Report for July 2016 - draft in progress

Report Date
July 2016

Report compiled by Dawn Holmes (Programme Manager) for Liz Welch & Lee Hamill (Programme Owners)

Section 1: Programme Commentary, RAG and Resources Update

Section 2: Projects Not Started

Section 3: Projects In Progress

Section 4: Closed or Withdrawn Projects

Section 1: Programme Commentary, RAG and Resources Update

  • FIN104 Scan & destroy closed this month
  • FIN108 Essential enhancements (FIS) will now extend into 16/17 to allow completion of compliance work for international bank validation
  • FIN109 Essential enhancement (SAS) closed this month
  • FIN110 Coldfusion migrations closed this month
  • FIN112 Strategic Review will now extend into 16/17 to completion of final workshop
  • FIN113 Migrate eTime & JAMS closed this month, completing under budget

The programme is showing a surplus of days for the end of year due to FIN113 completing under-budget, FIN114 forecasting to be under-budget, plus unused days from the programme management allocation.

 

 

 

Section 2: Projects Not Started

 

Project InfoProgramme Managers Commentary

AP45-020

Estates & Buildings - Finance interface requirements

Core funded

Planning - n/a

Delivery - n/aJan 2017

 RAG Status : BLUE

This is no longer required & will be withdrawn

AP56-016

eFinancials upgrade

Core funded

Planning - Oct 2016

Delivery - Jul 2017

 RAG Status : GREEN

This is now planned for 16/17

AP56-054

Finance BI improvement

Core funded

Planning - n/a

Delivery - n/a

 RAG Status : GREEN

This is now planned for 16/17

 

Section 3: Projects in Progress

 

Project InfoProject Managers Commentary

FIN104 (AP45-018)

Supporting scan & destroy policy using Serengeti

Category: Discretionary

Milestones

N/A as project now closed

RAG Status : BLUE

Report by Dawn Holmes for July 2016

 Achievements this period

  • Summary analysis paper review with Project Sponsor and Business Lead
  • Final changes to summary analysis paper agreed and report signed-off
  • Findings from analysis passed to Serengeti service owner and Head of Production Management to take forward as ongoing support items
  • Project completion report produced
  • Project closed

Issues

  • None to highlight this period

Next steps

  • N/A as project now closed

FIN108 (AP56-042)

Essential Enhancements (FIS)

Category: Discretionary

Milestones

Target date

Milestone

17-Aug-2016

Batch 4 delivery

23-Aug-2016

Batch 4 deployment sign-off review

02-Sep-2016

Batch 4 closure

RAG Status : RED*

*Please note:  The above red RAG status simply denotes that the project's milestones have changed over the course of this month.  The current status of all RAG measures is GREEN.

Report by Jill Nicoll for July 2016

Achievements in last period

  • Live deployment completed for eTime - H2020 Print Preview for new Category/Tasks Types (Batch 3 Jira FIN108-13)
  • Live deployment completed for eExpenses enhancements (Batch 3b Jiras FIN108-36, FIN108-37, FIN108-38, FIN108-39, FIN108-44)
  • Deployment sign-off confirmed for Batches 1, 2, 3 and 3b
  • Project Closure confirmed for Batches 1, 2, 3 and 3b

 

Issues

Issues have still to be resolved in the migration of International Bank Validation to external hosting:

  • Finance colleagues have concerns about the warning messages returned by Bank Validation in eFinancials in Dev and Test
  • Bank Validation continues to fail in FPM in Dev and Test

The Bank Validation migration is a compliance requirement.   It is therefore not possible to close this project until a solution has been reached, and the new hosted software has been deployed to Live, for both eFinancials and FPM.

  • The Business Lead, Programme Manager and Portfolio Manager have therefore agreed that the project may be extended into the 2016/17 Planning Year, solely to support the ongoing issues with the Bank Validation.

In accordance with this agreement, the two Bank Validation related Jiras have been moved into a new Batch 4, which will carry forward into 2016-17, to support remedial activity by Experian and ABS.  These Jiras are:

  • International Bank Validation (Phase 1) - Change of Hosting from UOE to Experian (Jira FIN108-2)
  • FPM v2.3 Configuration on Dev Environment (Jira FIN108-26)

Next Steps

  • ABS and Experian to resolve Bank Validation issues

FIN109 (AP56-042)

Essential Enhancements (SAS)

Category: Discretionary

Milestones

        N/A

RAG Status : BLUE

Report by Jill Nicoll for July 2016

Achievements in last period

  • eFin password change deployed to Live (FIN109-8).
  • Deployment sign-off confirmed.
  • Closure sign-off confirmed.
  • Project closed.  

Issues

  • n/a  

Next Steps

  • n/a

FIN110 (AP56-015)

Coldfusion upgrade for finance applications

Category: Compliance

Milestones

N/A

RAG Status : BLUE

Report by Ben Armstrong for July 2016

Achievements this period

  • Ran project closure meeting with project team, with positive feedback on how the project was managed
  • Project approved for closure by WIS on 18th July

Issues

  • None noted

Next steps

  • None noted - project has closed

FIN111 (AP56-036)

eExpenses enhancements

Category: Discretionary

Milestones

 RAG Status : BLUE (suspended)

Report by Dawn Holmes for July 2016

This project is now suspended until 16/17

FIN112

Strategic Review of Financial Review

Category: Funded

Milestones

Target dateTitle
19-Aug-2016Workshops complete
26-Aug-2016Analysis & action plans complete
31-Aug-2016Closure

RAG Status : AMBER

Report by Dawn Holmes for July 2016

Achievements this period

  • Workshops held with USG and Procurement Office
  • Draft management summary report produced
  • Draft anaysis summary produced
  • Further workshop summary packs produced and distributed

Issues

  • Due to busy diaries, one of the workshops had had to be held in early August.  This has extended the planned milestone dates by one month and the project will now span into 16/17.  The overall budget is unaffected.

Next steps

  • Conduct the final workshop and incorporate the ouputs into the management summary and workshop summaries
  • Close the project

FIN113 (AP56-017)

Migrate JAMS & eTime applications

Category: Compliance

 Milestones

 RAG Status : BLUE

 

Report by Anne Mathison for July 2016

Achievements this period

Project closed 6-Jul-16

 

FIN114 (AP56-039)

Financial documents revitalisation (Version One)

Category: Discretionary

Milestones

Target date

Title

Complete

06/05/16

Planning

YES

05/08/16 (29/07/16)

Delivery

YES

30/08/16

Closure

NO

 RAG Status : GREEN

Achievements this period

Review of User Acceptance Testing plan: signed off

Review of Implementation Plan: signed off

Review of Closure report: signed off

Review of Deployment Checklist: not required: signed off

Concurrent Build, Test, Integration - ongoing

Deploy to LIVE - ongoing

Issues

None

Next Steps

John Miliken (ABS) to provide a Customer System Design Document post GO LIVE

Closure

Section 4: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

FIN105 (AP45-019)

Financial reporting changes for FRS102

David Watters

Category: Compliance

Project closed 07/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin105/completion_report

FIN102 (In-year)

eExpenses Phase 2

Dawn Holmes

Category: Discretionary (Sponsor Funded)

Project closed 11/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin102/completion_report

FIN101 (AP23-003)

SSO/Launchpad Phase 2

Morna Findlay

Category: Discretionary

Project closed 18/09/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin101/completion_report

FIN086 (AP23-004)

ePay Reconciliation

Category:  Compliance

Project closed 07/10/2015

Link to completion report https://www.projects.ed.ac.uk/project/fin086/completion_report

FIN081 (AP12-024)

Document Management for Finance Applications

Category: Discretionary

Project withdrawn due to insufficient budget

FIN106 (AP45-925)

Albacs Replacement

Category: Compliance

Project Closed 31/05/2016

Link to completeion report https://www.projects.ed.ac.uk/project/fin106/completion_report

FIN109 (AP56-042)

Essential Enhancements (SAS)

Category: Discretionary

Project closed 27/07/2016

Link to Completion Report https://www.projects.ed.ac.uk/project/fin109/completion_report

FIN110 (AP56-015)

Coldfusion upgrade for finance applications

Category: Compliance

Project closed 18/07/2016

Link to completion report https://www.projects.ed.ac.uk/project/fin110/completion_report

FIN104 (AP45-018)

Supporting Scan & Destroy Using Serengeti

Category : Discretionary

Project closed 28/07/2016

Link to completion report https://www.projects.ed.ac.uk/project/fin104/completion_report

FIN113 (AP56-017)

Migrate JAMS & eTime applications

Category: Compliance

Project closed 6/07/2016

Link to completion report https://www.projects.ed.ac.uk/project/fin113/completion_report

 

Documentation