Report for June 2016

Report Date
June 2016

Report compiled by Dawn Holmes (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)

Section 1: Programme Commentary, RAG and Resources Update

Section 2: Projects Not Started

Section 3: Projects In Progress

Section 4: Closed or Withdrawn Projects

Section 1: Programme Commentary, RAG and Resources Update

 Key highlights & issues  this month: -

  • FIN108 Essential Enhancements (FIS) -  emerging risk that international bank validation issues in FPM may not beresolved before year end.  ABS are working on a fix for FPM as a priority. but this may not be available until early August. This will impact on 16/17 plans and budgets.
  • FIN110 Coldfusion Migratios - now delivered and project closing
  • FIN112 Strategic Review - emerging risk that not all workshops will be complete before year end.  This will impact on 16/17 plans and budgets
  • FIN113 Migrate eTime & JAMS - now delivered and project closing
  • FIN114 Version One - due to resource conflicts within both Finance and ABS, the project closure will now be extending into early August.  The project is forecasting a reduced budget estimate as the majority of the work needs to be undertaken by ABS
  • eFin upgrade - ABS have recently reported that the V5 beta version is now out with early adopters. Start date for our updgrade has been moved out to October.

 

The programme budget is reporting a surplus this month due to FIN108, FIN112 and FIN114 now forecasting to extend into 16/17 plus the reduced estimate for FIN114.  This surplus will be released to the CSG portfolio for re-prioritisaiton.

 

 

 

 

Section 2: Projects Not Started

 

Project InfoProgramme Managers Commentary

AP45-020

Estates & Buildings - Finance interface requirements

Core funded

Planning - Aug 2016

Delivery - Jan 2017

 RAG Status : GREEN

This is now planned for 16/17

AP56-016

eFinancials upgrade

Core funded

Planning - Oct 2016

Delivery - Jul 2017

 RAG Status : RED

ABS have now confirmed that eFinancial v5 Beta is out with early adopters.  As the perference is to allow a few month between early release and our upgrade, the project start date has now been moved out by a further 2 months to start in October.

AP56-054

Finance BI improvement

Core funded

Planning - Aug 2016

Delivery - Apr 2017

 RAG Status : GREEN

This is now planned for 16/17

 

Section 3: Projects in Progress

 

Project InfoProject Managers Commentary

FIN104 (AP45-018)

Supporting scan & destroy policy using Serengeti

Category: Discretionary

Milestones

Target dateTitle
15-Jul-2016Final analysis paper complete
29-Jul-2016Closure

RAG Status : GREEN

Report by Dawn Holmes for June 2016

Achievement this period

  • Write-up of summary & recommendations document completed & distributed for review.
  • Meeting booked with Project Sponsor for review/sign-off

Issues

  • None

Next steps

  • Project closure

FIN108 (AP56-042)

Essential Enhancements (FIS)

Category: Discretionary

Milestones

DateMilestone

01-Jul-2016

Delivery of final enhancements batch

15-Jul-2016

Deployment Sign-off Review of final enhancements batch

22-Jul-2016

Closure Sign-off Review

RAG Status : AMBER

Report by Jill Nicoll for June 2016

Achievements in last period

  • Live roll-out completed for New eStore for Tissue Culture Facility (Batch 3 Jira FIN108-9).
  • Live deployment completed for eTime universe and Research FP7 report (Batch 3 Jira FIN108-32)
  • UAT testing signed off for eTime - H2020 Print Preview for new Category/Tasks Types (Batch 3 Jira FIN108-13)
  • Testing signed off for FPM v2.3 - New Patch release to be applied to Dev (Batch 3 Jira FIN108-34)

 Issues

  • FPM Dev issues for FPM v2.3 Configuration on Dev Environment (Batch 3 Jira FIN108-26) are not yet resolved.  ABS has committed to providing a further patch
  • Following UAT sign-off, a new FPM Test issue arose for International Bank Validation (Phase 1) - Change of Hosting from UOE to Experian (Batch 3 Jira FIN108-2). Fix currently being tested in-house by FPM, issue raised as milestones may be in danger

Next Steps

  • ISA and Finance to complete remaining Batch 3 deliveries
  • Close project

 

The project status is given as Amber

 

FIN109 (AP56-042)

Essential Enhancements (SAS)

Category: Discretionary

Milestones

DateMilestone
01-Jul-2016Delivery of final enhancements batch
15-Jul-2016Deployment Sign-off Review of final enhancements batch
22-Jul-2016Closure Sign-off Review

RAG Status : GREEN

Report by Jill Nicoll for June 2016

Achievements in last period

  • eAuthorisations BI universe and reports deployed to Live (FIN109-10)
  • eFin password change applied in Test (FIN109-8). Testing signed-off 5/7/16

Issues

  • The project's budget is under strain because the actual effort required for the eFin password change work has been higher than estimated.
    • With the agreement of the Business Lead and the Programme Manager, the project budget will be balanced by transferring some of the completed effort on the eAuthorisations universe and report to FIN112.

Next Steps

  • Apply eFin password changes to Live (FIN109-8)
  • Close project

The RAG status is given as Green

FIN110 (AP56-015)

Coldfusion upgrade for finance applications

Category: Compliance

Milestones

Target dateTitle
08-Jul-2016Project closure

RAG Status : GREEN

Report by Ben Armstrong for June 2016

Achievements this period

  • Deployment Sign-Off confirmed for all applications by Project Team
  • Circulated project closure report for review and sign-off

Issues

  • None noted

Next steps

  • Close project

FIN111 (AP56-036)

eExpenses enhancements

Category: Discretionary

Milestones

 RAG Status : BLUE (suspended)

Report by Dawn Holmes for June 2016

This project is now suspended until 16/17

FIN112

Strategic Review of Financial Review

Category: Funded

Milestones

Target dateTitle
30-Jun-2016Workshops complete
15-Jul-2016Action plans complete
29-Jul-2016Closure

RAG Status : AMBER

Report by Dawn Holmes for June 2016

Achievements this period

  • A further 4 workshops were held this month - Research Grants, Accommodation Services, SCE Schools and MVM Schools.
  • Analysis work is well underway and draft information packs are being reviewed with Business Leads from Finance.
  • Work has started on the summary & recommendations analysis

Issues

  • HSS Schools have requested that their workshop be held in August, which is beyond the target milestone for completing the workshops.  A decision is needed from the Project Sponsor as to whether the project can continue into 16/17 (i.e. will funding be in place).  As this is likely to affect the timeline the project has been reported on AMBER status this month. This has been flagged to the Portfolio Manager.

Next steps

  • Gain agreement on remaining workshops and plan accordingly
  • Issue information packs
  • Complete summary analysis
  • Closure

FIN113 (AP56-017)

Migrate JAMS & eTime applications

Category: Compliance

 Milestones

Target DateTitle
06-Jul-16Closure
06-Jul-16DSOR for JAMS

 RAG Status : BLUE

Report by Anne Mathison for June 2016

Report Date:
June 2016

Achievements this period:

  • eTime TAD updated (6-Jun)
  • Acceptance Test eTime in TEST
  • Acceptance Test JAMS in TEST
  • Live prep for eTime
  • Live prep for JAMS
  • Load balancer updated (Unix) for Live for JAMS and eTime
  • eTime LIVE (22-Jun)
  • JAMS LIVE (21-Jun)
  • DSOR for eTime (28-Jun)
  • DSOR for JAMS (28-Jun)
  • Closure (4-Jul)
  • Issues:

  • None
  • Next Steps:

  • Closure (4-Jul) completed, so also added to achievements and project now closed

 

 

FIN114 (AP56-039)

Financial documents revitalisation (Version One)

Category: Discretionary

Milestones

Target date

Title

29/07/16

Delivery

30/08/16

Closure

 RAG Status : GREEN

Report by Nikki Hackett Reed for June 2016

Achievements this period

ABS resource challenges (leavers), John Miliken Annual Leave (20/6-01/7) and Gordon Forbes Annual Leave (04/07-15/07) have all impacted on our proposed support requirements for delivery prior to 15/16 year end.

UAT period, whilst still over a 2 week period has been reduced to 5 days instead of 10 days.

Handover to production may be impacted

GO LIVE still with in 15/16 (29/07) but Closure 16/17 (30/08 )

WIS approved but extending the project into next year is far from ideal as Finance have no budget to cover it, so completing as much of the Closure Report as possible in advance, closing as soon as possible after go-live etc

https://www.wiki.ed.ac.uk/display/insite/Applications+WIS+Notes+-+10+Jun...

15/16 - 16/17 review

Approved budget 50 days: Revised budget: 24 days

15/16 = 20.2 days

16/17 = 3.8 days

Issues

Issue 5 (Risk5) - 03/06/16 - Due to ABS resource challenges the period in which John Miliken from ABS can support us for concurrent Build/ Integration/ Acceptance / Delivery has been extended to 21/07 - 27/07 which means we will not close until 30/08 and enter 16/17.

https://www.projects.ed.ac.uk/project/fin114/issues/5

Next Steps

Concurrent Build, Integration, Acceptance and Deliver

Section 4: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN105 (AP45-019)

Financial reporting changes for FRS102

David Watters

Category: Compliance

Project closed 07/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin105/completion_report

FIN102 (In-year)

eExpenses Phase 2

Dawn Holmes

Category: Discretionary (Sponsor Funded)

Project closed 11/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin102/completion_report

FIN101 (AP23-003)

SSO/Launchpad Phase 2

Morna Findlay

Category: Discretionary

Project closed 18/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin101/completion_report

FIN086 (AP23-004)

ePay Reconciliation

Category:  Compliance

Project closed 07/10/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin086/completion_report

FIN081 (AP12-024)

Document Management for Finance Applications

Category: Discretionary

Project withdrawn due to insufficient budget

FIN106 (AP45-925)

Albacs Replacement

Category: Compliance

Project Closed 31/05/2016

Link to completeion report https://www.projects.ed.ac.uk/project/fin106/completion_report

 

Documentation

Not available.