Report for September
- Report Date
- September 2013
Nikki Stuart (IS Apps Programme Manager) for Eilidh Fraser, Gordon Forbes (Programme Owners)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS073 - PDF Issue remains, although interim fix is in place to allow users to generate PDFs. The Board have agreed that if the new PDF screen to be released by Core is tested and signed off then this project can progress to closure.
HRS072 - Awaiting confirmation from Payroll that HMRC have accepted the final report to be submitted for the September PAYE return. Project Closure documentation is ready for submission on confirmation.
HRS071 - A number of last minute changes were needed before the data would pass the HESA Schema and Business rule checks. This work is complete but has impacted the estimate. There is a risk that HESA will request that a further change is made to accomodate for data not held for casual staff.
HRS075 - Project Brief has been drafted and will be sent to stakeholders for review once the September RTI PAYE submission is complete (HRS072).
Staff Development Procurement and Implementation - Proposal withdrawn for 13/14 to be resubmitted as part of the 14/15 planning round.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP34-025 eRecruitment Phase 2 (Redeployment and Talent Pool) Funded Planning - October 2013 Delivery - July 14 RAG Status GREEN | Plan Business Consultations are running through to end July. This project cannot start until clear agreement has been reached on how to proceed. The eRecruitment Project Board has requested that the eRecruitment team review the high level plan for Phase 2 and the requested eRecruitment efficiency review to present a plan for the September Project Board.
Dependencies Business Consultations complete and policy decisions agreed with all stakeholders |
AP34-023 HR & Payroll Reporting Tool Compliance Planning - January 2014 Delivery - July 2014 RAG Status GREEN | Plan
Dependencies Ongoing work for eRecruitment and HESA testing will impact HR's ability to input to this project. Pensions and Payroll departments cannot undertake any work on this in August 2013 due to leave commitments. depending on when the Annual Maintenance project starts this could impact availability of business resources. |
AP34-022 HESA Staff Return 13/14 Compliance Planning - February 2014 Delivery - August 2014 RAG Status GREEN | Plan
Dependencies HESA have indicated that as the changes for 12/13 were substantial that changes for 13/14 will be minimal. This will not be certain until HESA release details of any required changes. |
AP34-024 Moving HR Databases (R12 /eRecruitment) to New Infrastructure Compliance Planning - October 2013 Delivery - December 2013 RAG Status GREEN | Plan Head of Production Management (IS Apps) has indicated that this Oracle HR & Payroll migration should be completed before the Family pack patching for HR & Payroll Annual Maintenance 13/14.
Dependencies eRecruitment migration will need to be co-ordinated with Core should they need to undertake any updates to the application configuration. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||
HRS071 (AP23-006 ) HR HESA Staff Return 12/13
Category: Compliance
Milestones
RAG Status AMBER
| Report by Nikki Stuart for September 2013 Achievements in last period:
Issues:
Next Steps: IS team: support HR to ensure that the HESA submission can be made as required Review last minute changes made after the final extract and update the extract code to ensure that these are included in the live code for future years. Business: Confirm HESA response regarding the LOCLEAVE for casual staff Submit initial XML to HESA
| ||||||
Oracle HR & Payroll Annual Patching
Category: Compliance Milestones
RAG Status GREEN | Report by Anne Mathison for September 2013 Achievements in Last Period
Issues
Next Steps.
| ||||||
HRS073 eRecruitment Phase 1b
Category: Funded Milestones
RAG Status AMBER
| Report by Nikki Stuart for Septembert 13 Achievements in Last Period
Issues
Next Steps
| ||||||
HRS075 (AP34-021) HR & Payroll Annual Maintenance 13/14
Compliance Planning - October 2013 Delivery - May 2014 RAG Status GREEN | Report by Nikki Stuart for Septembert 13
Achievements in last period:
Issues:
Next Steps: Approval of Project Brief and initial plan |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Project Code HRS074 & AP23-053 Project Title Staff Development Procurement and Implementation | Report by Nikki Stuart It was agreed with HR that both the Staff Development Procurment and Implementation projects should be withdrawn. A revised proposal will be submitted during annual planning 13/14 which may cover a revised scope.
|
|