Report for December 2017

Report Date
December 2017

Resource Position 

For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.

Forward Look

For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.

Section 2: Projects Not Started

Project Info Programme Managers Commentary

FIN121

eTime 17/18 (eSignature)

Planning - tbc

Delivery - tbc

 RAG Status : Amber

Awaiting confirmation from Finance if this project is to progress.  Issue escalated to Portfolio Manager.

Budget has been reduced to 60 days (Issue 2) as the project would not be able to be completed in 2017/18. 

FIN122

Decommissioning ABS Expense System 

Planning - tbc

Delivery - tbc

 RAG Status : GREEN

Discussion had with Finance and Application Management regarding dependencies with FIN 118.  Progress TBC

FIN123

Annual Finance Document Revitalisation 17/18

Planning - tbc

Delivery - tbc

 RAG Status : GREEN

This work is expected to be initiated in February 2018.  On-going discussions with FIS to progress.

 

 

Section 3: Projects in Progress

 

Project Info Project Managers Commentary

FIN118 (AP56-016)

eFinancials upgrade

Core funded

Target Date

Title

09-Jun-2017

End of Analysis / Design

01-Dec-2017

End of DEV / sign-off

27-Feb-2018

Readiness / Approval to Go-Live

12-Mar-2018

Go-Live

30-Apr-2018

Deployment Sign-off

31-May-2018

Project Closure

 

RAG Status: Amber

Report by Chris Orrell

 

FIN119 (AP67-024)

eInvoicing for Medium Suppliers

 

Target Date Title
10-Nov-2017 End of Planning
17-Nov-2017 Phase 1 – Engage with the Scottish Government Team
15-Dec-2017 Phase 1 - Analysis completed – in house / CIBR solutions
15-Dec-2017 Phase 1 - Analysis completed – Scottish Government solution
22-Dec-2017 Phase 1 – Decision made on solution(s) to implement
22-Dec-2017 Phase 1 – Suppliers identified / agreed
19-Jan-2018 Phase 2 – Create work packages / discrete backlog items
09-Feb-2018 Phase 2 – Deploy any technology required to implement the Scottish Solution
28-Feb-2018 Phase 2 – Time and budget allowing add the Suppliers to the solution(s)
16-Mar-2018 Phase 2 – Deployment sign off
30-Mar-2018 Project closure

 

 

RAG Status : GREEN

Report by Richard Bailey for December.

 

Achievements this Period

  • Reference calls held with Moray & South Lanarkshire Councils.  Feedback from both was positive about their experiences implementing and working with the Scottish Government Solution (SGS). 
  • Technical resource identified in order to draw up a Design Document in order to implement the SGS.
  • At this stage it is thought by the Project Team that the SGS will replace the in-house / CIBER eInvoicing Solution (to be confirmed).   
  • Initial contact made with Andrew McFarlane, regarding the capability of Serengeti to make sure it has the scalability / capacity to store the electronic invoices.  Initial thoughts are that as an enterprise solution this should be OK.

Issues

  • N/A

Next Steps

  • A second presentation by the SG Team to the Project Stakeholders is arranged for Wednesday 10th January. 
  • Make a decision on if the SG Solution meets requirements.
  • Get a Design Document drafted and determine  if the SGS is the only eInvoicing solution required at the University.
  • Re-address the milestones once the decision is made
  • Plan subsequent work packages (based on the decisions made / the Design Document).

FIN 120 (AP67-025)

Fraud protection for Accounts Payable

Target Date

Title

07-Nov-2017

Readiness / Approval to Go-Live

09-Nov-2017

Go-Live

16-Nov-2017

Deployment Sign-off

22-Dec-2017

Project Closure

 RAG Status : GREEN

 

Report by Emma McNab for December 2017

Achievements this Period

  • Completion report drafted

Issues

N/a

Next Steps

  • Completion report sign off.

 

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

FIN116 (AP67-022)

eTime - guaranteed hours

Category: Discretionary

Project Manager - Richard Bailey

Project closed 15th September 2017

Completion Report

FIN117 (AP56-054)

Finance BI Improvement

Category: Discretionary

 

Project Manager - Richard Bailey

Project closed 4th August 2017

Completion Report

FIN108 (AP56-042)

Essential enhancements (FIS)

Category: Discretionary

Project Manager - Emma McNab

Project Closed 6th October 2017

Completion Report

Documentation

Not available.