Report for November 2019
- Report Date
- November 2019
Section One: Programme Commentary, RAG and Resources Update
Commentary
- The overall status of the HRS Programme is Green , with both the HESA project and the GDPR project closing as planned.
- The underspend in this year's HESA project was used to cover the unplanned effort required to complete the GDPR project.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - November 2019
Resources to end November 2019
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
---|---|
AP90-033 HESA Staff Return 19/20 |
This project is not due to be started until March 2020 |
Section Three: Projects in Progress
Project Info |
Project Managers Commentary |
HRS096 GDPR Updates for eRecruitment Milestones :
RAG Status :BLUE
|
Report by Ken Miller for November 2019Achievements this Period
Issues
Next Steps
Project RAG status of BLUE |
HRS097 HR/HESA Staff Return 2018/19
Milestones :
RAG Status :BLUE
|
Report by Anne Mathison for November 2019Achievements
Issues
Next Steps
Project RAG status of BLUE |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
---|---|
This project closed on 6 November 2019 |
|
HRS096 GDPR Updates for eRecruitment |
This project closed on 22 November 2019 |