Report for February 2015
- Report Date
- February 2015
Susan McKeown (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS083 - AMBER - This project has had some delay due to essential patching work under PPP003 Annual Maintenance project but is still resourced to complete this financial year. The Amber status is due to revised milestones requiring approval.
HRS084 - This project has been started, the brief has been drafted and the kick-off meeting scheduled for w/c March 9.
AP34-025 - RED - UoE staff supporting Supplier completing Proof of concept for introducing validation and testing upgrade process. This work is planned to complete at the end of March. This project to convert the character set and upgrade eRecruitment would not be able to start until the completion of this work.
AP45-063 - This project is scheduled to start in March. The PM and software development resources have already been assigned.
HRSP01 shows as overspent due to pre-planning for project work for eRecruitment and some HESA 14/15 tasks which are being completed ahead of the project starting next year.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP34-025 eRecruitment Upgrade & Character set conversion Funded Planning - April 2015 Delivery - July 2015 RAG Status RED | Plan eRecruitment Supplier is completing a Proof of Concept which will introduce data entry validation into the application and test the upgrade and character set conversion process the University would then complete with the Supplier under this project.
The earliest that planning could commence on this project is late March, when it should be known whether or not the Proof of Concept will be successful.
Dependencies Successful Proof of concept and validation in application and Supplier's availability |
AP45-063 HESA Staff Return 14/15 Compliance Planning -April 2015 Delivery - October 2016 RAG Status GREEN | Plan Project planned to start 30 March 2015. The programme is completing carryover tasks from the HESA 13/14 project as the opportunity arises in Development Services between December 2014 and the start of this project.
Dependencies |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||
HRS083 (AP45-042) Enhancing Employment Removal of HTBN Compliance Milestones
RAG Status AMBER | Report by Morna Findlay for February 2015
Achievements this Period
Issues
Next Steps
| ||||||||||
HRS084 (AP45-042) Enhancing Employment Analysis Compliance
Milestones
Delivery - July 2015
RAG Status GREEN
| Report by Franck Bergeret for February 2015
Achievements this Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Project Code (AP-No) Project Title | Report by Project Manager Project Closure Milestone Achievement date Provide link to the project's Completion Report |
HRS078 (AP34-024) Moving eRecruitment Database to new Infrastructure | Report by Anne Mathison Project Closure Milestone Achievement date 22-Aug-14 Project's Completion Report is available on the website. |
HRS080 (AP34-924) Capture Staff Levels in Oracle HR and Payroll
| Report by Anne Mathison Project Closure Milestone achieved 30-Sep-14 Project's Completion Report |
HRS082 (AP34-022)HR HESA Staff Return 13/14 | Report by Anne Mathison Project Closure Milestone Achievement date 24-Oct-14 Project's Completion Report is available on the website |
AP23-053 Learning Management Funded | Withdrawn November 2014 |