Report for December 2017
- Report Date
- December 2017
Resource Position
For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.
Forward Look
For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.
Section 2: Projects Not Started
| Project Info | Programme Managers Commentary |
|
FIN121 eTime 17/18 (eSignature) Planning - tbc Delivery - tbc RAG Status : Amber |
Awaiting confirmation from Finance if this project is to progress. Issue escalated to Portfolio Manager. Budget has been reduced to 60 days (Issue 2) as the project would not be able to be completed in 2017/18. |
|
FIN122 Decommissioning ABS Expense System Planning - tbc Delivery - tbc RAG Status : GREEN |
Discussion had with Finance and Application Management regarding dependencies with FIN 118. Progress TBC |
|
FIN123 Annual Finance Document Revitalisation 17/18 Planning - tbc Delivery - tbc RAG Status : GREEN |
This work is expected to be initiated in February 2018. On-going discussions with FIS to progress. |
Section 3: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||||||||
|
FIN118 (AP56-016) eFinancials upgrade Core funded
RAG Status: Amber |
Report by Chris Orrell |
||||||||||||||||||||||||
|
FIN119 (AP67-024) eInvoicing for Medium Suppliers
RAG Status : GREEN |
Report by Richard Bailey for December.
Achievements this Period
Issues
Next Steps
|
||||||||||||||||||||||||
|
FIN 120 (AP67-025) Fraud protection for Accounts Payable
RAG Status : GREEN
|
Report by Emma McNab for December 2017 Achievements this Period
IssuesN/a Next Steps
|
Section 4: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
FIN116 (AP67-022) eTime - guaranteed hours Category: Discretionary |
Project Manager - Richard Bailey Project closed 15th September 2017 |
|
FIN117 (AP56-054) Finance BI Improvement Category: Discretionary
|
Project Manager - Richard Bailey Project closed 4th August 2017 |
|
FIN108 (AP56-042) Essential enhancements (FIS) Category: Discretionary |
Project Manager - Emma McNab Project Closed 6th October 2017 |