Commentary

 HRS076 - closed in this reporting period

HRS075 - All mandatory patches in LIVE and no issues - project will now close

HRS077 - reports delayed due to leave and conflct with HRS075, Payroll reports descoped from project so all remaining deliverables are HR related. 

HRS078 - RED - Project progressing well but no budget to cover deficit, project will remain in red until closure. 

HRS079 - AMBER - Revised Project plan for the non mandatory patching for RTI and AE functionality requires effort in 14/15 to fit with the HRS075 patching and business commitments. If funding for the 10 days is not confirmed days may need to be reduced from elsewhere in the programme if this is the priority. 

HRS080 - AMBER - risk that there may be further conflict from HR HESA but minimal work to complete HRS080 build so low risk.

HRS081 - AMBER - Project Planning impacted by eRecruitment Migration. 

HRS082 - GREEN - HR HESA work progressing to plan with testing underway. 

AP34-025 - AMBER - Project Board representatives met with Core and it has been agreed that this project will not start until October at the earliest. 

 

 

 

 

 

 

 

 

 Section Two: Projects Not Started

 

 

Project InfoProgramme Manager's Commentary

 AP34-025

eRecruitment Phase 2 (Redeployment and Talent Pool)

Funded

Planning - October 2014

Delivery - July 2015

RAG Status

AMBER

Plan

Project will now not start until October 2014 at the earliest, project plan will need to be reviewed and replanned with discussions with User Group and Project Board. 

 

 

Dependencies

 

 

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

HRS075 (AP34-021)

HR & Payroll Annual Maintenance 13/14

 Compliance

Milestones

Target DateTitle
7-Jul-2014Direct Earnings Patch
22-Jul-2014Project Closure

RAG Status

GREEN 

 

 

Report by Anne Mathison for June 2014

Achievements this period

  • DEA1 patch signed off in DEV, and Tested and Signed off in TEST 2-Jun
  • DEA2 patch signed off in DEV, and Tested and Signed off in TEST 3-Jun
  • RTI Fix signed off in DEV, and Tested and Signed off in TEST 3-Jun
  • DEA1, DEA2 and RTI Fix deployed to LIVE on 7th July 
  • HMRC accepted Full Payment submission following LIVE updates and Direct Earnings process completed. 

Issues

  • None

Next Steps 

  • Project Closure 

HRS077

Improved Reporting from Oracle HR, Payroll and Pensions

Compliance

Report by Steph Ruthven for June 2014

 

Achievements in last period

  • First 2 HR reports complete

  • Payroll reports no longer required

Issues

  • None

Next Steps 

  • Finish HR report 3 and peer testing

HRS078 (AP34-024)

Moving eRecruitment database to New Infrastructure

Compliance

Milestones

 

 

DateMilestone
21-Jul-2014eRecruitment Acceptance Signoff
30-Jul-2014eRecruitment Deploy
12-Aug-2014eRecruitment Deployment Signoff Review and Closure

 

RAG Status

RED

 

Report by Anne Mathison for June 2014

 

Achievements this period 

  • Revised Technical Architecture Document
  • Completed DEV migration testing as well as any development fixes
  • DEV Migration complete
  • Completed Test implementation document
  • Migrate to TEST
  • Began Customer Acceptance Testing

Issues

  • Discussions with CORE on going regarding the Jump Start issue re Testing required for Acceptance completion
  • Revised estimate is over budget and has not been agreed within the HRS Programme, Programme Manager looking into

Next steps

 
  • Complete HR Acceptance testing
  • Agree down time with HR and Core (current plan 28-29 July)
  • Resolve remaining issues from Test Migration (1)
  • Finalise completed Technical Architecture Document and Operations Document
  • Migrate to LIVE
  • Support Live Deployment

HRS079

RTI and AE Enhancements

Funded

Current Milestones

to be planned following confirmation of remaining work  

RAG Status

AMBER

Report by Nikki Stuart for June 2014 

Achievements this period 

  1. Clone of TEST from LIVE 

  2. All Mandatory patches progressed through DEV, TEST and LIVE (through the HRS075 Annual Maintenance Project)

Outstanding Issues

Milestones to be planned following confirmation of any funding for 14/15 and agreement of LIVE target dates

 

Next steps

  1. Confirm if funding available for 14/15 patching

  2. Replan milestones to cover Rup7 patching for RTI and AE functionality

HRS080

Capture Staff Levels in Oracle HR and Payroll

Funded

Report by Nikki Stuart for June 2014

Achievements this period

  1. New Oracle field, BI field and API deployed to TEST

  2. Testing underway

Outstanding Issues

Successful Applicant interface update will not be progressed to TEST as Peer testing identified a further update. The developer is now progressing HR HESA work and this must be the priority until the HESA build is completed. 

Next steps

  1. Acceptance Sign off 

  2. Deploy New Oracle field, BI field and API to LIVE
  3. complete successful applicant build and progress to TEST and LIVE

 

 

HRS081

Migrate Oracle HR & Payroll Database to new Infrastructure

Compliance

Current milestones:

24-Jul-2014Planning Sign-Off

Plan

RAG Status:

AMBER

 

Report by David Watters for June 2014

Achievements in Last Period

  • Change of project manager
  • Work started on project planning

Issues

  • Planning milestone rejected by WIS
  • Unavailability of colleagues to discuss planning because of issues with HRS078

Next Steps

  • Submit planning milestone to WIS
  • Prepare and finalise project brief
  • Commence preparatory work for migration

 

HRS082

HR HESA Staff Return 13/14

Compliance

Report by Anne Mathison for June 2014

Achievements this period

  • Completed all known work on the 2013-14 HESA changes

  • Completed all known work on new 2013-14 HESA changes

  • Iterative Build Milestone achieved

  • All  changes are in Test

Issues

  • None

Next steps

  • Support  Acceptance testing
  • Complete the required project documentation
  • Deploy to Live

 

 

 

 

 

 

 

 

 

 

 

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

HRS074 & AP23-053

Staff Development Procurement and Implementation

Report by Nikki Stuart

It was agreed with HR that both the Staff Development Procurement and Implementation projects should be withdrawn. A revised proposal will be submitted during annual planning 13/14 which may cover a revised scope. 

 

 

 

 

HRS072 (AP23-005)

Oracle HR & Payroll Annual Patching 2012/13

 

Report by Anne Mathison

Project Closure was agreed in November 2013;

Completion Report for HRS072 Closure Milestone Review

 

HRS071 (AP23-006 )

HR HESA Staff Return 12/13

Report by Nikki Stuart

Project Closure was agreed in December 2013; 

Completion Report can be found at https://www.projects.ed.ac.uk/project/HRS071/completion_report 

HRS073

eRecruitment Phase 1b

Report by Nikki Stuart

Project Closure was agreed in December 2013; 

Completion Report can be found at https://www.projects.ed.ac.uk/project/hrs073/completion_report

 

HRS076

eRecruitment Efficiencies Review

Report by Dawn Nicholls

Project closure was approved on 4th June

Completion Report can be found at https://www.projects.ed.ac.uk/project/hrs076/completion_report