Report for January 2020
- Report Date
- January 2020
Section One: Programme Commentary, RAG and Resources Update
Commentary
- With no active projects in this month, there is no project activity to report.
- The programme is initiating the HESA project in February
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - January 2020
Resources to end January 2020
Programme management is showing overbudget but this is Initiation effort for the HESA 19/20 project and this effort will be moved to that project once it is opened.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
---|---|
AP90-033 HESA Staff Return 19/20 |
This project is being initiated on February |
Section Three: Projects in Progress
Project Info |
Project Managers Commentary |
None open in this period |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
---|---|
This project closed on 6 November 2019 |
|
HRS096 GDPR Updates for eRecruitment |
This project closed on 22 November 2019 |
Attachment | Size |
---|---|
resources_jan_20.png | 25.38 KB |
forward_look_jan_20.png | 38.53 KB |