Report for April 2014
- Report Date
- April 2014
Nikki Stuart (IS Apps Programme Manager) for Margaret Ayers and Terry Fox (Programme Owners)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS075 - AMBER - Oracle intend to release a further patch to resolve the issues with the Direct Earnings/HR Global patches. P60 work is completing through testing and is on target for delivery to LIVE by end May.
HRS076 - GREEN - final report with HR for review, delay to eRecruitment Project Board means that the full review by the PB has been delayed. This should not delay project closure.
HRS077 - GREEN - Analysis completed and further information requested from HR, Payroll and Pensions to support design decisions.
HRS078 - AMBER - discussions continuing with Core to agree migration path, project under replanning.
HRS079 - GREEN - Additional funding confirmed by CSG to ensure that the remaining Autoenenrolment and EPS activities can be completed.
HRS080 - GREEN - Build continuing and Peer testing planned for May.
AP34-025 - Project Board decision to delay this work until after the eRecruitment Database migration and ongoing support activities are completed.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP34-025 eRecruitment Phase 2 (Redeployment and Talent Pool) Funded Planning - June 2014 Delivery - May 2015 RAG Status GREEN | Plan Project Board agreed to delay Phase 2 until after the completion of the database migration, exepected June 2014.
Dependencies
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||
HRS075 (AP34-021) HR & Payroll Annual Maintenance 13/14 Compliance Milestones
RAG Status AMBER
| Report by Anne Mathison for April 14 Achievements this period
Issues
Next steps
| ||||||||||
HRS076 eRecruitment Efficiencies Review Funded Milestones
RAG Status GREEN | Report by Dawn Nicholls for April 2014Achievements this period
Issues
Next steps
Further information on project activities can be seen in the project journal | ||||||||||
HRS077 Improved Reporting from Oracle HR, Payroll and Pensions Compliance Milestones
RAG Status GREEN | Report by Steph Ruthven for April 2014Achievements in last period
Issues
Next Steps
| ||||||||||
HRS078 (AP34-024) Moving eRecruitment database to New Infrastructure Compliance Current Milestones In the process of being re-planned
RAG Status AMBER
| Report by Anne Mathison for April 14 Achievements this period
Next steps
| ||||||||||
HRS079 RTI and AE Enhancements Funded Current Milestones
RAG Status GREEN | Report by Nikki Stuart for April 2014 Achievements this period
None Next steps
| ||||||||||
HRS080 Capture Staff Levels in Oracle HR and Payroll Funded Current Milestones
RAG Status GREEN | Report by Nikki Stuart for March 2014 Achievements this period
Issue with the data update API and advice being sought from Oracle. Next steps
| ||||||||||
HRS082 HR HESA Staff Return 13/14 Current Milestones under planning
RAG Status GREEN | Report by Anne Mathison for April 14 Achievements this period
Issues Next steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
HRS074 & AP23-053 Staff Development Procurement and Implementation | Report by Nikki Stuart It was agreed with HR that both the Staff Development Procurement and Implementation projects should be withdrawn. A revised proposal will be submitted during annual planning 13/14 which may cover a revised scope.
|
Oracle HR & Payroll Annual Patching 2012/13
| Report by Anne Mathison Project Closure was agreed in November 2013; Completion Report for HRS072 Closure Milestone Review |
HRS071 (AP23-006 ) HR HESA Staff Return 12/13 | Report by Nikki Stuart Project Closure was agreed in December 2013; Completion Report can be found at https://www.projects.ed.ac.uk/project/HRS071/completion_report |
HRS073 eRecruitment Phase 1b | Report by Nikki Stuart Project Closure was agreed in December 2013; Completion Report can be found at https://www.projects.ed.ac.uk/project/hrs073/completion_report |