Report for March 2014
- Report Date
- March 2014
Nikki Stuart (IS Apps Programme Manager) for Margaret Ayers and Terry Fox (Programme Owners)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS075 - AMBER - Tax Year End patching and Business Processes completed but late patches released from Oracle for the 14/15 Financial Year have errored in DEV, Service request raised with Oracle for support. This has resulted in additional effort and impacts to the P60 updates.
HRS076 - GREEN - Data gathering complete and the initial draft of the Efficiencies Review report is with HR for review before circulating to the eRecruitment User Group and Project Board.
HRS077 - GREEN - Analysis with the three business areas underway to draft a prioritised list of compliance reporting issues.
HRS078 - AMBER - Issues encountered during DEV migration require documentation from supplier, this has resulted in delays to the previously planned milestones. Discussions are underway to obtain required documentation.
HRS079 - GREEN - RTI Full Payment Submission now outputting correctly following patching and configuration changes. Payroll have undertaken an extensive reconciliation process and the FPS will now be submitted to HMRC on Friday 11th April. The project will now move on to supporting the Auto-enrolement enhancements.
HRS080 - GREEN - Build has been delayed slightly due to a conflict with the Annual Maintenance work. Milestones have been re-planned as a result and the work is still expected to be complete before the June '14 target deadline.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP34-025 eRecruitment Phase 2 (Redeployment and Talent Pool) Funded Planning - April 2014 Delivery - March 2015 RAG Status GREEN | Plan Project Board agreed the high level plan at 4th February Board meeting Project Board subsequently approved the detailed estimates from Core and the project will start end April 2014.
Dependencies
|
AP34-022 HESA Staff Return 13/14 Compliance Planning - April 2014 Delivery - August 2014 RAG Status GREEN | Plan
Dependencies HESA have indicated that as the changes for 12/13 were substantial that changes for 13/14 will be minimal. This will not be certain until HESA release details of any required changes. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||
HRS075 (AP34-021) HR & Payroll Annual Maintenance 13/14 Compliance Milestones
RAG Status AMBER
| Report by Anne Mathison for March 14 Achievements this period
Issues
Next steps
| ||||||||||||||||||||
HRS076 eRecruitment Efficiencies Review Funded Milestones
RAG Status GREEN | Report by Dawn Nicholls for March 2014Achievements this period
Issues
Next steps
Further information on project activities can be seen in the project journal | ||||||||||||||||||||
HRS077 Improved Reporting from Oracle HR, Payroll and Pensions Compliance Milestones
RAG Status GREEN | Report by Steph Ruthven for March 2014Achievements in last period
Issues
Next Steps
| ||||||||||||||||||||
HRS078 (AP34-024) Moving HR Databases (R12 /eRecruitment) to New Infrastructure Compliance Current Milestones All require replanned
RAG Status AMBER
| Report by Anne Mathison for March 14 Achievements this period
Outstanding Issues
Next steps
| ||||||||||||||||||||
HRS079 RTI and AE Enhancements Funded Current Milestones
RAG Status GREEN | Report by Nikki Stuart for March 2014 Achievements this period
None Next steps
| ||||||||||||||||||||
HRS080 Capture Staff Levels in Oracle HR and Payroll Funded Current Milestones
RAG Status GREEN | Report by Nikki Stuart for March 2014 Achievements this period
The Annual Maintenance Project (HRS075) has encountered delays due to late release and issues with Oracle patches. This has resulted in a resource conflict with this project. Resources have been replanned, however, unresolved issues on HRS075 may result in further impact to this project. Next steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
HRS074 & AP23-053 Staff Development Procurement and Implementation | Report by Nikki Stuart It was agreed with HR that both the Staff Development Procurement and Implementation projects should be withdrawn. A revised proposal will be submitted during annual planning 13/14 which may cover a revised scope.
|
Oracle HR & Payroll Annual Patching 2012/13
| Report by Anne Mathison Project Closure was agreed in November 2013; Completion Report for HRS072 Closure Milestone Review |
HRS071 (AP23-006 ) HR HESA Staff Return 12/13 | Report by Nikki Stuart Project Closure was agreed in December 2013; Completion Report can be found at https://www.projects.ed.ac.uk/project/HRS071/completion_report |
HRS073 eRecruitment Phase 1b | Report by Nikki Stuart Project Closure was agreed in December 2013; Completion Report can be found at https://www.projects.ed.ac.uk/project/hrs073/completion_report |