Report for June 2020

Report Date
June 2020

Resource Position

 

Forward Look

 

 

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

PSO replacement

Discussions are progressing to confirm a requirements specification to be used for sourcing quotes

 

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN127

Finance General Data Protection Regulation (GDPR)

Core Funded

Milestones

 

RAG Status : AMBER

Report By Emma McNab for June 2020

Achievements in Last Period:

  • Progressed analysis of systems within current scope of the project.

Issues

  • The revised number of systems that fall within the scope of the project has resulted in the project being a lot more complex than the original brief estimated.
  • Alignment and expectations of cleansing of historic data within systems especially those being replaced by People and Money inconsistency.  (Issue 13) 
  • The current Covid-19 situation has made data gathering more challenging (although it is still being progressed)

Next Steps

  • Finalise analysis of systems within current scope of the project.

  • Prioritise systems which require DPIA to be undertaken and assign responsibility

 

FIN130

Essential Updates to Finance Systems for Security

Core Funded

Milestones

Stage Milestone Due Date Complete
Plan Planning 03-Apr-2020 Yes
Analyse Analysis Review 15-Apr-2020 Yes
Analyse Analysis Complete 01-May-2020        Yes
Design Design Complete 08-Jun-2020 Yes
Build Build Complete 12-Jun-2020 Yes
Integrate       Integration Testing Complete        26-Jun-2020 Yes
Accept Acceptance Complete 10-Jul-2020 No
Deliver Delivered 17-Jul-2020 No
Close DSOR 24-Jul-2020 No
Close Closure 31-Jul-2020 No

 

RAG Status : Green

Report By Kevin Hone for June 2020

 

 

Achievements

  • Business Requirements Document and 3rd party development costs agreed.
  • 3rd party build complete and presently undergoing User Acceptance Testing.

Issues

  • None.

Next Steps

  • Completion of User Acceptance Testing.
  • Project Implementation and closure.

 

 

 

 

FIN132

HR and Payroll Annual Maintenance 19/20

Core Funded

Milestones

RAG Status :

No milestones

Report By Anne Mathison for June 2020

Achievements

  • Replaned and completed Phase 3 Post Budget Milestone
  • Replaned Project Closure Milestone
  • Phase 3 Post Budget Milestone signoff completed
  • HRDEV and HRTEST clones completed
  • Closure report circulated

  • Closure report comments received and report updated
  • Closed project FIN132

  • Agreed P60 action

    • testing, 

    • printing and

    • posting will be covered by Payroll when they have access to Charles Stuart House again

Issues

  • No issues

Next Steps

  • No next steps

Project RAG status of BLUE

 

FIN134

C-Series Upgrade

Core Funded

Milestones:

Stage Milestone Due Date Complete
Plan Planning Complete 10-Apr-2020 Yes
Execute       Wider Engagement Complete       20-Apr-2020 Yes
Deliver Development Complete 01-May-2020       Yes
Deliver PT-X switch-on 08-Jun-2020 Yes
Execute Testing Complete 23-Jun-2020 Yes
Deliver Project Delivered 26-Jun-2020 Yes
Deliver DSOR 03-Jul-2020 Yes
Deliver C-Series Decommission 10-Jul-2020 No
Close Project Closure 24-Jul-2020 No

 

RAG Status : Green

 

Report By Kevin Hone for June 2020

Achievements:

  • Project delivered.

Issues:

  • None.

Next Steps:

  • Monitor July payment runs using PT-X.
  • C-Series Decommission.
  • Project closure.

 

 

 

 

 

 

 

 

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

FIN118 (AP56-016)

eFinancials upgrade

 

Closure Report

FIN123 (AP56-016)

Annual Finance Document Revitalisation 17/18

Closure Report

FIN125

Media Production for Annual Report and Accounts    

 

Closure Report

FIN126

Essential Finance System Compliance Updates and Document Revitalisation

 

Closure Report

FIN128

FPM Upgrade

 

Closure Report

FIN131

Pension Scheme Changes

 

Withdrawal Report

FIN132

HR & Payroll Annual Maintenance 19/20

 

Closure Report

FIN133

Corporate Planner Upgrade

Closure Report

 

FIN119

eInvoicing

 

 

 

Closure Report
Programme Status
Has formal escalation taken place?
No

Documentation

Not available.