Report for December 2019

Report Date
December 2019

Section One: Programme Commentary, RAG and Resources Update

Commentary

  • With no active projects in this month, there is no project activity to report.
  • The 3 year planning for this programme was completed in December

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

Forward Look - December 2019

Resources to end December 2019

Section Two: Projects Not Started 

Project Info Programme Manager's Commentary 
AP90-033 HESA Staff Return 19/20

This project is not due to be started until March 2020

 

Section Three: Projects in Progress

Project Info

Project Managers Commentary
  None open in this period

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

HRS097 HR/HESA Staff Return 2018/19

This project closed on 6 November 2019

HRS096 GDPR Updates for eRecruitment

This project closed on 22 November 2019

 

 

AttachmentSize
Image icon resources_dec_19.png25.75 KB
Image icon forward_look_dec_19.png41.84 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No