Report for October 2018
- Report Date
- October 2018
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Susan McLaren (HRS Programme Owner).
Section One: Programme Commentary, RAG and Resources Update
Commentary
During October, work progressed well in both projects:
- HRS094 HESA Staff Return 17/18 has reached the final delivery and closure phase.
- A delay in the delivery of the business HRS096 GDPR Updates for eRecruitment will cause a delay in the start of the implementation. This is compounded with need to fit the implementation with the system availability to support the monthly run. This means the delivery will move to January. This change results in project reporting a AMBER status.
The overall USG Other Programme status is GREEN.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - October 2018
Resources to end October 2018
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
---|---|
HESA Staff Return 18/19 | To be started in February 2019. |
Section Three: Projects in Progress
Project Info |
Project Managers Commentary | ||||||||||||||||
HRS094 HESA Staff Return 17/18 Milestones
RAG StatusGREEN |
Report by Anne Mathison for October 2018Achievements
Issues
Next Steps
|
||||||||||||||||
HRS096 GDPR Updates for eRecruitment Milestones
RAG StatusRED |
Report by Ken Miller for October 2018Achievements this Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
No Project has been closed this session yet