Report for April 2013
- Report Date
- April 2013
Nikki Stuart (IS Apps Programme Manager) for Lindsey Miller, Eilidh Fraser, Gordon Forbes (Programme Owners)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS068 - eRecruitment Lessons learned exercise held with the Project Team. Similar exercise conducted with User Group and feedback requested from the Project Board and Core. Final Report delayed due to high volume of data and Project Managers conflicting priorities.
HRS070 - Draft closure report created. Closure now expected mid May.
HRS071 - HESA testing is now underway. An initial issue with the additional questions set up in eRecruitment has now been resolved. Changes to scope have impacted the project, however, the project still remains GREEN and on track to meet milestones.
HRS072 - RED as the issue with the P60 reports is still with Oracle, the priority for this has been increased and daily updates have been requested. Additional patches have been provided by Oracle impacting on the overall project estimate.
HRS073 - Project GREEN again and has been replanned following last months issues. Revised plan has been approved by the Board and communications issued to Users. Good progress is being made with testing.
HRS074 - Project Planning underway with the first Project Team meeting arranged for 9th May.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP23-053 Staff Development- Implementation Funded Planning tbc Delivery tbc RAG Status GREEN
| Plan tbc - will depend on outcome of procurement project
Dependencies Implementation requirements will depend on the outcome of the procurement project. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||
HRS068 (AP01-011) HR Sytsem R12 Upgrade
Category: Compliance Milestones
RAG Status BLUE
| Report by Nikki Stuart for April 2013
Achievements in Last Period
Issues
Project Status is blue as delivery is complete.
| ||||||||||||||
HRS070 (AP90-049 ) Procure and Implement New Recruitment System
Category: Discretionary
Milestones
RAG Status BLUE
| Report by Nikki Stuart for April 2013
Achievements in Last Period
Next Steps
Project Status is blue as delivery is complete.
| ||||||||||||||
HRS071 (AP23-006 ) HR HESA Staff Return 12/13
Category: Compliance
Milestones
RAG Status GREEN | Report by Jill Nicoll for April 2013 Achievements in last period: Build (excluding APEX forms):
The Business Area Manager provided the full business logic required to derive LEVELS. This logic will be applied during the UAT stage. Developers attended Oracle APEX training. Second developer has built APEX forms. These are currently in Peer Testing. Issues: An issue was identified with the TEST eRecruitment application resulting from the updates for the eRecruitment Phase 1b project. This has resulted in an ongoing delay in setting up the applicants required for UAT testing. Scope was added to the project when HESA released requirement changes on 30th April. These changes will impact the HR extract to the HESA tables, and will require the Designer's time to assess and specify the resulting code changes. However the Desgner is booked for only one day per week during the UAT stage, to support the developers and complete the System documentation. Further, the Designer has been over-booked by project HRS072 for the same period. PM to request as much additional Desgner booking as possible, to fit around HRS072 bookings. There has been a 2-day delay to the Test deployment of the Apex forms. This is due to a high number of Peer testing feedback items. The revised target date for release for UAT is Weds 8th May. The developer effort recorded against the Build stage is 16 days over the Build estimate. This overspend has been compensated for by reducing the Project Management and QA budgets for the project. As a result, the overall project budget has not increased. Next Steps:
Core to fix Test eRecruitment. Business testers to set up test applicants. Apex forms to be released for UAT. UAT testing to be completed and signed off. All project code to be deployed to Live. | ||||||||||||||
Oracle HR & Payroll Annual Patching
Category: Compliance Milestones
RAG Status RED | Report by Anne Mathison for April 2013Major issue this month is the resolution of the P60 which is legally required for end on May. The number of urgent patches and issues have required significantly more time than was expected to process and patch Achievements in Last Period -
Issues
Next Steps
| ||||||||||||||
HRS073 eRecruitment Phase 1b
Category: Funded Milestones
RAG Status GREEN | Report by NIkki Stuart for April 13
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||
RS074 (AP23-053) Staff Development System- Procurement Funded
Milestones
Remaining Milestones still to be planned
RAG Status GREEN | Report by NIkki Stuart for April 13 Achievements in Last Period
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Project Code AP23-007 Project Title HR Real Time Tax Year End 12/13
Compliance | Report by Nikki Stuart This project was withdrawn on 19th October 2012
The deliverables and revised estimated effort for these have been merged with teh Tax Year End Project for the newly named HR & Payroll Annual Maintenance project. Please see the PRICCL log for further details https://www.projects.ed.ac.uk/programme/hr/issues/3
|