Report for December 2019
- Report Date
- December 2019
Section One: Programme Commentary, RAG and Resources Update
Commentary
- With no active projects in this month, there is no project activity to report.
- The 3 year planning for this programme was completed in December
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - December 2019
Resources to end December 2019
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
---|---|
AP90-033 HESA Staff Return 19/20 |
This project is not due to be started until March 2020 |
Section Three: Projects in Progress
Project Info |
Project Managers Commentary |
None open in this period |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
---|---|
This project closed on 6 November 2019 |
|
HRS096 GDPR Updates for eRecruitment |
This project closed on 22 November 2019 |
Attachment | Size |
---|---|
resources_dec_19.png | 25.75 KB |
forward_look_dec_19.png | 41.84 KB |