Report for August 2020

Report Date
August 2020

Report compiled by Andy Stewart  (IS Apps Programme Manager) for Candice Schmid (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

During August 

The overall programme budget has been set as follows

Project  Days Allocated 
HAS008 - eOPAS Upgrade  12
HASP01 - Programme Management  6

 

There has been very little project activity this month;

  • The Health Passport Improvements project was closed 
  • The only remaining project, HAS008, is currently suspended.  This is scheduled to recommence in October 2020

Forward Look

Resource Position 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

 

 Section Three: Projects in Progress

 

Project Info Project Managers Commentary

HAS008

eOPAS Upgrade 

Category: Discretionary

Milestone

Milestone Due Date
Project Resumption  05-Oct-20
Complete MJog installation on Test  16-Oct-2020
Sign-Off MJog User Acceptance Testing 13-Nov-2020
Deploy MJog to Live 23-Non-2020
Sign-Off DSOR 07-Dec-2020
Closure 18-Dec-2020

 

RAG Status: Suspended 

Report by Andy Stewart for August 2020

Achievements this Period

  • MJog
    • MJog have advised that the updated software is scheduled to be delivered by the end of September 
    • Request to MJog to recommence the installation on the Test environment w/c 12th October 

Issues 

  • No issues 

Next Steps 

  • Confirm upgrade schedule with MJog
  • Project suspension to be lifted w/c 5th October 

 

  Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary
HAS009 Health System Passport Improvements 

The project was closed in August 2020

Closure Report 

Closure 

 

 

 

Section Five: Programme Risks

Date Updated Risk Ref. Programme Risks RAG Status Risk Owner
02/09/20 2

Disruption from the current Novel coronavirus (Covid-19) outbreak

 Amber Candice Schmid

 

 

Section Six : Programme Meeting Minutes

The minutes from the programme meetings since July 2018 can be located on the Health and Safety SharePoint site

 

Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No