Report for November 2019

Report Date
November 2019

Section One: Programme Commentary, RAG and Resources Update

Commentary

  • The overall status of the HRS Programme is Green , with both the HESA project and the GDPR project closing as planned.
  • The underspend in this year's HESA project was used to cover the unplanned effort required to complete the GDPR project.

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

Forward Look - November 2019

 

Resources to end November 2019

 

Section Two: Projects Not Started 

Project Info Programme Manager's Commentary 
AP90-033 HESA Staff Return 19/20

This project is not due to be started until March 2020

 

Section Three: Projects in Progress

Project Info

Project Managers Commentary

 

HRS096 GDPR Updates for eRecruitment

 

Milestones :

  • None
RAG Status :

BLUE

 

Report by Ken Miller for November 2019

Achievements this Period

  • Complete controlled closure saving the proposed plan, estimates and existing scripts on the project web site and K\: drive so the solution could be implemented if required.
  • Project closed.

Issues

  • None

Next Steps

  • None

Project RAG status of BLUE

HRS097 HR/HESA Staff Return 2018/19

 

Milestones :

  • None
RAG Status :

BLUE

 

Report by Anne Mathison for November 2019

Achievements

  • Closure report prepared
  • Closure report signed off
  • Project closed 6-Nov

Issues

  • None

Next Steps

  • None 

Project RAG status of BLUE  

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

HRS097 HR/HESA Staff Return 2018/19

This project closed on 6 November 2019

HRS096 GDPR Updates for eRecruitment

This project closed on 22 November 2019

 

 

AttachmentSize
Image icon resources_nov_19.png25.58 KB
Image icon forward_look_nov_19.png29.96 KB
Programme Status
Has formal escalation taken place?
No