Report for February 2021

Report Date
February 2021

Section One: Programme Commentary, RAG and Resources Update

Commentary

  • The programme's status is GREEN with all started projects successfully completed.
  • This month the programme has moved the start date of the HESA 20/21 project out to April as if the P&M HESA Hub is ready, then the Staff Return for 20/21 will be completed using that functionality.
  • 3 year planning has also progressed this month
  • The programme may be affected by the Coronavirus risk as noted at Portfolio level

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

Forward Look - February 2021

Resources to end February 2021

Section Two: Projects Not Started 

 

Project Info Programme Manager's Commentary
HRS099 HESA Staff Return 2020/21 Start 1st April 2021

Section Three: Projects in Progress

Project Info 

 Project Managers Commentary

No Open projects to report progress on 

 

N/A

 

Section Four: Closed or Withdrawn Projects

 

 

Project Info Project Managers Commentary
HRS097 HR/HESA Staff Return 2018/19

This project closed on 6 November 2019

HRS096 GDPR Updates for eRecruitment

This project closed on 22 November 2019

 

HRS098 HESA Staff Return 2019/20

This project closed on 4 December 2020

AttachmentSize
Image icon resources_feb_21.png48.21 KB
Image icon forward_look_feb_2021.png25.8 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No