Milestones:
Agreed at WIS - 30-Jul-2019, these need to be confirmed with Finance against the latest Project Proposal:
RAG Status : RED
|
Report By Richard Bailey for July 2019
For reference: SG = Scottish Government, SGS = Scottish Government Solution
Achievements this Period
- The Project remains escalated to the Senior Supplier and Head of Development Services
- The issues experienced with the application on TEST have been resolved.
- Acceptance testing has been completed by Finance against version dev_1.0.0-b77/dev_1.0.0-b78 of the eInvoicing application with no show stopping bugs identified
- A draft proposal to complete the project, which once agreed with Finance, will see the Project milestones that have been reset formalised and the Project status will reduce back to Amber
Issues
Next Steps
- Look to achieve sign off from Finance against the latest Project Proposal
- PICCL the change / agree revised budget sign off of the proposal is agreed
- Deploy eInvoicing application code to LIVE
- Start a pilot with the first Supplier (XMA Ltd)
|
FIN126
Core Funded
Essential Finance System Compliance Updates and Document Revitalisation
Milestones:
Proposed milestones are:
| Stage |
Milestone |
Due Date |
Complete |
| Plan |
(A) Signed Letter of engagement
|
20-March-2019 |
Yes |
| Plan |
Planning Complete (Project Brief) |
03-May-2019 |
Yes |
| Analyse |
(B) Business Analysis Complete |
07-June-2019 |
Yes |
| Execute |
(A) Completion of For:sight Proof of Concept phase |
14-June-2019 |
No |
| Analyse |
Re-Planning Post Compliance (Phase (B)) Scoping |
14-June-2019 |
No |
| Build |
(B) Build Complete |
28-June-2019 |
No |
| Accept |
(B) Acceptance Testing Complete |
05-July-2019 |
No |
| Deliver |
(A) Purchase of Arkk, For:sight bridging software |
19-July-2019 |
No |
| Deliver |
(B) Deploy to Live |
19-July-2019 |
No |
| Close |
Project Closure |
02-Aug-2019 |
No |
RAG Status: AMBER
|
Report By Ken Miller for July 2019
Achievements in Last Period
Work Stream (A)
- Arkk addressing a number of configuration issues between For:sight and Finance reports. Headway being made but not yet in a position to complete a comparison VAT return.
Work Stream (B)
- Completion of analysis of requirements capture.
- Requirements forwarded to Advanced for their review.
- TestRail set up for initial "As is" and post development UAT.
- "As is" testing completed successfully.
- Advanced consultant on site 17/18 July. Completed updates as requested.
- UAT undertaken via TestRail. A number of issues raised regarding the work undertaken.
Issues
- It has been reported that we may require a new legal contact. This needs confirmed so that impact on the project can be minimised.
- Work streams require milestones updated to reflect revised schedule.
Next Steps
Work Stream (A)
- Arkk to address outstanding configuration issues.
- Dual run of For:sight output against present process to be undertaken for the last quarter.
- Complete and sign off UAT.
- DPIA to be addressed once UAT has been signed off.
Work Stream (B)
- Completion review of post development issues.
- Liaise with Advanced regarding resolution of outstanding issues.
|
FIN127
Finance General Data Protection Regulation (GDPR)
Core Funded
Milestones
RAG Status : AMBER
|
Report By Ken Miller for July 2019
Achievements in Last Period
- Initial review of Finance artefacts completed with regards identification of GDPR data.
- Progress meeting with Finance highlighted a number of applications that had not been included in initial scope of project. Confirmation of project scope to be undertaken.
Issues
- Nicola Henderson has been assigned to the project as BA to replace Chimezie Umeh who is no longer at the University.
Next Steps
-
Confirm projects that should be in scope of project.
-
Completion of GDPR compliance analysis phase.
-
Re-planning meeting based upon GDPR compliance analysis results to confirm revised schedule and scope of project to be carried into 2019/20.
|
FIN128
FPM Upgrade
Core Funded
Milestones
RAG Status : RED
|
Report By Kevin Hone for July 2019
Achievements in Last Period:
- Focus has been the provision of on-going support for User Acceptance Testing (UAT).
- Preparations for implementation.
Issues:
- Some faults have been found during UAT, none of which are considered to be showstoppers.
- UAT is taking longer than planned. Finance focus is presently on completing the FIN119 project as a priority.
- Finance have advised to postpone the planned go-live date of the 13th August.
Next Steps:
- To re-plan an implementation date after completion of UAT. Due to the timelines involved with that of implementing FIN119, this could now follow the September change freeze.
|
FIN129 - PCI DSS Audit
Core Funded
| Project Initiation Complete |
22/04/19 |
| Project Planning Complete |
07/06/19 |
| Workshop 1 - Scope Complete |
27/05/19 |
|
Workshop 2 - Actions Complete
|
12/06/19
|
|
Workshop 3 - Options Complete
|
27/06/19
|
|
Workshop 4 - Recommendations
|
10/07/19 |
| Project Delivery Sign-off |
26/07/19
|
| Project DSOR Sign-off |
02/08/19
|
RAG Status : AMBER
|
Report By Kevin Hone for July 2019
Achievements in Last Period:
- All planned workshops have now been held.
- A Wiki page has been updated with known detail for the Card Payment Gateway and VOIP.
- All Finance questions asked have been answered.
Issues:
- A recommendations paper being written by Finance has yet to be concluded.
Next Steps:
- To re-plan project closure.
- To raise change request for time and end date. (Delivery and DSOR to be targeted for 23/08).
|