August Programme Report
- Report Date
- August 2017
Morna Findlay (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Commentary
The programme manager considers that overall the programme is GREEN. The start date for the Tomcat end of life project is yet to be agreed but IS are confident that it can be scheduled at an appropriate time.
Risk - Erecruitment Licencing - NCA required
The e-recruitment contract needs to be updated by October 2017. The original 5 year contract concludes in October and any extension for a further year must be arranged by October. An extension would be done as a Non-Competitive Action (NCA) and this is essential to be licensed to continue using eRecruitment. HRS resources are currently working on extending this contract.
Projects in Progress: summary
HRS092 - GREEN
Forward Look for August 2017


Resources to 01/09/2017

Section Two: Projects Not Started
There are no approved projects planned to this month. The following projects will start later in the year.
| AP17-18: APEX Tomcat 7 End of Life |
| AP17-18: HESA Staff Return 17/18 |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||
|
HRS092 (AP67-034) HESA Staff Return 16/17 Category : Core-funded Compliance Milestones
RAG Status GREEN |
Report by Anne Mathison for August 2017AchievementsNo action for IS since the Finance cost centre file was loaded. HR will run the final extract in Live on 30-Aug Issues
Next Steps
Project has a RAG status of GREEN
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
Working Time Capture and Reporting ( was Enhancing Employment Technical Implementation) |
Closure approved July 2017 |