Report for July 2016 - DRAFT
- Report Date
- July 2016
Susan McKeown (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS089 - GREEN - Project's budget updated and resources booked for rescheduled dates, with delivery due on 28 September HRS090 - GREEN- Progressing to plan HRS091 - RED - Project brief was signed off with revised estimate. RED status reflects that project's budget was reduced by more than 20%.
Resources to 31/7/16
Forward Look for July 2016
Section Two: Projects Not Started
All projects are either in progress or delivered
Project Info | Programme Manager's Commentary |
|
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||
Category: Funded Milestones
RAG Status GREEN
| Report by Susan McKeown for July 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||||||
Category: Compliance Milestones
RAG Status GREEN | Report by Anne Mathison for July 2016Achievements:
Issues
Next Steps
| ||||||||||||||
Working Time Capture and Reporting ( was Enhancing Employment Technical Implementation) Category: Discretionary Milestones
RAG Status RED | Report by Susan Duff for July 2016Achievements in Last Period
Issues
Next Steps
The project Status is RED to reflect the change in deliverables agreed in the now signed off Project Brief which has resulted in a reduction to the budget. The budget reduction and continuing effort into 16/17 has been approved by the Programme Manager and WIS. |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
HRS086 eRecruitment Proof of Concept Category: Discretionary, Funded | Report by Susan McKeown Project Closure Milestone achieved on 25-Aug-15 Project's Completion Report is available on the website. |
HRS085 HESA Staff Return 14/15 Category: Compliance | Report by Anne Mathison Project Closure Milestone achieved on 20-Nov-15 Project's Completion Report is available on the website. |
Category: Funded | Report by Susan McKeown Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website. |
HRS088 HR Transformation: Governance and Planning Category: Compliance | Report by Susan McKeown Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website |
HRS084 Enhancing Employment Analysis Category: Discretionary | Report by Franck Bergeret Project Closure Milestone achieved on 18-Feb-16 Project's Completion Report is available on the website |