Report for February 2013

Report Date
February 2013

 

Nikki Stuart (IS Apps Programme Manager) for Lindsey Miller, Eilidh Fraser, Pamela Blair (Programme Owners)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Commentary

HRS068 - eRecruitment Lessons learned exercise had to be postponed to allow key people to attend an urgent Autoenrolment/Tax Year End Meeting. Due to leave and other commitements this exercise cannot be held until April

HRS070 - Closure delayed  so as not to impact resourcing of HRS072 during critical phase. Closure reschdeuled for end March. 

HRS071 - Lead Developer was lost to HRS072 to undertake critical Autoenrolment work. Project to be replanned. 

HRS072 - Critical issues encountered during Autoenrolment updates, matter was escalated and resolved by Oracle before manual process had to be implemented. Tax Year end and RTI updates planned for LIVE on 10th/11th March

HRS073 - Supplier has started initial developments. Detailed plan to be produced for HR testing of releases and IS Apps development.

HRS074/AP23-053 - Project initiated with planning to formally start in April.

 

 

 

 Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary

AP23-053

Staff Development- Implementation

Funded

Planning tbc

Delivery tbc

RAG Status

GREEN

 

Plan

tbc - will depend on outcome of procurement project

 

Dependencies

Implementation requirements will depend on the outcome of the procurement project. 

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

HRS068 (AP01-011)

HR Sytsem R12 Upgrade

 

Category: Compliance

Milestones

 

 

 
22-Mar-2013Closure

RAG Status

BLUE

 

Report by Nikki Stuart for February 2013 

 

Achievements in Last Period

  • sickness absence issue was resolved by Oracle and the fixes applied to DEV, TEST and LIVE

 

Issues 

  • Closure has been postponed due to the same resources being required to deliver the critical autoenrolment and tex year end deliverables for HRS072 HR & Payroll Annual Maintenance

 

Next Steps

  • Closure review and sign off

 

Project Status is blue as delivery is complete.

 

 

HRS070 (AP90-049 )

Procure and Implement New Recruitment System

 

Category: Discretionary

 

Milestones

  

26-Apr-2013Closure

 

 

RAG Status

BLUE

 

Report by Nikki Stuart for February 2013

 

 

Achievements in Last Period

  • Ongoing resolution of remaining LIVE issues with Core
  • Preparation for hands-on training
  • BOXI testing
  • User Group and Project Board meetings to review and confirm Phase 1b requirements
  • Continued planning for Phase 1b and project initiated

 

Issues 

  • Investigation is still ongoing for outstanding issues relating to notifications. Core and HR are working together to try to replicate this intermittent issue while Core are monitoring the servers/processes. 
  • Closure review meeting had to be cancelled due to a higher priority issue with the autoenrolment process that required key people at both meetings.  Due to leave and other commitments of key project team members, the meeting could not be rescheduled until 10th April. 

 

Next Steps

  • Closure review and sign off 

 

Project Status is blue as delivery is complete.

  

 

HRS071 (AP23-006 )

HR HESA Staff Return 12/13

 

Category: Compliance

 

Milestones

 

10-Apr-2013Build sign-off
22-Apr-2013Integration sign-off
22-May-2013Acceptance sign-off
30-May-2013Delivery
19-Jun-2013Delivery sign-off
15-Nov-2013Post-deployment sign-off
13-Dec-2013Closure

 

 

RAG Status

AMBER  (due to loss of Lead Developer to HRS072)

Report by Jill Nicoll for February 2013

Achievements in last period:

  • System Design completed and approved.
  • Estimates reviewed, with no significant changes.
  • The first new Developer is progressing well with the Build.
  • The second new Developer has been enrolled on the training course on the new software tool that will be used to redevelop the HESA forms.

 

Issues

  • Last month, we reported that the Systems Designer / Lead Developer has a great many other demands on her time,and that her team leader had consequently advised that her booking should be reduced to only 56% fte.  This month, the demands on this key project resource have have continued to increase.  Indeed, issues with project HRS072 have resulted in the complete loss of this key resource for more than a week. 
  • There is currently no indication as to when HRS072 will return the Systems Designer / Lead Developer to this project.  If necessary, the project will be be re-planned, and milestones adjusted, upon her return. 
  • As reported last month:  "It was agreed at the Business Analysis Review meeting that there is a potential to deliver in a phased approach, with the changes to the HR database and application being released ahead of the rest of the deliverables.  This would allow HR more time to input data into the new HR fields."   The above-mentioned loss of the Lead Developer has resulted in a delay to this key project deliverable.  An alternate resource is being sought to complete the abandoned tasks.
  • The project team is still unsure as to how to derive two of the required data elements (ACTSOC and ACEMPFUN). 

 

Next Steps:

  • Project team to resolve the question of how to derive ACTSOC and ACEMPFUN.
  • Business Area Manager to provide the logic required to derive LEVELS.
  • Business Area Manager to provide an initial data mapping from Level 5 Org Unit to CURACCDIS. 
  • PURE system owner to provide initial csv downloads for ECRSTAT and RESAST.
  • Second new developer to attend Apex training course in late March. 
  • The Build is scheduled to progress throughout March. 

HRS072 (AP23-005)

Oracle HR & Payroll Annual Patching

 

Category: Compliance

Milestones

 

Target dateTitle
08-Mar-20132 ASOR TYE, RTI and Security Patches
13-Mar-20132 Deploy TYE, RTI and Security Patches
03-Apr-20132 P60 Live
30-Apr-20133 Build Budget and any RTI Changes
24-May-20133 ASOR Budget and any RTI Changes
05-Jun-20133 Deploy Budget and any RTI Changes
31-Jul-2013Closure

 

RAG Status

Amber 

Report by Anne Mathison for February 13

 

Achievements in Last Period

  • Unplanned Auto-enrolment (AE) work required before TYE - achieved
    • AE progressed through DEV and TEST by 1st March and deployed to LIVE 4th March  
  • P2 TYE and RTI investigation complete
  • P2 TYE and RTI Dev patches complete
  • P2 Security + JRE Patches and Password change Investigation is complete

 

Issues

  1. Unplanned Auto-enrolment work was required as soon as possible and has had to be accommodated before the tight P2 TYE + RTI patches deadlines.

    • This has then reduced the time available for TYE + RTI in Dev and Test

    • Separating out and replanning the P2 Security patches

    • Delaying implementing the P60 work

  2. HR Globals has caused errors when completing patches.

  3. Unplanned TYE +RTI required patch arrived 4-Mar-13 also required for Phase 2 go LIVE - currently being progressed after AE (AE LIVE on 4th March, TYE+RTI to TEST Patches 5th March)

    • Have to accommodate this work through DEV / TEST / LIVE for go Live on 11-12 March

 

Next Steps

  • Release to Test Phase 2 for TYE, and RTI is scheduled for 5th March

  • UAT  for Phase 2 for TYE, and RTI is scheduled for 6-7th March (contingency 8th March am

  • Go Live for Phase 2 for TYE, and RTI is scheduled for 11-12th March, with signoff on 13th March

  • Milestones and estimates to be revised for remaining Phase 2 prices of work

  • P2 P60 to be replanned after 13th March

  • P2 Security + JRE patches an Password change to be replanned after 13th March

 

HRS073

eRecruitment Phase 1b

 

Category: Funded

Milestones

 

22-Feb-2013Planning
22-Feb-2013Analysis (Requirements Gathering and Core Specifications)
29-Mar-2013Build - Priority 1 and Bug Fixes
26-Apr-2013Test - Priority 1 and Bug Fixes
03-May-2013Deployment - Priority 1 and Bug Fixes
10-May-2013Build - Priority 2
07-Jun-2013Test - Priority 2
14-Jun-2013Deployment - Priority 2
28-Jun-2013Closure

 

RAG Status

GREEN 

Report by NIkki Stuart for February 13

 

Achievements in Last Period

  • Planning and gathering requirements
  • Discussions with Core over draft requirements and specifications
  • Project Board approval to initiate project

 

Issues 

  • None

 

Next Steps

  • User Group to agree requirements
  • detailed planning for Phase 1b (including milestones)
  • draft and agree project brief

RS074 (AP23-053)

Staff Development System- Procurement

Funded

 

Milestones

To be planned in April

 

RAG Status

GREEN

Report by NIkki Stuart for February 13

 

Achievements in Last Period

  • Time recording code created in ASTA
  • Draft Project Brief created

 

Issues 

  • N/A

 

Next Steps

  • Planning meetings with HR and other project team 
  • Invitations to Project Board members

 

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

  

Project Code 

AP23-007

Project Title

 HR Real Time Tax Year End 12/13

 

Compliance

Report by Nikki Stuart

This project was withdrawn on 19th October 2012

 

The deliverables and revised estimated effort for these have been merged with teh Tax Year End Project for the newly named HR & Payroll Annual Maintenance project. 

Please see the PRICCL log for further details 

https://www.projects.ed.ac.uk/programme/hr/issues/3