MARCH 2018
- Report Date
- March 2018
Report by Mark Hay, MVMBUS Programme Manager.
for Jim Nisbet (MVMBUS Programme Owner.
CMVM Head of IT (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)
Distribution:
- Campus / Deanery meetings.
- College Operations Group (COG) meeting
- Excerpts taken into CSG report.
Section One: Programme Commentary, RAG and Resources Update
Programme Managers Commentary
MVM508 [CMVM Staff and Visitor print consolidation]
The issues around the networking at Chancellors are now being investigated and identification of possible issues is closer. Continued dialogue is taking place to seek movement on the matter. This is the primary reason the project is amber .
MVM509 [Implementation of Vet Practice Management System]
The project continues. There are still some concerns over the Tristan element but actions are being sought and continued involvement of the relevant parties ensure that the matter is being handled at the appropriate level.
MVM522 [MVM Business Process Review for SharePoint Delivery]
Project brief now approved by stakeholders . Considerable progress is now being made. The project remains at amber due to time constraints.
MVM523 [Pilot project for WHO's OFF online Staff Leave Management]
No reporting required.
MVM501[Lease standardisation and tenant IT service entitlement]
Now moved to closed (see below)
MVM525 [Procurement of a Vendor Neutral Archiving (VNA) System for the Vet School]
Progress is being made and the project is moving to approval stage.
Forward Look - March 2017
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary | |
---|---|---|
MVM502 |
CMVM College IT communications strategy | This project will be placed under review in Q2 2018 |
MVM503 | CMVM IT Finance costs portfolio | This project will be placed under review in Q2 2018 |
MVM507 | Risk, Business Continuity and Disaster Recovery | Linked primarily CIS002 - Oct 2016 - MVM518 - This project will be placed under review in Q2 2018 |
MVM510 | CMVM Digital literacy staff and student development | This project will be placed under review in Q2 2018 |
MVM514 | CMVM Bioquarter Infrastructure & IT Services Development | This project will be placed under review in Q2 2018 |
MVM516 | IS - Honours Project Portal move to central resources | Currently at the review stage by Programme Manager |
Active Projects |
[MVM508]: CMVM Staff and Visitor print consolidation Report by Sarfraz Mohammed Achieved
Issues
Next Steps
|
[MVM509] Implementation of Vet Practice Management System Report by Colin Watt Achievements in Last Period
Issues
Next Steps
|
[MVM522] MVM Business Process Review for SharePoint Delivery Report by Paul De'Ath Achievements
Issues
Next Steps
|
[MVM523]Pilot project for WHO's OFF online Staff Leave Management Report by Jens Brincker Project currently suspended - No report required |
[MVM525] Procurement of a Vendor Neutral Archiving (VNA) System for the Vet School Report by Megan Graham Achievements This Period
Issues
Next Steps
|
Section Four: Closed, Withdrawn or Suspended Projects (For legacy information)
CLOSED
Project Info | Project Managers Commentary |
---|---|
MVM009 | Closed |
MVM512 | Closed |
MVM513 | Closed |
MVM519 | Closed |
MVM501 | Closed |
WITHDRAWN
Project Info | Programme Managers comments |
---|---|
[MVM511] CMVM College WWW Presence development | Withdrawn |
[MVM717] CMVM Developing the CMVM Intranet environment | Withdrawn |
[MVM521] Scientific Linux 7 (SL7) - Psychiatry | Withdrawn |
[MVM504] CMVM Digitisation of paper records | Withdrawn |
[MVM506] CMVM Reporting and data intelligence | Withdrawn |
[MVM503] CMVM Corporate Business Services review | Withdrawn |
SUSPENDED
Project Info | Programme Managers comments |
---|---|
[MVM523] Pilot project for WHO's OFF online Staff Leave Management | Project suspended until July 2018 |