Report for October 2021

Report Date
October 2021

 

Report by Muriel Mewissen on behalf of Mark Hay (MVMBus Programme Manager), for Jim Nisbet (Programme Owner) and Sheila Fraser (MVM Portfolio Manager)

 
Distribution:
  • Campus / Deanery meetings.
  • College Operations Group (COG) meeting
  • Excerpts taken into CSG report.

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During October, ongoing projects continue to progress well. 

The overall status of the MVMBus programme is GREEN.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Forward Look - October 2021

 

Section Two: Projects Not Started

Project Info Notes
MVM507 Risk, Business Continuity and Disaster Recovery Agreement that MVM507 is to be delayed until next year (September 2021)  following mid year review at Programme Review Monthly Meeting - February 2021.

 

Section Three: Projects in Progress

MVM528 Provet Optimisation - RAG Status: SUSPENDED

Report by Muriel Mewissen

Achievements in last period

Next Steps

  • Review suspension in October 2021

MVM529 Enabling CMVM Rooms for Hybrid Meetings - RAG Status: GREEN

Report by Sheila Fraser

Achievements in last period

  • QMRI rooms Peter Levine & Weiderlight rooms completed, and in use for hybrid meetings. Mary Kinross room updated (small item to improve is yet to be delivered, but room is functional as-is using the in-room PC). Auditorium also functional but requiring one further update. In-room guides completed for all QMRI & Chancellor's Building Rooms.
  • First hybrid College Operations Group held (CB Boardroom) and first hybrid College Strategy Group meeting held (QMRI, Mary Kinross).
  • Email to QMRI drafted to be shared by Building Manager.

Issues

  • Request to HP to re-invoice with zero VAT has still not been actioned, despite chasing of HP resulting in delay in payment.

Next Steps

  • Complete work in: QMRI (Auditorium & Peter Levine), Hugh Robson G6 (control panel shortage), and SCRM Seminar Room power supply and control programming.
  • Update summary list of rooms for College reference with information on the equipment available.

MVM530 Cataloguing CMVM IS Services - RAG Status: AMBER

Report by Myles Ewen

Achievements in last period

  • 1st revision of (23 potential) Teaching & Learning services completed (with Alan Gilchrist).
  • 2 further workshop session carried out with Sheila and campus leads (66% potential non-T&L services now reviewed).
  • 3 further workshops scheduled.

Issues

  • Lack of resource availability within the ITIL team delaying decisions, direction and work on:
    • Submission/request process for new service entries into the IS Service Catalogue.
    • How CMVM IT Services will be differentiated and viewed/filtered in the IS Service Catalogue.
  • PM will be seconded fully out of CMVM to assist CSG Head of IT from Jan 4th - end of Aug 2022.

Next Steps

  • Run further workshops.
  • Merge T&L services into master catalogue. 
  • Produce complete 1st draft CMVM service list (ITIL team engagement is required to advance beyond this point).

MVM531 CMVM Study Spaces - 2021 - RAG Status: GREEN

Report by Sheila Fraser

Achievements in last period

  • MEC: check-in desk bookings enabled for study in Computer Lab 1, when it is not being used for teaching, with QR codes now on 15 of the desks. Bookings can still be made via the Timetabling team for teaching. Positive feedback received from a student who was using the Group Study room on the re-opening of Computer Lab 1.

Issues

  • Lauriston Place: Dentistry team still require to maintain 2m distancing as they are within an NHS Lothian building, meaning no further study spaces can be opened up. The QR codes are yet to be replaced for check-in/out.
  • Chancellor's Building: rooms with study spaces (e.g. Seminar Rooms) are fully booked out for teaching: no study space will be available so the rooms do not require to be set up as dual-use rooms.
  • Kennedy Tower: will not open until Semester 2: no study space will be available so the room does not require to be set up currently.

Next Steps

  • Lauriston Place: Complete QR code swap for Dentistry

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's commentary
N/A No project has been complete this session.

 

Section Five: Programme Meeting Minutes

Date Comments
13 October 2021 Programme Review Monthly Meeting - October 2021
16 September 2021 Programme Review Monthly Meeting - September 2021
13 July 2021 Programme Review Monthly Meeting - July 2021
3 June 2021 Programme Review Monthly Meeting - June 2021
11 May 2021 Programme Review Monthly Meeting - May 2021
21 April 2021 Programme Review Monthly Meeting - April 2021
3 March 2021 Programme Review Monthly Meeting - March 2021
3 February 2021 Programme Review Monthly Meeting - February 2021
12 January 2021 Programme Review Monthly Meeting - January 2021
16 December 2020 Programme Review Monthly Meeting - November & December 2020
11 November 2020 Programme Review Monthly Meeting - October 2020
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No