Report for May 2013
- Report Date
- May 2013
Nikki Stuart (IS Apps Programme Manager) for Lindsey Miller, Eilidh Fraser, Gordon Forbes (Programme Owners)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
HRS068 - Project closed 24-May-13
HRS070 - Closure delayed due to holidays. Closure now planned for mid June.
HRS071 - Project set to GREEN as everything apart from eRecruitment Interace will be live by 14th June
HRS072 - Project back to GREEN as the P60 was printed and delivered before the end of May. Now back to more RTI patches.
HRS073 - Project GREEN again and has been replanned following last months issues. Revised plan has been approved by the Board and communications issued to Users. Good progress is being made with testing.
HRS074 - Project AMBER due to risk to funding and unclear business requirements.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP23-053 Staff Development- Implementation Funded Planning tbc Delivery tbc RAG Status GREEN
| Plan tbc - will depend on outcome of procurement project. Current plan suggests that the procurement would not be complete until April 2014 at the earliest.
Dependencies Implementation requirements will depend on the outcome of the procurement project. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||
HRS070 (AP90-049 ) Procure and Implement New Recruitment System
Category: Discretionary
Milestones
RAG Status BLUE | Report by Nikki Stuart for May 2013
Achievements in Last Period
Next Steps
Project Status is blue as delivery is complete.
| ||||||||||
HRS071 (AP23-006 ) HR HESA Staff Return 12/13
Category: Compliance
Milestones
RAG Status GREEN
| Report by Jill Nicoll for May 2013 Achievements in last period: UAT sign-off confirmed for HR database and application changes. HR database and application changes deployed to Live. UAT sign-off confirmed for HESA Apex forms and BOXI Universes. UAT sign-off confirmed for eRecruitment extract. Issues: By the morning of the UAT sign-off meeting, not all of the UAT testing had been completed. This resulted in delays to the Acceptance sign-off, Delivery, and Delivery sign-off milestones. An additional deployment delay will also be required, for the eRecruitment extract changes only. This is to allow more time for HR to load the new ACTSOC values into eRecruitment. Next Steps: Final UAT sign-off for HESA changes to be confirmed. HESA changes to be deployed to Live. HR to load new ACTSOC values, and make the new ACTSOC fields "active", in eRecruitment. eRecruitment extract to be deployed to Live. Deployment sign-off to be confirmed. | ||||||||||
Oracle HR & Payroll Annual Patching
Category: Compliance Milestones
RAG Status GREEN | Report by Anne Mathison for May 2013Achievements in Last Period -
Issues
Next Steps
| ||||||||||
HRS073 eRecruitment Phase 1b
Category: Funded Milestones
RAG Status GREEN
| Report by NIkki Stuart for May 13
Achievements in Last Period
Issues
Next Steps
| ||||||||||
RS074 (AP23-053) Staff Development System- Procurement Funded
Milestones
Remaining Milestones still to be planned
RAG Status AMBER
| Report by NIkki Stuart for May 2013 Achievement this Reporting Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Project Code AP23-007 Project Title HR Real Time Tax Year End 12/13
Compliance
| Report by Nikki Stuart This project was withdrawn on 19th October 2012
The deliverables and revised estimated effort for these have been merged with the Tax Year End Project for the newly named HR & Payroll Annual Maintenance project. Please see the PRICCL log for further details https://www.projects.ed.ac.uk/programme/hr/issues/3
|
Project Code HRS068 (AP01-011) HR System R12 Upgrade
Category: Compliance
| Report by Nikki Stuart This project was closed on 24th May 2013 |
Section Five: New Approved Projects from 13/14 Annual Plan
Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.
Project Info | Project Managers Commentary |
AP34-XXX eRecruitment Phase 2 (Redeployment and Talent Pool) Funded Planning - August 2013 Delivery - January 2014 RAG Status
|
Plan Business Consultations are running through to end July. This project cannot start until clear agreement has been reached on how to proceed.
Dependencies Business Consultations complete and policy decisions agreed with all stakeholders
|
AP34-XXX HR & Payroll Annual Maintenance 13/14 Compliance Planning - October 2013 Delivery - May 2014 RAG Status
| Plan Real Time Information (RTI) and Autoenrolement, introduced in 12/13, have potentially altered the normal plan and approach for this project. It may be more sensible to start this project earlier should the start of the RTI submissions to HRMC require immediate updates.
Dependencies Start and end dates will depend on what Oracle release patches and how urgently they need to be applied to our system. |
AP34-XXX HR & Payroll Reporting Tool Compliance Planning - December 2013 (could be earlier?) Delivery - July 2013 RAG Status | Plan
Dependencies Ongoing work for eRecruitment and HESA testing will impact HR's ability to input to this project. Pensions and Payroll departments cannot undertake any work on this in August 2013 due to leave commitments. depending on when the Annual Maintenance project starts this could impact availability of business resources. |
AP34-XXX HESA Staff Return 13/14 Compliance Planning - November 2013 Delivery - September 2014 RAG Status
| Plan
Dependencies HESA have indicated that as the changes for 12/13 were substantail that changes for 13/14 will be minimal. This will not be certain until HESA release details of any required changes. |