Report for January 2013

Report Date
January 2013

 

Nikki Stuart (IS Apps Programme Manager) for Lindsey Miller, Eilidh Fraser, Pamela Blair (Programme Owners) 

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

 

Section One: Programme Commentary, RAG and Resources Update

 

Commentary

HRS070 Implement New Recruitment System - deployment sign off agreed, formal closure to be progressed. 

HRS068 R12 Upgrade for HR and Payroll - deployment sign off agreed, formal closure to be progressed. 

HRS072 HR and Payroll Annual Maintenance - milestones revised as Oracle had not released the security patches as expected. These have now been released and the revised milestones appear acheiveable. 

HRS071 HR HESA Staff Return 12/13 - design milestone achieved and revised estimate remains within budget

HRS073 eRecruitment Phase 1b - new fFunded in-year project initiated. Detailed planning will be undertaken in February. 

 

 

 

 Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary

AP23-053

Staff Development System- Procurement

Funded

 

Planning March 2013

Delivery Dec 2013

RAG Status

GREEN

Plan

agreed that Business Analysis of functional/user requirements will be undertaken in 12/13 with the remainder of the effort now schduled for 13/14.

 

Dependencies

Discussions underway with procurement to agree required procurement route and gather basic information for procurement. 

AP23-053

Staff Development- Implementation

Funded

Planning tbc

Delivery tbc

RAG Status

GREEN

 

Plan

tbc - will depend on outcome of procurement project

 

Dependencies

Implementation requirements will depend on the outcome of the procurement project. 

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

HRS068 (AP01-011)

HR Sytsem R12 Upgrade

 

Category: Compliance

Milestones

 

 

01-Feb-2013Closure
 

RAG Status

GREEN

 

Report by Nikki Stuart for January 2013 

 

Achievements in Last Period

  • Resolution of memory errors issue

  • ongoing discussions with Oracle regarding the sickness absence LIVE issue

  • Deployment sign off achieved

  • Transport Loans Application signed off and deployed to LIVE

  • completion/updates of support documentation

 

Issues 

  • Oracle have not provided resolutions for the service requests relating the sickness absence and V9 history issues. It has been agreed that the programme mananager and Applications support co-ordinator will monitor and if Oracle provide a fix this will be handled through support (unless it is deemed that a project is necessary to implment the changes)
  • APEX Operational documentation and handover has not been completed due to higher priority eFinancials upgrade work. This will be undertaken asap when the required Technology Architect is available. 

 

Next Steps

  • Closure review and sign off

 

 

HRS070 (AP90-049 )

Procure and Implement New Recruitment System

 

Category: Discretionary

 

Milestones

  

01-Feb-2013Closure

 

 

RAG Status

GREEN

 

Report by Nikki Stuart for January 2013

 

Achievements in Last Period

  • Ongoing resolution of remaining LIVE issues with Core
  • Refresh of DEV and TEST from LIVE
  • Preparation for hands-on training
  • BOXI testing
  • Planning for Phase 1b
  • deployment sign off achieved

 

Issues 

  • Core have not delivered resolution for all final LIVE issues. It has been agreed that this should not delay deployment sign off as these issues will be progressed with Core by the HR Systems Team Manager and the HR Programme Manager. 
  • It has not been possible to complete testing of the BOXI universe due to conflicting resources in HR. Acceptance sign off and deployment to LIVE will be progressed under Phase 1b. 

 

Next Steps

  • Closure review and sign off
  • Initiate eRecruitment Phase 1b

  

 

HRS071 (AP23-006 )

HR HESA Staff Return 12/13

 

Category: Compliance

 

Milestones

 

08-Feb-2013System Design sign-off
05-Apr-2013Build sign-off
22-Apr-2013Integration sign-off
22-May-2013Acceptance sign-off
30-May-2013Delivery
19-Jun-2013Delivery sign-off
15-Nov-2013Post-deployment sign-off
13-Dec-2013Closure

 

 

RAG Status

GREEN

Report by Jill Nicoll for January 2013

Achievements in last period:

Business Requirements Document created and approved

It was agreed at the Business Analysis Review meeting that there is a potential to deliver in a phased approach, with the changes to the HR database and application being released ahead of the rest of the deliverables.  This would allow HR more time to input data into the new HR fields.

Four Design stage meetings have been held with the key business stakeholders

The System Design is progressing well

A new Configuration Team member has been recruited to take forward a significant portion of the Build work

A development request form has been submitted to the Configuration Team manager, for another new team member to attend a training course on the new software tool that will be used to redevelop the HESA forms.

Issues

The Systems Designer has a great many other demands on her time, for example recruitment and mentoring of new team members.  This has impacted the time she has had available for project work.  Consequently, the Configuration Team Manager has advised that she should now be bookable only to 56% fte.  This has resulted in a milestone delay to the Design stage, and may have a knock-on impact on subsequent milestones.

Next Steps:

System Design to be completed and approved

Estimates to be reviewed, and project re-planned to reflect any changes

 

HRS072 (AP23-005)

Oracle HR & Payroll Annual Patching

 

Category: Compliance

 

Milestones

 

Target dateTitle
22-Feb-20132 Build TYE, RTI and Security Patches
08-Mar-20132 ASOR TYE, RTI and Security Patches
13-Mar-20132 Deploy TYE, RTI and Security Patches
03-Apr-20132 P60 Live
30-Apr-20133 Build Budget and any RTI Changes
24-May-20133 ASOR Budget and any RTI Changes
05-Jun-20133 Deploy Budget and any RTI Changes
31-Jul-2013Closure

 

 

 

RAG Status

GREEN 

Report by Anne Mathison for December 12 and January 13

Achievements in Last Period

  • Both Clones completed
  • Phase 1 Acceptance Testing had some issues and was signed off late, but was still in time to enable Phase 1 to go LIVE.
  • Phase 1 Family Pack and Auto-Enrolment went LIVE as planned (24-25th Jan-13)

Issues

  • Phase 2 delayed by Oracle
  • Oracle Tax Year End (TYE) patches released 1st Feb, work for Phase 2 re-planned to start 11th Feb

Next Steps

  • Investigation into Phase 2 Tax Year End (TYE), Real Time Information (RTI), P60, JRE and Security Patches
  • Build for Phase 2 TYE, RTI, P60, JRE and Security Patches is planned to be completed
  • Release to Test Phase 2 for TYE, RTI JRE and Security Patches

HRS073

eRecruitment Phase 1b

 

Category: Funded

 

Milestones

TBC

 

 

RAG Status

GREEN 

Report by NIkki Stuart for January 13

 

Achievements in Last Period

  • Planning and gathering requirements
  • Discussions with Core over draft requirements and specifications
  • Project Board approval to initiate project
 

 Issues  

 
  • None

Next Steps

  • User Group to agree requirements
  • detailed planning for Phase 1b (including milestones)
  • draft and agree project brief

 

Section Four: Closed or Withdrawn Projects

 

 

 

 

Project InfoProject Managers Commentary

  

Project Code 

AP23-007

Project Title

 HR Real Time Tax Year End 12/13

 

Compliance

Report by Nikki Stuart

This project was withdrawn on 19th October 2012

 

The deliverables and revised estimated effort for these have been merged with teh Tax Year End Project for the newly named HR & Payroll Annual Maintenance project. 

Please see the PRICCL log for further details 