Report for December 2020

Report Date
December 2020

Section One: Programme Commentary, RAG and Resources Update

Commentary

  • The programme's status is GREEN with the successful delivery and closure of the HESA staff Return 19/20.
  • A risk regarding HESA for 20/21 has been raised with Director of HR Services was discussed at the last programme meeting. The Director will determine when the HESA Hub will be delivered by P&M/Inoapps and whether this can be brought forward from the current plan of delivery in phase 3. As contingency now, this programme will retain in the plan to have HRS099 start as planned in March. 
  • The programme may be affected by the Coronavirus risk as noted at Portfolio level

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

Forward Look - December 2020

Resources to end December 2020

Section Two: Projects Not Started 

 

Project Info Programme Manager's Commentary
HRS099 HESA Staff Return 2020/21 Start TBC - working assumption start March 2021

Section Three: Projects in Progress

Project Info 

 Project Managers Commentary

 

HRS098 HESA Staff Return 2019/20

 

Milestones :

  • No milestones remain
RAG Status :

BLUE

 

 Monthly Project Report by Anne Mathison

Achievements

  • Circulated and signed off  Closure Report
  • Closed Project

Issues

  • No issues

Next Steps

  • No further steps

 

Section Four: Closed or Withdrawn Projects

 

 

Project Info Project Managers Commentary
HRS097 HR/HESA Staff Return 2018/19

This project closed on 6 November 2019

HRS096 GDPR Updates for eRecruitment

This project closed on 22 November 2019

 

HRS098 HESA Staff Return 2019/20

This project closed on 4 December 2020

 