Report for May 2020
- Report Date
- May 2020
Section One: Programme Commentary, RAG and Resources Update
Commentary
- The programme's current status is GREEN, with HESA project progressing to plan.
- The programme's budget has been reduced following the re-estimation of HRS098 and return of unallocated programme contingency to the portfolio.
- The programme manager completed a review of open programme risks in January 2020 and has requested confirmation from People and Money (P&M) programme that risks relating to current Oracle HR & Payroll and eRecruitment systems are fully transferred to the P&M programme and therefore can be closed for the HRS programme.
- The programme may be affected by the Coronavirus risk as noted at Portfolio level.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - May 2020
Resources to end May 2020
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
---|---|
All project now in progress or delivered |
Section Three: Projects in Progress
Project Info |
Project Managers Commentary | ||||||||||||||||
HRS098 HESA Staff Return 2019/20
Milestones :
RAG Status :GREEN |
Report by Anne Mathison for May 2020Achievements
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
---|---|
This project closed on 6 November 2019 |
|
HRS096 GDPR Updates for eRecruitment |
This project closed on 22 November 2019 |
Attachment | Size |
---|---|
forward_look_may_20.png | 34.77 KB |
resources_may_20.png | 25.96 KB |