Report for October 2012
- Report Date
- October 2012
Report compiled by Nikki Stuart (IS Apps Programme Manager) for Lindsey Miller, Eilidh Fraser, Liz Welch (Programme Owners) - DRAFT
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
eRecruitment is AMBER to reflect the need to agree a deployment sign off date following a high volume of post launch issues
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP23-053 Staff Development System- Procurement Funded
Planning January 2013 Delivery July 2013 RAG Status GREEN | Plan Start January 2013 with any procurement completed by July 2013
Dependencies Discussions underway with procurement to agree required procurement route and gather basic information for procurement. |
AP23-053 Staff Development- Implementation Funded Planning tbc Delivery tbc RAG Status GREEN
| Plan tbc - will depend on outcome of procurement project
Dependencies Implementation requirements will depend on the outcome of the procurement project. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||
HRS068 (AP01-011) HR Sytem R12 Upgrade
Category: Compliance Milestones
RAG Status GREEN
| Report by Nikki Stuart for October 2012
Achievements in Last Period
Issues
| ||||||||||||
HRS070 (AP90-049 ) Procure and Implement New Recruitment System
Category: Discretionary
Milestones
RAG Status AMBER
| Report by Rhian Davies for September 2012 Achievements in Last Period
Next Steps
AMBER status reflects the need to agree a revised Deployment sign off date. It was not possible to submit agree this until it was clear when the critical issues were likely to be closed out. | ||||||||||||
HRS071 (AP23-006 ) HR HESA Staff Return 12/13
Category: Compliance
Milestones tbc in ToR
RAG Status GREEN | Report by Jill Nicoll for October 2012 Achievements in last period: Project initiated. Initial meeting held with Business Area Manager. Issues It is likely that the same resources from the HR systems team and IS Configuration Teams will be required for this project and also eRecruitment, R12 Upgrade, HR Tax Year End/HR Real Time Information. Next Steps: Terms of Reference (ToR) document to be created.
| ||||||||||||
HRS072 (AP23-005) Oracle HR & Payroll Annual Patching
Category: Compliance
Milestones to be agreed in Brief
RAG Status GREEN
| Report by Anne Mathison for October 2012 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Project Code AP23-007 Project Title HR Real Time Tax Year End 12/13
Compliance | Report by Nikki Stuart This project was withdrawn on 19th October 2012
The deliverables and revised estimated effort for these have been merged with teh Tax Year End Project for the newly named HR & Payroll Annual Maintenance project. Please see the PRICCL log for further details https://www.projects.ed.ac.uk/programme/hr/issues/3
|