Report for July 2016 - draft in progress
- Report Date
- July 2016
Report compiled by Dawn Holmes (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)
Section 1: Programme Commentary, RAG and Resources Update
Section 2: Projects Not Started
Section 3: Projects In Progress
Section 4: Closed or Withdrawn Projects
Section 1: Programme Commentary, RAG and Resources Update
- FIN104 Scan & destroy closed this month
- FIN108 Essential enhancements (FIS) will now extend into 16/17 to allow completion of compliance work for international bank validation
- FIN109 Essential enhancement (SAS) closed this month
- FIN110 Coldfusion migrations closed this month
- FIN112 Strategic Review will now extend into 16/17 to completion of final workshop
- FIN113 Migrate eTime & JAMS closed this month, completing under budget
The programme is showing a surplus of days for the end of year due to FIN113 completing under-budget, FIN114 forecasting to be under-budget, plus unused days from the programme management allocation.
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
AP45-020 Estates & Buildings - Finance interface requirements Core funded Planning - n/a Delivery - n/aJan 2017 RAG Status : BLUE | This is no longer required & will be withdrawn |
AP56-016 eFinancials upgrade Core funded Planning - Oct 2016 Delivery - Jul 2017 RAG Status : GREEN | This is now planned for 16/17 |
AP56-054 Finance BI improvement Core funded Planning - n/a Delivery - n/a RAG Status : GREEN | This is now planned for 16/17 |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||
FIN104 (AP45-018) Supporting scan & destroy policy using Serengeti Category: Discretionary Milestones N/A as project now closed RAG Status : BLUE | Report by Dawn Holmes for July 2016 Achievements this period
Issues
Next steps
| ||||||||||||
FIN108 (AP56-042) Essential Enhancements (FIS) Category: Discretionary Milestones
RAG Status : RED* *Please note: The above red RAG status simply denotes that the project's milestones have changed over the course of this month. The current status of all RAG measures is GREEN. | Report by Jill Nicoll for July 2016 Achievements in last period
Issues Issues have still to be resolved in the migration of International Bank Validation to external hosting:
The Bank Validation migration is a compliance requirement. It is therefore not possible to close this project until a solution has been reached, and the new hosted software has been deployed to Live, for both eFinancials and FPM.
In accordance with this agreement, the two Bank Validation related Jiras have been moved into a new Batch 4, which will carry forward into 2016-17, to support remedial activity by Experian and ABS. These Jiras are:
Next Steps
| ||||||||||||
FIN109 (AP56-042) Essential Enhancements (SAS) Category: Discretionary Milestones N/A RAG Status : BLUE | Report by Jill Nicoll for July 2016 Achievements in last period
Issues
Next Steps
| ||||||||||||
FIN110 (AP56-015) Coldfusion upgrade for finance applications Category: Compliance Milestones N/A RAG Status : BLUE | Report by Ben Armstrong for July 2016 Achievements this period
Issues
Next steps
| ||||||||||||
FIN111 (AP56-036) eExpenses enhancements Category: Discretionary Milestones RAG Status : BLUE (suspended) | Report by Dawn Holmes for July 2016 This project is now suspended until 16/17 | ||||||||||||
FIN112 Strategic Review of Financial Review Category: Funded Milestones
RAG Status : AMBER | Report by Dawn Holmes for July 2016 Achievements this period
Issues
Next steps
| ||||||||||||
FIN113 (AP56-017) Migrate JAMS & eTime applications Category: Compliance Milestones RAG Status : BLUE |
Report by Anne Mathison for July 2016Achievements this periodProject closed 6-Jul-16 | ||||||||||||
FIN114 (AP56-039) Financial documents revitalisation (Version One) Category: Discretionary Milestones
RAG Status : GREEN | Achievements this periodReview of User Acceptance Testing plan: signed off Review of Implementation Plan: signed off Review of Closure report: signed off Review of Deployment Checklist: not required: signed off Concurrent Build, Test, Integration - ongoing Deploy to LIVE - ongoing IssuesNone Next StepsJohn Miliken (ABS) to provide a Customer System Design Document post GO LIVE Closure |
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN105 (AP45-019) Financial reporting changes for FRS102 David Watters Category: Compliance | Project closed 07/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin105/completion_report |
FIN102 (In-year)eExpenses Phase 2 Dawn Holmes Category: Discretionary (Sponsor Funded) | Project closed 11/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin102/completion_report |
FIN101 (AP23-003)SSO/Launchpad Phase 2 Morna Findlay Category: Discretionary | Project closed 18/09/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin101/completion_report |
FIN086 (AP23-004) ePay Reconciliation Category: Compliance | Project closed 07/10/2015 Link to completion report https://www.projects.ed.ac.uk/project/fin086/completion_report |
FIN081 (AP12-024) Document Management for Finance Applications Category: Discretionary | Project withdrawn due to insufficient budget |
FIN106 (AP45-925) Albacs Replacement Category: Compliance | Project Closed 31/05/2016 Link to completeion report https://www.projects.ed.ac.uk/project/fin106/completion_report |
FIN109 (AP56-042) Essential Enhancements (SAS) Category: Discretionary | Project closed 27/07/2016 Link to Completion Report https://www.projects.ed.ac.uk/project/fin109/completion_report |
FIN110 (AP56-015) Coldfusion upgrade for finance applications Category: Compliance | Project closed 18/07/2016 Link to completion report https://www.projects.ed.ac.uk/project/fin110/completion_report |
FIN104 (AP45-018) Supporting Scan & Destroy Using Serengeti Category : Discretionary | Project closed 28/07/2016 Link to completion report https://www.projects.ed.ac.uk/project/fin104/completion_report |
FIN113 (AP56-017) Migrate JAMS & eTime applications Category: Compliance | Project closed 6/07/2016 Link to completion report https://www.projects.ed.ac.uk/project/fin113/completion_report |