Commentary

HRS070 Implement New Recruitment System - AMBER status reflects high volume of post launch feedback and need to agree revised deployment date. 

HRS068 Oracle HRMS R12 Upgrade - AMBER status reflects need to replan milestones. Deployment sign off has been scheduled for the early January. 

HRS072 HR and Payroll Annual Maintenance - AMBER status reflects emerging issues with DEV clone. 

 

 

 

 Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary

AP23-053

Staff Development System- Procurement

Funded

 

Planning January 2013

Delivery July 2013

RAG Status

GREEN

Plan

Start January 2013 with any procurement completed by July 2013

 

Dependencies

Discussions underway with procurement to agree required procurement route and gather basic information for procurement. 

AP23-053

Staff Development- Implementation

Funded

Planning tbc

Delivery tbc

RAG Status

GREEN

 

Plan

tbc - will depend on outcome of procurement project

 

Dependencies

Implementation requirements will depend on the outcome of the procurement project. 

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

HRS068 (AP01-011)

HR Sytem R12 Upgrade

 

Category: Compliance

Milestones

 

Milestone

Planned Date

Acceptance - Transport Loans APEX Application

30-Nov-2012

Deployment

07-Dec-2012

Closure

17-Dec-2012

 

 

RAG Status

AMBER

 

Report by Nikki Stuart for November 2012 

 
Achievements in Last Period
  • Project has provided extended support for R12, particularly to cover the first payroll run
  • Investgated and Resolved post upgrade issues
  • Build for Transport Loans Application completed
  • system documentation including Disaster Recovery and System description completed
  • Disaster Recovery testing succesful
  • Handover to Technology Management comeplet

 

Issues 
  • The project team are now all involved in high priority HR & Payroll Annual Maintenance or HESA project work. This along with continuing issues with the eRecruitment system/interfaces impacted on the teams ability to complete out all tasks. Milestones now need to be revised. 
 Next Steps
  • Resolve final post upgrade issues
  • Deliver TRansport Loans Application to TEST
  • Complete final post upgrade tasks that were agreed during TEST as being lower priority
  • Deployment sign off 

 

AMBER status reflects need to replan milestones.

 

HRS070 (AP90-049 )

Procure and Implement New Recruitment System

 

Category: Discretionary

 

Milestones

 

 

 

 

RAG Status

AMBER

 

Report by Rhian Davies for November 2012 

 

Achievements in Last Period
  • Resolution of live issues with Core and HR configuration
  • Resolution of live issues with the successful applicant interface
  • Discussions with Core and IS Apps on Mod Security
  • Continued engagement with Core
Issues 
  • The high volume of post launch issues have continued. It has therefore not been possible to agree a revised deployment sign off date. This will now be scheduled for early January. 

 

Next Steps
  • Review BOXI Universe and Update Objects
  • Replan IDM/HR Interface Testing
  • Deployment sign off 
  • Planning for Phase 2 project

 

AMBER status reflects the need to agree a revised Deployment sign off date. It was not possible to submit agree this until it was clear when the critical issues were likely to be closed out. 

 

 

 
 

HRS071 (AP23-006 )

HR HESA Staff Return 12/13

 

Category: Compliance

 

Milestones

 

19-Dec-2012Business Analysis sign-off
30-Jan-2013System Design sign-off
05-Apr-2013Build sign-off
22-Apr-2013Integration sign-off
22-May-2013Acceptance sign-off
30-May-2013Delivery
19-Jun-2013Delivery sign-off
15-Nov-2013Post-deployment sign-off
13-Dec-2013Closure

 

 

RAG Status

GREEN

Report by Jill Nicoll for November 2012

Achievements in last period:

Terms of Reference document created and approved

Project planned and resources requested

Resources assigned for Business Analysis and System Design stages 

Issues

The Business Area Manager is a key project resource, particularly throughout the Business Analysis and System Design stages.  We are concerned that there are a great many other demands on her time, for example for eRecruitment and Annual Maintenance.  This may impact the time she will have available to support these critical early stages of HR HESA.  Delays in the early stages would also have a knock-on impact on subsequent milestones.

Next Steps:

Business Requirements Document to be created

 

HRS072 (AP23-005)

Oracle HR & Payroll Annual Patching

 

Category: Compliance

 

Milestones

 

07-Dec-2012Refresh HR Dev from Live
14-Dec-20121 Build Family Pack and Auto-Enrolment
14-Dec-2012Refresh HR Test from Live
17-Jan-20131 ASOR Family Pack and Auto-Enrolment
28-Jan-20131 Deploy Family Pack and Auto-Enrolment
11-Feb-20132 Build TYE, RTI and Security Patches
28-Feb-20132 ASOR TYE, RTI and Security Patches
06-Mar-20132 Deploy TYE, RTI and Security Patches
30-Apr-20133 Build Budget and any RTI Changes
24-May-20133 ASOR Budget and any RTI Changes
05-Jun-20133 Deploy Budget and any RTI Changes
31-Jul-2013Closure

 

 

 

RAG Status

AMBER due to error with Oracle on first CLONE since R12

 

Report by Anne Mathison for November 2012

Achievements in Last Period

  • Brief agreed
  • Resourcing finalised
  • Planning milestone approved

Issues

  • Clone issue raised with Oracle (4/12/12). If the Clone issue is not resolved by 7/12/12, all following steps will be impacted. (Issue 5 raised)

Next Steps

Assuming clone issue is resolved by 7/12/12:  

  • Clone copies to be completed in DEV and TEST
  • Investigation into Phase 1 Family Pack and Auto-Enrolment work
  • Phase 1 Family Pack and Auto-Enrolment Build completed
  • Acceptance testing for Phase 1 Family Pack and Auto-Enrolment signedf by 17-Jan-2013
  • Deployed to LIVE 24-25th Jan-2013

 

Section Four: Closed or Withdrawn Projects

 

 

 

 

Project InfoProject Managers Commentary

  

Project Code 

AP23-007

Project Title

 HR Real Time Tax Year End 12/13

 

Compliance

Report by Nikki Stuart

This project was withdrawn on 19th October 2012

 

The deliverables and revised estimated effort for these have been merged with teh Tax Year End Project for the newly named HR & Payroll Annual Maintenance project. 

Please see the PRICCL log for further details 

https://www.projects.ed.ac.uk/programme/hr/issues/3