionary

Project closed 18/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin101/completion_report

FIN086 (AP23-004)

ePay Reconciliation

Category:  Compliance

Project closed 07/10/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin086/completion_report

FIN081 (AP12-024)

Document Management for Finance Applications

Category: Discretionary

Project withdrawn due to insufficient budget

FIN106 (AP45-925)

Albacs Replacement

Category: Compliance

Project Closed 31/05/2016

Link to completeion report https://www.projects.ed.ac.uk/project/fin106/completion_report

 

Documentation

Not available.