Report for October 2014
- Report Date
- October 2014
Susan McKeown (IS Apps Programme Manager) for Margaret Ayers (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS082 - CLOSED in this period.
HRS083 - GREEN - Enhancing Employment Removal of HTBN project opened this month with the brief due for sign-off on 07/11/14.
AP34-025 - AMBER- Project Board met on 31 October 2014 and approved that the team should prepare costed proposals for converting the character set and an upgrade. The enhancements will be postponed to 15/16. Budget to be confirmed.
AP45-042 - GREEN - Enhancing Employment Balance Row to be used for the analysis project starting late November.
AP23-053 - AMBER- This project will primarily be Project Services time developing a Business Case leading into a Procurement. Confirmation required on budget and approval required from University for project to proceed.
HRSP01 shows as overspent due to pre-planning for projects work for Enhancing Employment and eRecruitment. HRSPB2 The five day deficit has now been corrected by reducing the effort to complete this year to 25 days.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP34-025 eRecruitment Phase 2 (Redeployment and Talent Pool) Funded Planning - November 2014 Delivery - July 2015 RAG Status AMBER | Plan October Project Board agreed in principle that the activity for this year should be converting the character set and upgrading rather than the further enhancements noted in phase 2's proposal. The team are to produce costed proposals for the Board's consideration. The analysis of v20 is still to be completed so that communications to the User Group can include what can be expected in the upgraded version this year as there will be benefits for the users.
Dependencies Approval of costed proposals noted above from Project Board |
AP45-042 Enhancing Employment Balance Row Compliance Planning - November 2014 Delivery - May 2015 RAG Status GREEN | Plan This is the second project from AP45-042 in 14/15. This project will complete the analysis of the many employment contract profiles members can have in preparation for the technical implementation project in 15/16. The Business have already started mapping out the possible employment profiles.
Dependencies Resource availability in Project Services, HRS and local HR teams. |
AP45-063 HESA Staff Return 14/15 Compliance Planning -April 2015 Delivery - October 2016 RAG Status GREEN | Plan Project planned to start 30 March 2015. The programme is planning to complete carryover tasks from the HESA 13/14 project as the opportunity arises in Development Services between December 2014 and the start of this project.
Dependencies |
AP23-053 Learning Management Funded Planning - Feb 2015 Delivery - Jan 2016 RAG Status AMBER | Plan The work for 14/15 will predominantly be Project Services time assisting in the completion of the Business Case leading into a Procurement. HR are in the process of confirming the funding for this project.
Dependencies Business approval for project to proceed and confirmation of budget. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||
HRS083 (AP45-042) Enhancing Employment Removal of HTBN Compliance Milestones
RAG Status GREEN | Achievements this Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Project Code (AP-No) Project Title | Report by Project Manager Project Closure Milestone Achievement date Provide link to the project's Completion Report |
HRS078 (AP34-024) Moving eRecruitment Database to new Infrastructure | Report by Anne Mathison Project Closure Milestone Achievement date 22-Aug-14 Project's Completion Report is available on the website. |
HRS080 (AP34-924) Capture Staff Levels in Oracle HR and Payroll
| Report by Anne Mathison Project Closure Milestone achieved 30-Sep-14 Project's Completion Report |
HRS082 (AP34-022)HR HESA Staff Return 13/14 | Report by Anne Mathison Project Closure Milestone Achievement date 24-Oct-14 Project's Completion Report is available on the website |