Report for November 2020

Report Date
November 2020

Section One: Programme Commentary, RAG and Resources Update

Commentary

  • The programme's status is GREEN with the archive successfully completed for the HESA staff Return 19/20
  • A risk regarding HESA for 20/21 has been raised with Director of HR Services which will be discussed at the next programme meeting
  • The programme may be affected by the Coronavirus risk as noted at Portfolio level

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

Forward Look - November 2020

Resources to end November 2020

Section Two: Projects Not Started 

 

Project Info Programme Manager's Commentary
HRS099 HESA Staff Return 2020/21 Start TBC - working assumption start March 2021

 

Section Three: Projects in Progress

Project Info

Project Managers Commentary
HRS098 HESA Staff Return 2019/20

 

Milestones :

Milestone Due Date
Close (MAJOR)  04-Dec-2020
RAG Status :

GREEN

Report by Anne Mathison for November 2020

Achievements

  • Any HESA activities agreed before  the final sign off deadline 
  • Final Submission Milestone achieved and signed off
  • Completed  all 19-20 Archives in November for DEV, TEST and LIVE
  • Prepare Closure Report

Issues

  • No issues

Next Steps

  • Circulate and sign off  Closure Report
  • Close Project

RAG status GREEN

 

Section Four: Closed or Withdrawn Projects

 

 

Project Info Project Managers Commentary
HRS097 HR/HESA Staff Return 2018/19

This project closed on 6 November 2019

HRS096 GDPR Updates for eRecruitment

This project closed on 22 November 2019

 

 

AttachmentSize
Image icon resource_nov_2020.png21.4 KB
Image icon forward_look_nov_2020.png26.59 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No